Where: Winston-Salem Northern Beltway, Eastern Half; US 52 near NC 65 near Stanleyville to I-74 east of Winston-Salem, Forsyth CountyLength: 17.1 Miles***Needed: Construct New Freeway (Partially completed)Work Started: December 10, 2014First section, US 421 to US 158 opened Sept. 5, 2020Second section, US 158 to US 311 opened Dec. 23, 2020Third section, US 311 to NC 66 opened Nov. 7, 2022Fourth Section: NC 66 to US 52, opened Nov. 19, 2023Completion of Rest: Scheduled for November 2026Opened sections of route temporarily signed as until Loop completed in 2026 |
I-74 is to leave US 52 near NC 65 and be routed on the eastern half of the Winston-Salem Northern Beltway to US 311. The Winston-Salem Northern Beltway is a planned 34 mile arc freeway from US 158 southwest of the city to US 311 in the southeast. The Eastern Half is to run from US 52 to US 311. Though US 52 through Winston-Salem is a freeway, it is substandard and NCDOT from the beginning of I-74 planning apparently felt that routing through traffic away from Winston-Salem was a better option than upgrading US 52 through downtown. (Though in recent years they have completed projects to upgrade the highway and remove problem interchanges, and, they plan for US 52, if completely upgraded, to serve as an extension of I-285*).1
Though long-planned and constantly postponed, due to either litigation, or the lack of funding, the first segment of the Beltway started construction in December 2014. Both the pressing of NCDOT by local officials and the, not coincidental, recalculation of the new transportation funding mechanism announced by NCDOT in 2013, caused the Beltway project not only to jump from last place in the state Loop construction list, but to be placed on the Urban Loop Acceleration Plan list. Thus a project that only a couple years ago was projected not to start until the mid 2020's, has received enough funding, made possible by Grant Anticipation Revenue, or GARVEE, bonds, which allow NCDOT to borrow against future federal funding, to at least build the first couple segments, the first from Business 40/US 421 to US 158 was let in October, and awarded in early November 2014 to Dragados USA Inc of NYC for $153,999,950.2 The starting date of the project was December 10, 2014. The completion date has moved over the length of construction.3 A NCDOT Press Release from April 17, 2019 indicated it could open by the end of that year, it didn't, a map detailing new exit numbers for the US 421/Salem Parkway issued by NCDOT in January 2020 indicated the completion date was Spring 2020, then NCDOT said that it will open by August.4 Lanes were closed on the Salem Parkway/US 421 starting in late April to allow final paving of the ramps between the Beltway and US 421, and periodic closings continued into early September, suggesting opening was near. The segment was finally opened on the morning of September 55 (See photos section). (Drive on the new segment with this video). Jumping the gun a bit, the NCDOT traffic map, by Bing, added the first segment of the Beltway, despite it not being open yet, to its North Carolina map the third week of April:
Work started on a second segment from US 158 to US 311 on January 19, 2018. NCDOT stopped posting information on the contract in November 2020, implying it would be open soon. NCDOT announced the roadway would open on December 23, 2020, six months early, since the official completion date was in 2021. The route ended up opening on December 27.6,7 (Check out this video of a drive on the newly completed roadway.) On April 5, 2018, NCDOT announced it had awarded the contract to build segments D, E and F to Flatiron Constructors, Inc. for $120 million, this extended the Beltway from US 311 to NC 66/University Parkway. Design work started on April 30, 2018 and construction in April 2019. This section opened to traffic on November 7, 2022.8 This despite a news report in early 2022 that it was more likely to open closer to the end of the year.9 It will take a little longer to complete this part of the Beltway the final mile to US 52. A Design-Build contract to connect the Beltway at NC 66 to a new interchange with US 52 (Contract C204137) was awarded in October 2018, and as of the latest update at the end of September 2024 was 94.7% complete (up only slightly in 7 months from a listing of 93.1% complete in January), work was originally supposed to be completed more than a year earlier in September 2022. In late March 2022, however, the completion date was moved to July 2, 2023, this didn't change until February 2024 when it was moved to, still a little late, August 29, 2023 (perhaps meant to say 2024? Apparently not, as of October 2024 it is listed as September 13, 2023).4 News reports at the time of the completion to NC 66 indicated the opening of this section was to occur some time in late Summer 2023. In early July a Winston-Salem Journal article stated the planned opening date now was to be around Thanksgiving.10 NCDOT announced in a press release in mid-November that the initial opening of the interchange, the connections between the Beltway and US 52 North and US 52 South and the Beltway would occur on November 18, after lane closures along the intersecting routes starting the day before.11 Only 1 lane in each direction was opened first, with both directions of US 52 using the future I-74 West lanes, with openings of additional lanes and other ramps within the interchange occurring in stages into 2024.12 Work continued through the summer and fall of 2024. NCDOT announced lane closures the week of September 22 to 29 along NC 74 East beyond the split from US 52 South for final paving of the permanent eastbound lanes. The same press release indicated that the final alignment of the roadway would open after a complete closure of NC 74 East on September 25. It was assumed permanent signage will be installed at the same time or soon after, but a video taken on October 7 (see link below) showed only supports being stored for overhead signs at the Westinghouse Road exit.13 The Preliminary work on the US 52 interchange (Contract C203840), modifying the exit ramp with NC 65 and building a wider NC 65 bridge to accommodate future ramps between US 52 and the Beltway started in January 2017, which also included preliminary work on the western section interchange with US 421, and was finished in October 2019, (see photos of construction below). Here's the latest NCDOT map of the completed Beltway route, from November 2022:
The next segment to be constructed is at the other end of the Beltway, from I-40 to the US 421/Salem Parkway (Former Business 40), which was to be started in October 2020, but which was not let until December 2021. Work started on this project on April 4, 2022 and as of 2+ years later on October 15, 2024 was nearly 2/3 (63.0%) complete. Work is to be completed by the end of April 2027.14 The last segment of the Eastern beltway, between I-74 (former US 311, still referred to as that in contract documents) and I-40, first delayed in September 2019 from late 2020 until March 2021, was let in October 2022 with work starting on December 1, 2022 and more than 1 1/2 years later, as of October 22, 2024 was more then half (56.6%) finished, though the completion date was moved back in August 2023, by 2 days, from March 30 to April 1, 2027.14 Though this project is scheduled to be completed a month earlier than the US 421 to I-40 section,it is to be opened at the same time.14 As a result of the delays, the eastern section will now not be completed until at least late 2026. An NCDOT spokesman in June 2024 indicated the project was more than half complete and ahead of schedule, indicating the completion date was 2026.17 Meanwhile, NCDOT's budget problems caused them to postpone work on the western section of the Beltway to at least 2033. For a more detailed discussion of these projects, see the Project History section, below. Here's an NCDOT maps of how the Beltway stands as of January 2022, as published in the Winston-Salem Journal:9
Here's an earlier map of the Beltway Project by NCDOT showing the construction segments as of August 2017 with then dates of both Eastern and Western Beltway construction:
LATEST PHOTOS (Updated 11/2/24)
Screen grabs from video taken driving US 52 South to NC 74 East by Benjamin Wolf (jcil4ever on AARoads Forum) on October 16, 2024:
Driving onto the start of the new alignment for the NC 74 East /Beltway lanes at the split with US 52 South.
At the time there the video was shot there was only 1 lane open along the new NC 74 East /Beltway lanes.
Driving under the NC 65 bridge on the new NC 74 East /Beltway lanes.
A temporary No Left Turn sign as the new alignment for the NC 74 East /Beltway lanes approaches the future ramp from the western Beltway section.
More to come...
Screen grabs from video taken driving the I-74 corridor by Big Rig Travels on October 7, 2024:
A. Driving I-74 West through the Beltway interchange construction area:
Entering the work zone on I-74 West after Union Cross Road. The noise wall along I-74 East appears to be completed.
Approaching the site of the future interchange where I-74 West traffic will head off to the right.
Work is proceeding on constructing the support structure for the future I-74 West Beltway ramp.
Approaching the site of the future flyover ramp to the Beltway headed west.
Heading under the future flyover ramp to I-74 West with partially completed bridge deck.
Work in the median after the site of the future eastbound flyover ramp.
Site of future ramp from the Beltway to current I-74 West, future NC 192.
B. Driving US 52 North through the Beltway interchange area:
View along US 52 North showing no sign of paving yet on future exit ramp to the NC 74 Beltway heading east.
US 52 North lanes are also still restricted in the future NC 74 East ramp area by temporary barriers while a permanent median barrier is being constructed.
Meanwhile paving and other work has continued on the future US 52 North ramp to the western section of the Beltway which won't be built for a few years.
View looking towards the current NC 74 West merge and to the left the completed NC 74 East lanes heading under the US 52 North bridge with the incomplete west lanes to the right.
Another view from the US 52 North bridge approaching end of NC 74 West ramp with closer view of opened EB and under construction WB Beltway lanes.
US 52 North traffic separated from future I-74 West lanes approaching on-ramp from NC 65 at northern end of Beltway interchange.
Screen grabs from drive along I-40 West through the Beltway construction zone in Tar Heel Dashcam video from early October 2024:
Recently placed, and to be covered up until 2026, advance sign for future I-74/ Winston-Salem Northern Beltway exit at ramp to Union Cross Road on I-40 West.
Completed section of noise wall after Union Cross Road exit on I-40 West, matching previously placed wall along the eastbound lanes.
Noise wall still under construction along future ramp to I-74/ Winston-Salem Northern Beltway from I-40 West.
Flyover ramp construction continues at site of future I-74/ Winston-Salem Northern Beltway exit on I-40 West. Hard to tell from the photo, but traffic has been moved to new I-40 East lanes that go under the ramp.
Empty former I-40 East lanes seen after site of future I-74/ Winston-Salem Northern Beltway exit along I-40 West.
New NCDOT traffic camera view of southern end of US 52/Beltway interchange, October 2024:
Traffic camera images taken October 13 showing realignment and widening of US 52 South approaching the Ziglar Road bridge, and that the ramp from US 52 North to the Beltway East is still not open.
Screen grabs from Google Maps Street View coverage of US 52 North approaching the Beltway interchange, September 2024:
From US 52 South:
The ramp for the NC 65 exit, now separated from NC 74 Beltway traffic, with temporary gore sign surrounded by traffic barrels.
Approaching the NC 65 bridge, unopened NC 74 Beltway permanent lanes to the left.
Approaching the ramp from the NC 65 exit, the temporary barriers on the left were removed the weekend of October 26-27 and the US 52 South lanes repaved.
The end of the temporary barrier can be seen ahead, NC 74 East traffic still using the future westbound lanes to the left.
Views from the NC 65 bridge:
Looking north at the permanent NC 74 East lanes ready to open and traffic continuing on the future westbound lanes with traffic from NC 74 West using the US 52 North lanes. NC 74 East traffic was moved onto the permanent lanes in early October.
Now looking south, the permanent NC 74 East lanes ready to open on the right with traffic from NC 74 West using the US 52 North lanes on the left.
EARLIER IN 2024:
Screen grabs from Google Maps Street View coverage of I-40 East approaching the Beltway interchange construction zone, June 2024:
Completed concrete roadway awaiting opening of ramp to I-74 Beltway ramp.
Getting closer to the future I-74/Beltway ramp. A guardrail has been installed.
The concrete roadway ends at the future ramp.
Looking along the paved ramp toward the split of ramps for each direction of the I-74 Beltway.
Completed concrete roadway along side in progress landscaping approaching the start of the future I-40 East lanes.
Part of the concrete roadway awaiting completion to tie into the current I-40 East lanes. Traffic was shifted onto the new lanes later in the summer, see October photos.
NCDOT traffic camera on US 421 South from October 2, 2024 showing no change yet in signage for NC 74 East, only listing US 311, even after all ramps were opened to and from US 52 in late September:
NCDOT Traffic Camera on US 52 from September 23, 2024 shows new traffic pattern northbound under Ziglar Road bridge near Beltway interchange, but there is no change southbound and the ramp from US 52 North to NC 74 East appears to be still under construction:
Screen grabs of Google Maps Street View camera traveling along I-40 East through the Beltway interchange construction zone in April 2024:
Entering construction zone on I-40 East showing start of concrete roadbed for future third lane.
An overhead advance sign for the Beltway exit has already been put up and covered over waiting for the interchange to open in 2026.
The added concrete right lane prior to the Beltway exit appears almost completed.
The foundation for another overhead sign awaits its gantry prior to the future Beltway exit.
The future off-ramp to the Beltway, notice at least one covered up sign has been placed at the future split of east and west lanes.
Concrete being placed on future I-40 East lanes as they diverge from current alignment after future Beltway exit ramp.
The future I-40 East lanes continue towards the site of flyover ramp construction for the Beltway interchange.
A closer view of one of the Beltway to I-40 flyover ramps stopping just short of the future I-40 East lanes.
Looking the other direction at the future flyover ramp from the current I-40 East lanes.
One of the overhead ramps crossing the lanes of another as seen across the future I-40 East lanes.
Steel support beams from one of the flyover ramps approaching the current I-40 East lanes.
View of the same ramp from the other direction.
Another covered up overhead advance sign, this one for the Union Cross Road exit at the future merge site from the ramp from I-74 East to I-40 East.
Street View captured a steel girder being placed on supports for one of the future flyover ramps over I-40 East.
Construction vehicle traveling along future I-40 East lanes between on-ramps in the Beltway interchange work zone, meanwhile closed bridge still over I-40 West lanes.
Not all concrete had been placed along future I-40 East approaching the ramp from I-74 West.
Approaching the completed noise wall along the future ramp from I-74 West, construction vehicles on the future I-40 East lanes.
Completed noise wall approaching future 3-lane I-40 East roadway at I-74 West ramp still under construction.
It appears some work is still ongoing along the future I-40 East right lane approaching the Union Cross Road exit.
While the I-40 East noise wall is complete, work is still proceeding for the wall along I-40 West.
The new exit sign for the Union Cross Road exit, this one doesn't have to be covered up.
Screen grabs of Google Maps Street View camera traveling along I-74 East through the Beltway interchange construction zone in April 2024:
View from I-74 East after the Ridgewood Road exit of the Beltway interchange project work zone.
Approaching the work zone for the future exit ramp for I-74 West/ Beltway.
At the future exit ramp to the Beltway/ I-74 West.
Current I-74 East lanes shifting over to the left to accommodate bridge and future Beltway interchange work.
Supports for the Beltway interchange ramp bridge have been placed over the future eastbound lanes.
A closer look at the installed road deck for the future ramp over the eastbound roadway.
View across I-74 West at bridge abutment construction for the other side of the Beltway west interchange ramp bridge.
View from I-74 East after the future ramp to the westbound Beltway as lanes start to shift back to the right.
Looking across I-74 West again at construction work zone for future ramps to and from the Beltway.
Work continuing along I-74 East after the future Beltway interchange site.
The 3/4 Mile advance sign for Union Cross Road standing in the future right lane of I-74 East.
Supports for future noise wall along I-74 East sit alongside the widened roadway.
Further along I-74 East the noise wall supports have been placed.
And a completed section of noise wall approaching Union Cross Road.
More noise wall supports stored near the end of the Beltway interchange work zone at Union Cross Road.
The signage for NC 74 West/Winston-Salem Northern Beltway on US 421/Salem Parkway have still not been updated to reflect the extension to US 52 North in November 2023. [Still true in August 2024]
The signage at the NC 66 also has still not been updated to reflect the extension to US 52.
Traffic beyond the NC 66 exit is still restricted to 1 lane 6 month after the road opened to US 52.
NC 74 West at ramp from NC 66/University Parkway approaching the Parkway bridge.
The view towards US 52 after the University Parkway bridge, NC 74 West still using US 52 South/Future I-274 Beltway ramp.
NC 74 West traffic heading onto the exit ramp.
NC 74 West heading up the future exit ramp.
Temporary NC 74 West lanes crossing over Grassy Creek.
Approaching the future split of ramps for US 52 South and for NC 65 via US 52 North.
Construction barrels block off the future US 52 ramp still under construction.
At the split of the future 2-lane ramp to US 52 South, and eventually the western section of the Beltway from the ramp to US 52 North.
A closer view at the future 2-lane ramp heading towards the ramp bridge still under construction.
Temporary NC 74 West lanes heading towards US 52 North (seen in the distance).
Continuing along the NC 74 West ramp, looking over to the Beltway lanes, eastbound still under construction with NC 74 East traffic still using future westbound lanes.
View of the Beltway ramp bridge over the current NC 74 East and future westbound lanes.
Another view of eastbound NC 74 lanes still under construction from the ramp currently carrying NC 74 West traffic.
The NC 74 West ramp curves to meet with US 52 North.
Getting closer to US 52 North (and don't forget Future I-285 North).
Approaching the current end of NC 74 West at US 52 North, blue services sign for NC 65 exit.
Ramp from NC 74 West merging with US 52 North.
Currently US 52 North narrows to 2 lanes approaching the NC 65 bridge. Future I-74 West lanes to the left.
Heading under the NC 65 bridge, the exit ramp starting just before.
Looking at construction of future NC 74 East lanes from US 52 North under the NC 65 bridge.
US 52 (Future I-74) construction continues beyond the NC 65 exit ramp.
Images of construction along US 52 North at the northern end of the future Winston-Salem Northern Beltway/Future I-74 interchange, screen grab images from video by Tar Heel Dashcam posted on April 24, 2024:
Passing under the Ziglar Road bridge prior to the Beltway interchange construction site, traffic still moves over to the left due to continuing ramp construction.
Approaching the future I-74 East Beltway ramp, still only graded.
Now passing the next future Beltway ramp for future I-274 West.
A closer look shows that there is paving going on at this future Beltway ramp. Perhaps this is to be used temporarily to access the Beltway eastbound while the permanent one is completed?
Now about to pass under the NC 65 bridge on Beltway exit lane. US 52 South traffic still using Future I-74 West lanes. Still no permanent signage for the NC 65 exit, the VMS is the 1/2 Mile advance sign.
Images of construction along US 52 South at the northern end of the future Winston-Salem Northern Beltway/Future I-74 interchange, screen grab images from video by Driving Around NC posted on April 22, 2024:
Approaching the NC 65 bridge on US 52 South after split from NC 74 East/Winston-Salem Northern Bypass lanes, still using future I-74 West lanes.
Future NC 74 East/Winston-Salem Northern Bypass lanes to the left still being constructed while traffic uses future I-74 West lanes further beyond.
View across US 52 South to the Future I-74 East/Winston-Salem Northern Bypass ramp, still under construction at the end of the Beltway interchange work zone.
EARLIER PHOTOS
Images of construction along I-74 at the southern end of the future Winston-Salem Northern Beltway, screen grab images from video by TarHeel Travels posted on March 23, 2024:
Entering the construction zone on I-74 West with traffic transitioning to new lanes to the left in the distance.
Transitioning to new lanes on I-74 West prior to future ramp to the Winston-Salem Northern Beltway. Landscaping continuing along the eastbound lanes.
A crane seen in the future Beltway lanes heading off to northwest from current I-74 West.
Closer view of the future site of the Beltway lanes heading off to the right with some ramp support structures under construction.
View from current I-74 West of future site of Beltway ramps with bridge structures being constructed.
Closer view of the bridge structure being built over current I-74 that will carry eastbound traffic to the Beltway.
Entering the construction zone on I-74 West with traffic transitioning to new lanes to the left.
Photos of construction around the newly opened US 52 interchange with the Winston-Salem Northern Beltway with screen grab images from a video by TJElevatorfan from March 2024:
View from US 52 North of the still unfinished ramp to the NC 74 Beltway headed east. At least the landscaping is mostly complete.
A closer view of the ramp, some grading still to be completed in the distance.
Road closed (for a while) signs in front of the future ramp to the I-274 Winston-Salem Beltway west segment.
View over the interchange construction area towards the ramp that will carry traffic from the Beltway west to US 52 South, and eventually, I-274.
US 52 North approaching the current ramp carrying westbound Beltway traffic, the future lanes are still carrying eastbound traffic on the left.
Turning around....
View from the start of NC 74 East, on the future westbound I-74 lanes, after the Beltway ramp has split from US 52 South. headed east. Notice the future lanes are being prepared for paving.
View from NC 74 Beltway heading east towards US 52 North bridge with graded future eastbound lanes to the right.
NC 74 East heading under US 52 North, future Beltway east lanes to the right have been paved but no lane striping as of yet.
The NC 74 East Beltway now heading under the future ramp from the Beltway west to US 52 South.
The future NC 74 East Beltway lanes approaching the Grassy Creek bridge still has not been paved.
Temporary NC 74 East lanes transferring back to the permanent lanes prior to the NC 66 exit.
A portable VMS still being used as an advance sign for the NC 66 exit heading east.
Photos taken by David Johnson along I-40 East in the I-74/Beltway construction zone on February 25, 2024:
A concrete barrier separates construction equipment and the paved future ramp to the Beltway/I-74 East from I-40 East.
Work continues on constructing the flyover ramps from I-40 to the Beltway/I-74.
Two of the flyover ramps that will cross each other to and from the Beltway/I-74.
These supports along I-40 East still wait to be connected together.
A view of the future I-40 East bridge in front and flyover bridges under construction in the distance.
This bridge over I-40 East still awaits demolition. The completed noise wall between the future ramp from I-74 West to the Union Cross Road exit can be seen in the distance.
This NCDOT traffic image from Hanes Mill Road from February 23, 2024 shows a lack of progress over the winter in completing the ramp to the Beltway east from US 52 North, hopefully warm weather will speed up progress in paving at the interchange:
PHOTOS FROM 2023
The following are photos of the newly opened US 52 interchange with the Winston-Salem Northern Beltway. They include photos taken by Mark David Moore on December 15, 2023 and screen captures from a new video of the Beltway by Tar Heel Dashcam made earlier in December, starting at the NC 66 exit:
The exit sign for NC 66. The 'All Traffic Must Exit" tab had been taken down but no new sign for the US 52 exit had been placed yet. Traffic currently uses the future US 52 South exit ramp to get to US 52 North.
The new NC 74 West lane heading under the University Parkway bridge . The new ramp from NC 66 enters to the right.
The one opened lane after NC 66. The remaining 2 lanes await the completion of the Beltway connection westbound to US 52.
A concrete barrier has placed where westbound Beltway traffic is currently diverted along the future ramp to US 52 South (and longer in the future I-274 West).
Along the current NC 74 West ramp, approaching the future split with the ramp to carry traffic to US 52 South and, eventually, to I-274.
View from the westbound ramp of the future I-74 West lanes now being used for NC 74 East Beltway traffic from US 52 South, heading under the US 52 North bridge.
The current end of the ramp from the Beltway to US 52 North. The blue services signs are for the NC 65 exit. Meanwhile driving towards the Beltway along US 52 North...
Approaching the new Ziglar Road bridge on US 52 North, work needs to be completed here, and the concrete barrier along the right lane removed, before the new ramp to NC 74 East can be completed.
A temporary 1 Mile advance sign for the NC 65 exit sits after the ramp to NC 74 East to the right of the frame, which is still be graded.
Looking across the construction zone to the future ramp bridge that will carry traffic from NC 74 West to US 52 South along with work continuing on the still to be opened NC 74 East roadway.
Approaching the NC 65 bridge on US 52 North after traffic from NC 74 West, temporarily using the future NC 65 exit ramp, merges from the right. Now turning around and heading east towards the Beltway...
While current traffic from the Beltway to US 52 North uses an exit ramp, the NC 74 East lanes uses the future I-74 West lanes. Traffic has already split from US 52 South, which can be seen to the right. This split will be beyond the NC 65 bridge seen in the distance when the eastbound lanes are opened.
Two of the future I-74 West lanes are currently being used for NC 74 East traffic, US 52 can be seen on the right beyond the future eastbound lanes.
This section of future NC 74 East lanes had not been paved at the time of the video, suggesting it may be a while before the lanes are completed.
A closer view of the US 52 North bridge, work proceeding on the right to complete the permanent eastbound Beltway lanes.
Approaching the future ramp bridge for the US 52 South exit, still under construction.
The current NC 74 East lanes approaching the future ramp taking traffic from US 52 North.
Temporary road curve advisory signs marks the impending shift of NC 74 traffic back to the eastbound lanes after the Creek bridges.
The lanes shifting over to the eastbound lanes prior to the NC 66 exit.
Another portable VMS being used as an exit sign, in this case for the NC 66/University Parkway exit.
There was still only a temporary exit sign for NC 66 on NC 74 East when the video was filmed.
The exit signage for NC 74 West had not been changed along US 421/Salem Parkway to reflect the Beltway's completion to US 52 when the video was filmed.
Screen grab images from December 2023 Tar Heel Dashcam video of construction of I-74/Winston-Salem Northern Beltway interchange from I-40 East:
Contractors have started to place the roadway supports on the future flyover ramps for the Beltway interchange, as seen from I-40 East.
More flyover ramp progress in the Beltway interchange, as seen beyond the future new I-40 East bridge.
Work is also proceeding on building noise walls along the future ramp to I-74 East to I-40 East as seen near the future ramp merge.
Work has been completed in putting up the noise walls from this point after the future I-74 East ramp to near Union Cross Road (see video).
View of the Beltway exit ramp construction with I-40 looking north from Glenn Hi Road bridge.
Google Maps Street View images from October 2023 of construction of I-74/Winston-Salem Northern Beltway ramps from I-40 East:
Approaching paved future ramp to I-74 East/Winston-Salem Northern Beltway.
A closer look at the future ramp to I-74 East/Winston-Salem Northern Beltway prior to the 2 Miles advance sign for Union Cross Road.
Partially paved shoulder between the 2 paved future ramps to the I-74/Winston-Salem Northern Beltway.
Now approaching paved future ramp to the I-74 West Beltway.
Closer view of the future westbound Beltway ramp. A concrete barrier to separate I-40 and ramp traffic is under construction.
View of Beltway construction along I-74 West near from the future interchange to Ridgewood Road from September 2023:
Looking from I-74 West lanes at progress constructing the future interchange between the end of the Beltway and I-74.
A new concrete barrier has been placed along the I-74 West lanes for future construction in the median 1/2 mile from the Ridgewood Road exit.
Work continues on the future ramp from the end of the Beltway to current I-74, Future NC 192 West.
Variable speed limit signs mark the end of future Beltway on-ramp construction.
Looking back along I-74 West lanes at the future on-ramp at the end of the Beltway.
Aerial View of the US 52 interchange with NC 74/Winston-Salem Beltway prior to opening in November 2023, from Winston-Salem Journal:
Other photos and drone video are available in this November 16 article by the Winston-Salem Journal.
*Google Street View images from I-74 in the vicinity of the southern interchange construction zone, September 2023:
View from I-74 West of newly opened temporary I-74 lanes through the western end of the Beltway construction zone.
View of I-74 East traffic transitioning over to temporary I-74 lanes through the western end of the Beltway construction zone.
View from temporary I-74 East lanes of equipment being stored along old lanes in construction zone.
Equipment used for excavation on old I-74 lanes prior to the end of the temporary eastbound lanes.
Excavation along I-74 East lanes prior to first advance sign for the Union Cross Road exit.
Excavation all around the Union Cross Road 3/4 Mile advance sign.
Dirt mounds to be removed further along the I-74 East lanes.
Recent excavation getting closer to the Union Cross Road exit.
Approaching the end of the construction zone just prior to the Union Cross Road exit.
Looking across the I-74 West lanes at the site of the future Beltway interchange.
*Google Street View images from Kernersville Road in the vicinity of the interchange construction zone, July 2023:
Looking north from Kernersville road over Northern Beltway interchange construction area.
Looking west along Kernersville road at temporary roadway being built to carry traffic around future interchange construction area. This roadway was opened the weekend of September 16-17.
Construction of the temporary road continues north of the future Northern Beltway interchange site.
Looking back south along Kernersville Road toward Northern Beltway interchange construction area.
Sign images taken along NC 74 East by Mark David Moore, December 15, 2023:
An East NC 74 reassurance marker after the NC 66 exit.
The 1/2 Mile advance sign for the Baux Mountain Road exit.
The Baux Mountain Road exit sign, and a brave clean up crew member.
Another East NC 74 reassurance marker prior to the 2 Miles advance for the US 311 exit.
The 1 Mile advance for the US 311 exit. Signs in this direction include space for "North" when the route is truncated to the Beltway, no exact date has been given (see sign plans).
The gantry at the US 311 exit ramp also includes a 1 3/4 Miles advance sign for the S 158 exit, notice there are almost two miles between Exits 49 and 50.
The 1/2 Mile advance overhead for the US 158 exit.
The US 158 exit sign prior to the bridge, now 50 miles from the Virginia border.
An auxiliary sign for the upcoming US 421 exit, the Beltway signs were designed prior to the Salem Parkway naming and therefore are not included on the overheads.
T overhead 1/2 Mile advance sign for US 421. It is apparent this will be replaced by a much larger arrow-per-lane sign after the Beltway is completed.
The overhead signage at the start of the C/D lanes for the US 421 exit.
The overhead and ground mounted signage at the split of ramps for the US 421 exit. Given the actual direction of the highway, would it have been better to have East and West for the Salem Parkway sign?
EARLIER PHOTOS
Google Street View images from NC 66 Bridge looking toward Beltway/US 52 interchange construction zone, June 2023:
Looking west toward US 52 showing progress in paving future Beltway lanes towards US 52, at the time not beyond the creek bridges. Paving has commenced to the right of the future ramp that will take traffic to the western section of the Beltway (I-274) and to US 52/NC 8 South over I-74.
Google Street View images along I-74 West through Beltway interchange construction zone, June 2023:
Clearing along I-74 median at start of Beltway construction zone.
Clearing continues along I-74 West roadway for future Beltway ramp on right.
Clearing of I-74 median for future I-74 East lanes in Beltway construction zone.
Clearing along both sides of I-74 West nearing end of future Beltway on-ramp construction area.
Further west clearing continues in median an some activity along the shoulder as well.
Paving started for temporary East I-74 lanes just west of future Beltway interchange, these lanes were opened in August..
Clearing of I-74 median continues approaching the Ridgewood Road exit.
Variable Speed Limit signs along I-74 West approaching the Ridgewood Road exit and the end of the Beltway construction zone.
Google Street View images along US 52 South through the Beltway interchange construction zone, June 2023:
Future I-74 East lanes heading off on left from US 52 South to meet the Beltway.
Paving had started along this section of Future I-74 East lanes prior to barrier splitting of from US 52 South lanes.
View of completed US 52 North bridge over Future I-74 East lanes from US 52 South bridge.
Google Street View images along US 52 North through the Beltway interchange construction zone, June 2023:
View at the start of the new US 52 North lanes after the demolished Ziglar Road bridge.
The former US 52 North lanes will be part of the future ramp to I-74 East.
Closer view from the new US 52 North lanes to the future, still unpaved, ramp to the I-74 East Beltway.
View of the new US 52 North lanes after the future I-74 East Beltway exit ramp.
*The new US 52 North approaching the first bridge over the future Beltway.
*Looking northeast toward new bridge being built over the future I-74 roadway.
*Approaching the future ramp from the I-274 section of Beltway merging onto the new US 52 North lanes.
*View of the new US 52 North lanes after the future I-274 ramp merge crossing bridge over the future westbound Beltway.
*Another closeup look at bridge construction along the future I-74 roadway linking the Beltway with US 52 North.
*The new US 52 North lanes about to cross the second bridge over the future Beltway.
*Looking east from the new US 52 North lanes along the future pathway of I-74 to the NC 66 bridge showing completion of paving up to the new bridges.
*View of the new US 52 North lanes approaching the bridge over the future I-74 East lanes.
*Looking north prior to bridge over future I-74 lanes being graded back to NC 65 bridge.
*Crossing the bridge over the future I-74 lanes.
Looking back at the new US 52 North lanes crossing over the future I-74 East ramp to the Beltway.
View of the US 52 North merging back into its own alignment, paralleling the future I-74 West ramp from the Beltway.
US 52 North lanes on future C/D ramp that will carry I-74 West traffic approaching the NC 65 exit.
Future US 52 North/I-74 West lanes being graded approaching the NC 65 bridge.
US 52 North following ramp to NC 65 as future lanes are being graded.
Current US 52 North lanes heading under the NC 65 bridge.
Google Street View images along US 52 South in Beltway interchange construction zone, April 2023:
Not much has changed with the future Beltway ramp from US 52 South since October.
Looking east toward the future US 52 North lanes and bridge over the future Beltway.
Future US 52 lanes partially graded, guardrails in place.
Looking east at the future US 52 North lanes and bridge over a future Beltway ramp.
Looking back along the future US 52 North lanes and the future ramp carrying I-74 West from the Beltway.
Closer look at progress building the future I-74 West ramp to US 52 North, still much work to be completed.
Closure look at nearly complete future US 52 North lanes and bridge over the future Beltway. Traffic still using existing lanes to the left.
The future US 52 North bridge near completion at the southern end of the Beltway construction zone.
Looking back at the future US 52 North bridge and lanes heading towards the future Beltway exit.
Workers tying in the future US 52 North lanes with the existing ones close to the Ziglar Road bridge.
Looking across towards the future US 52 North exit ramp with the future Beltway.
Looking south along US 52 towards the partially demolished Ziglar Road bridge, needed to be replaced so this section can be widened as part of the Beltway interchange project.
Looking north again along US 52 at widening work being started north of the Ziglar Road bridge.
Looking towards US 52 North passing under the remains of the Ziglar Road bridge at the start of the Beltway interchange project work zone.
EARLIER PHOTOS
Google Street View images along I-40 in Beltway interchange construction zone, March 2023 (except where indicated) going west to east:
Grading for what appears to be the future ramp from I-40 East to I-74 East near the beginning of the work zone.
Additional grading and excavation seen beyond the concrete barrier.
Excavation of a hill encroaching on the work zone.
Approaching the future I-40 West interchange ramps.
A closer look at the supports under construction for the future flyover ramp from I-40 West to I-74 East.
Part of future bridge of I-40 East over the I-74 Beltway being constructed.
A close look at the closest support under construction for the future flyover ramp alongside I-40 East.
Future I-40 East lanes being excavated just beyond a mile from the Union Cross Road exit.
What remains of bridge over I-40 West being removed in I-74 Beltway construction zone.
Looking east along I-40 where grading for future lanes extends towards Union Cross Road.
Looking west just beyond ramp from Union Cross Road showing extensive landscape work along I-40 East.
A look at the excavation along the eastbound lanes from I-40 West approaching Union Cross Road, February 2023.
More excavation along I-40 East looking back towards the future I-74/Beltway interchange, February 2023.
Construction of a noise wall at the Union Cross Road exit on I-40 East.
Taken by Adam Prince along NC 74 West on March 31, 2023:
A closeup of the 1 Mile advance sign for the Beltway exit on US 421 North. Notice the sign has not been updated since the Beltway was opened to NC 66, probably not to encourage too much out of state traffic to US 52 North.
A closeup of the exit sign for the Beltway exit on US 421 North. The ramp is restricted to 1 lane due to new construction along NC 74 West.
View of the lane restrictions on NC 74 West between US 421 and US 158.
A closeup of the sound wall construction along NC 74 West causing the lane restrictions.
A closeup of the 1/2 mile advance sign for the US 158/Reidsville Road exit on NC 74 West.
Overhead signage at the US 158/Reidsville Road exit on NC 74 West.
A closeup of the 1 mile advance sign for the US 311/New Walkertown Road exit further west on NC 74.
Beyond US 311 is a 2 Miles advance for Baux Mountain Road. Is this interchange that important? There is also a West NC 74 reassurance marker beyond just before the next noise wall.
The exit sign for Baux Mountain Road. The ramp here has a noise wall.
The 1/2 Mile advance for NC 8/Germanton Road. Apparently this is Bridge No. 2775.
A closeup of the overhead signage at the NC 8/Germanton Road exit. The current end of the Beltway is 1 1/2 miles away.
The 1/2 Mile advance for NC 66/University Parkway and another All Traffic Exit yellow tab below the exit number.
The exit sign at the current end of NC 74 West at NC 66/University Parkway. The gantry awaits a US 52 exit sign.
Looking along the remaining section of the Beltway under construction to US 52 in the distance.
The NC 66 trailblazers along the ramp from NC 74 West. There is also a To US 52 trailblazer (see below) for any traffic wanting to use the neighborhood streets to travel between the 2 freeways.
Taken from Google Maps Street View images in January 2023 at the current western end of the Beltway at NC 66:
A To US 52 trailblazer on the ramp to NC 66, to help traffic get there from the Beltway.
Looking west from NC 66 bridge toward future interchange with US 52 and the Beltway.
Closeup of the East NC 74 and South NC 66 trailblazers at the intersection with the Beltway on-ramp.
PHOTOS FROM 2022
Taken from Google Maps Street View images in November and December 2022 along I-40 East and West at future Beltway interchange:
View across I-40 East lanes of construction for future Beltway interchange in November 2022.
View from I-40 East lanes of future Beltway interchange.
View of bridge support being constructed for the future Beltway interchange.
Grading for future lanes for either I-40 or Beltway interchange ramps.
Looking east along I-40 showing clearing and a slight lane shift being completed toward the median. Also houses now with view of construction zone.
Piece of construction equipment along I-40 East lanes in the Beltway interchange work zone.
Clearing continues approaching the Union Cross Road exit.
View of construction progress at the I-40 East Mile 200 marker.
Heading now westbound, in November and December 2022:
Clearing and grading has started just after the Union Cross Road exit. in November 2022.
In addition to clearing and grading, some concrete pipe structure appear along I-40 West.
The appearance of the construction zone at mile marker 200 heading west.
Some recently cleared land along I-40 West still in November 2022.
In addition to clearing some berms and rock fill for drainage purposes can be seen along this part of I-40 West.
Further grading progress can be seen looking from the I-40 West lanes now in December 2022.
Progress in building the bridge support seen from the I-40 West lanes also now in December 2022.
Additional supports for future ramps and bridges can be seen across the I-40 East lanes.
Crane helping construct future ramp with future Beltway lanes partially graded heading off in the distance.
More cranes and bridge supports under construction can be seen from the I-40 West lanes along with a tractor trailer advertising for more workers.
EARLIER PHOTOS
Taken during a road trip to North Carolina on October 14, 2022, photos east to west:
Competed Roadway, US 421 to US 311
First advance sign at two miles east of, for now NC 74 West, on US 421 North.
The 1 Mile advance sign on US 421 North, Salem Parkway West.
Entering the Beltway construction zone 1/2 mile from the NC 74 West exit.
Concrete barrier separates US 421 North traffic from widening project east of the NC 74 West exit.
Still before the NC 74 West exit, construction equipment along the future additional US 421 North lane.
More construction equipment along US 421 North.
The exit signage at the NC 74 (Future I-74) West Beltway ramp on US 421 North.
First advance sign for US 158 exit after merge of C/D ramp from US 421 exits on NC 74 West.
First temporary mile marker along NC 74 West.
First advance sign at two miles east of, for now NC 74 West, on US 421 North.
The 1/2 Mile advance comes with temporary signage indicating lane reductions after the exit.
The US 158 exit sign shares a gantry with the first advance sign for the current end of the Beltway at US 311/New Walkertown Road.
The gore sign for the US 158 exit, eventually 50 miles more on I-74 until the Virginia border.
The second NC 74 West reassurance marker after the US 158 exit has two support posts.
The 1 Mile advance for the 311 (North in the future, see sign plans) exit just prior to the lanes drop.
The temporary NC 74 Mile 50 marker.
The roadway prior to the US 311 exit has been repaved in anticipation of the route's extension to NC 66 in November.
The roadway prior to the US 311 exit has been repaved in anticipation of the route's extension to NC 66 in November.
The newly paved roadway continues beyond current end of NC 74 West at US 311. Notice the sign gantries up for the future eastbound Beltway in the distance (more to see in photos below).
Closeup of the gore sign for the US 311 exit. Will the 25 mph advisory be removed when the next section opens?
The North US 311 reassurance marker after turning left at the end of the exit ramp.
Baux Mountain Road
Recently placed 1 mile advance sign for the Baux Mountain Road exit on the umopened Beltway heading east at the NC 66/Old Hollow Road bridge.
NC 8 / Germanton Road Exit
Overhead signage at future NC 74 West ramp for the NC 8/Germanton Road exit (Exit 43). Notice the next All Traffic Exit warning sign appearing over the NC 66 (Exit 42) 1 1/2 Miles advance.
View from near the NC 8/Germanton Road exit looking along the future Beltway heading east toward Old Hollow Road (NC 66).
Closeup of the noise wall along the future Eastbound Beltway lanes near the NC 8/Germanton Road exit ramp.
View of soon to be activated VMS heading west near the NC 8/Germanton Road exit.
Approaching the roundabout at the future ramp to East NC 74 south of the bridge over the Beltway heading north on NC 8.
Crossing the nearly completed NC 8 bridge over the Beltway heading north.
North NC 8 trailblazer and covered over one for NC 74 West north of the bridge over the unopened Beltway.
Approaching the roundabout at the future ramp to West NC 74 heading north on NC 8.
After turning around, noticed this uncovered Jct NC 74 trailblazer approaching the roundabout with the future ramp to East NC 74.
Entering the roundabout north of the bridge over the Beltway with the future ramp to NC 74 (Future I-74) West.
Covered over trailblazer for West NC 74 along the roundabout heading south on NC 8.
Closeup of the future ramp to West NC 74 north of the NC 8 bridge over the Beltway.
Uncovered East NC 74 trailblazer approaching second roundabout for the future Beltway ramps on NC 8 South.
Looking north across unopened section of the Winston-Salem Beltway from the NC 8/Germanton Road bridge.
Looking south at the NC 8/Germanton Road bridge over the future section of NC 74 (I-74).
Looking north across unopened section of the Winston-Salem Beltway toward NC 66 from the middle of NC 8/Germanton Road bridge. Notice the first steps of lane striping along the left shoulders has begun (and some ground level signage has been installed).
Looking south along the unopened section of the Winston-Salem Beltway from the NC 8/Germanton Road bridge toward Old Hollow Road. More lane striping and ground level signage can be seen
Another view of the northern NC 8 roundabout from walking along the bridge.
A closer view of the future NC 74 West ramp from NC 8, with Road Closed sign being a suggestion, it appears (was tempted).
Stanleyville Road Bridge
Seen from the bridge, the overhead exit sign and All Traffic Must Exit yellow tab above at the future NC 66 exit.
A closer view at the future NC 66 exit. Notice the construction vehicle heading east.
The view west from the bridge toward the future NC 8 exit. There is a VMS headed in this direction as well.
A closer view at the future NC 8 exit. The same construction vehicle from above heading east, another heading the 'wrong way' in the westbound lanes.
NC 66/University Parkway Interchange
Uncovered Jct NC 74 trailblazer approaching the future Beltway ramps on NC 66 South.
Covered traffic signals at future NC 74 East ramp on NC 66 North.
North NC 66 trailblazer at future NC 74 West Beltway ramp.
Looking south along NC 66 toward future NC 74 West ramp.
Covered NC 74 West trailblazer next to one for South NC 66 approaching future Beltway interchange.
US 52 interchange
Approaching the site of the future ramp to NC 74 (I-74) East from US 52 North.
Workers paving site of the future ramp to NC 74 (I-74) East.
Work continuing on future US 52 North lanes in the Beltway interchange work zone.
View of future US 52 lanes paralleling current lanes approaching future on-ramp for I-74 West.
Grading of future US 52 lanes paralleling current lanes approaching old ramp bridge from US 52 South.
Future US 52 lanes tower over current lanes at site of future on-ramp for I-74 West from the Beltway.
View of future merge site for US 52 North and lanes from I-74 West/Northern Beltway prior to NC 65 exit.
Approaching the new NC 65 bridge with future US 52 North lanes under construction to the left.
Turning around, view of new US 52 South lanes approaching future on-ramp from I-74 West/Northern Beltway.
Site of the future on-ramp from I-74 West as it merges onto US 52 (Future I-285) South.
The 1 Mile advance sign for the Hanes Mill Road exit at the end of the Beltway construction zone.
The future on-ramp from I-274 East onto US 52 (Future I-285) South.
View approaching the end of the new US 52 South lanes at the southern limits of the Beltway interchange work zone.
Construction Photos
Images from Google Maps Street View of Beltway construction, taken in May to September 2022 east to west along the Beltway corridor:
I-40 (New 11/13) July-September 2022
View looking east from I-40 West toward the start of clearing at site surrounding the future Beltway interchange, 2 miles west of the Union Cross Road exit in September.
View looking from I-40 West toward equipment starting to clear the site of future Beltway interchange, in July.
View across I-40 East at site of future Beltway interchange, in August.
US 311
Looking north (west) from US 311 bridge along Future I-74 which appears paved and has noise walls installed along eastbound lanes.
Old Walkertown Road
Looking south towards the bridge at Dippen Road now with vegetation growing on surrounding landscaping.
Looking north towards the bridge now with noise walls along the future eastbound lanes.
Looking towards the railroad crossing and more noise walls along the roadway heading east.
NC 8 / Germanton Road interchange
The completed roundabout at the future ramps to and from I-74 East.
Looking east along the future Beltway/ I-74 lanes from the NC 8 bridge.
Now looking to the west from the NC 8 bridge showing a noise wall along the future I-74 East lanes.
The completed northern roundabout at the future Beltway/ I-74 West ramps.
Baux Mountain Road (New 11/13)
Looking north towards the first roundabout built at the site of future Beltway east on and off-ramps, taken in July 2022.
Looking along the future Beltway east on-ramp, recently paved.
Looking back towards the southern roundabout at the future Beltway east off-ramp, also recently paved.
Looking along the future off-ramp from NC 74 (Future I-74) East.
Looking north again towards the new Baux Mountain Road bridge over the unopened Beltway.
Looking west along the unopened Beltway from the Baux Mountain Road bridge.
Now looking east from the Baux Mountain Road bridge.
Heading north toward the second roundabout for future on and off-ramps from NC 74 West.
Light poles are up, but sound wall still needs completion along future on-ramp to NC 74 (Future I-74) West.
Looking toward the recently paved off-ramp from NC 74 (Future I-74) East. Notice the extensive noise wall along the westbound lanes.
Looking back towards the roundabout north of the Beltway.
Stanleyville Drive
Looking east from Stanleyville Drive bridge looking toward NC 8.
Looking west from Stanleyville Drive bridge looking toward NC 66, showing new support for future advance sign for NC 8 exit at left.
NC 66/University Parkway
Looking down future off-ramp from I-74 West from NC 66 northbound lanes.
Heading south on NC 66, traffic signals have been installed at the future westbound ramps.
Looking west from the NC 66 bridge toward the US 52 interchange, somewhat easy to tell where the US 52 contract, delayed by 8 months, starts.
Looking at traffic signals installed at future on-ramp to I-74 East from NC 66 northbound lanes.
Installed South NC 66 trailblazer at future I-74 East ramp.
US 52 interchange
Heading north
View along US 52 North entering Beltway interchange construction zone, future ramp to I-74 East being constructed.
Looking to the east toward future Beltway and ramps to and from US 52 North (I-74 West).
Future I-74 West lanes merging onto US 52 North at site of previous NC 66 exit, note ramp bridge from old US 52 South lanes still intact across the highway.
Only part of the former ramp carrying traffic from US 52 South to NC 66 still remains over the northbound lanes.
Heading south on new lanes:
Crossing new US 52 South bridge approaching future Beltway interchange.
View from US 52 North of overhead signage for US 52 South in place at future I-74 East Beltway ramp.
The future I-74 East ramp heading onto the Beltway (and the future start of I-285 South to the left).
US 52 South after the future I-74 East/Beltway off-ramp split. Note room for additional third lane.
New US 52 South lanes heading toward future Beltway on-ramp.
Looking east along future Beltway lanes from US 52 South bridge. New US 52 North bridge under construction.
Another future US 52 North bridge under construction as seen from the southbound lanes.
The 1 mile advance sign for Hanes Mill Road with US 52 exit number.
New US 52 southbound lanes at the future Beltway on-ramp.
A blue services sign for Hanes Mill Road prior to new bridge over railroad tracks along US 52 South.
Looking backwards along US 52 South showing progress in building future northbound bridge.
New US 52 South lanes about to meet original alignment at end of I-74/Beltway construction zone prior to Hanes Mill Road exit.
Photos taken by site contributor J. Austin Carter in late November 2021:
Around the future University Parkway/NC 66 exit:
View looking from University Drive (NC 66) eastward along future Beltway toward the Stanleyville Drive bridge.
View looking at new University Drive (NC 66) bridge from location of former roadway. Notice paving has started and a support for an advance sign for the NC 8/Germanton Road exit has been installed.
View looking south along the University Drive (NC 66) bridge.
View looking toward the University Avenue (NC 66) bridge in the vicinity of one of the future off-ramps from I-74.
From the vicinity of Stanleyville Drive:
View looking northwest from beyond the Stanleyville Drive bridge towards the future interchange at NC 66 / University Avenue.
Closer view looking at construction equipment along the future I-74 West roadway headed towards the future interchange at NC 66 / University Avenue.
Now looking southeast along the paved future Beltway towards the future interchange at NC 8 / Germanton Road.
A closer look towards the future interchange at NC 8 / Germanton Road shows an installed post for a future overhead sign, probably for the NC 66 exit.
At the future NC 8 / Germanton Road interchange
Looking south across the new Germanton Road bridge over the future Beltway, traffic using the new roundabout south of the bridge prior to the NC 66 intersection.
Looking north towards the new roundabout south of the Germanton Road bridge, being built as part of the Beltway construction.
Looking north/west from NC 8 / Germanton Road back towards Stanleyville Drive.
Looking south/east from NC 8 / Germanton Road back towards Old Hollow Road.
From the vicinity of Merrydale Drive and Old Hollow Road
Looking west along Future I-74 from Merrydale Drive toward new bridge for Merry Valley Lane and that for Germanton Road in distance.
Looking east now toward new bridge for Old Hollow Road over the Future I-74 Beltway.
Looking a little closer at the Future I-74 roadbed headed toward Old Hollow Road.
Now looking east from new Old Hollow Road bridge over the Future I-74 Beltway.
Images from Google Maps Street View taken in September 2021
The new US 52 South lanes bridge at the Future Beltway interchange, opened in November 2021:
View from existing US 52 South of near completion of bridge to carry future US 52 South as part of I-74/Beltway interchange project. Lanes opened in November.
Images from Google Maps Street View taken in July and August 2021
The US 311/New Walkertown Road interchange:
Future ramp to I-74 West blocked by traffic barrels with trailblazer for NC 74 East ramp opened in December 2020 on US 311 South.
US 311 bridge over partly opened Future I-74 Winston-Salem Northern Beltway.
East NC 74 and South US 311trailblazers at opened ramp to Future I-74 Winston-Salem Northern Beltway. This will also be the future end of US 311 South.
From Old Walkertown Road:
View of nearly completed Future Northern Beltway/ I-74 bridge over Old Walkertown Road looking north.
A slightly closer look at the Old Walkertown Road bridge looking north, showing it also serves as a railroad bridge.
Looking between the spans of the Old Walkertown Road/Railroad bridge, Future I-74 West to the left and East to the right.
Here's a view of nearly completed bridge looking south.
Closer look at the landscaping near the bridge at the Old Walkertown Road/Dippen Road intersection.
A closer look to the east of Old Walkertown Road showing landscaping still underway for the bridge.
Along NC 66/Old Hollow Road:
Rerouted NC 66 near the new bridge over the future I-74/Northern Beltway. It appears they forgot to move a speed limit sign.
From the Stanleyville Drive Bridge:
Looking west along the Future I-74/Northern Beltway toward the NC 66/University Parkway interchange. The roadbed has been paved.
Looking east along the Future I-74/Northern Beltway toward the NC 8/Germanton Road interchange. The roadbed has been graded.
A zoomed in look east toward the NC 8 interchange.
A zoomed in looking back west toward the NC 66 interchange.
Looking across the completed Stanleyville Drive bridge.
Taken from the NCDOT Traffic Camera at the US 158 exit in September 2021:
Closeup of overhead signage at ramp to NC 74 Beltway East from US 158 West.
Taken by Val Melvin in July 2021 along US 52:
View from US 52 North of start of Winston-Salem Beltway interchange construction zone prior to NC 65 exit.
Construction barrels mark construction along US 52 North of start of Winston-Salem Beltway interchange prior to NC 65 exit, the blue Gas services sign for that exit remains in place.
As is the NC 65 exit sign prior to the new NC 65 bridge.
The current traffic setup with the NC 65 exit starting prior to the bridge, but the actual ramp on the other side.
The new noise wall has been completed north of the future Winston-Salem Beltway interchange along the ramp that will carry I-74 West to US 52 North.
View of US 52 North heading toward future merge with ramp carrying I-74 West from the Winston Salem Northern Beltway.
The 1 Mile advance sign for the Westinghouse Road exit sits near the end of the future I-74 West ramp from the Winston Salem Northern Beltway to US 52 North.
Looking further along US 52 towards the end of Beltway construction at the Westinghouse Road exit.
A close up look at the yet to be landscaped siding along US 52 approaching the Westinghouse Road at exit.
A closer look at what will be a temporary placed exit sign for Westinghouse Road at the end of Winston Salem Northern Beltway construction.
Concrete and construction barrels separate US 52 traffic from Winston Salem Northern Beltway construction approaching the NC 65 exit.
View of Winston Salem Northern Beltway construction at the NC 65 exit. The future I-74 ramp is being built to the right of US 52 South.
Closeup of the NC 65 bridge completed as the first stage of Beltway interchange construction.
Workers on future Beltway ramp as seen from US 52 North after NC 65 bridge.
Closeup of the Beltway ramp construction.
Work proceeding on one of the Beltway interchange bridges south of NC 65.
Closeup of the other end of the interchange ramp bridge as seen from US 52 South.
NCDOT Traffic camera image shows the new signs on the US 421/Salem Parkway for the NC 74/Winston-Salem Beltway exit, now with a US 311 shield instead of US 158:
And an earlier image showing the change in shields on the exit sign of NC 74 West at the US 421 interchange:
From the newly opened section between US 158 and US 311 taken by Andrew B. Futrell:
Signage at US 158 exit with new exit sign for US 311 now uncovered after section opening.
View of newly opened section looking west from under US 158 bridge.
1-Mile advance sign for US 311 exit and VMS sign in the distance.
Now 2-lane roadway heading for new US 311 exit and current end to the Beltway.
Signage at US 311 exit where all traffic must exit.
From NCDOT traffic cameras now operating between US 158 and the soon to be opened US 311 interchange:
From December 12, 2020:
From US 158 camera looking west, image showing near completion of concrete roadway near US 158 bridge.
From December 4, 2020:
Looking west from US 311 bridge showing lane markings and sign installation needed prior to road opening by end of year.
Traffic camera image showing roadway near completion still needing signage and lane markings.
Photos taken from segment still under construction north/west of US 311 in December 2020 by Andrew B. Futrell:
Image showing roadway bridge near completion over future I-74/Northern Beltway.
Graded section of future Beltway lanes and another nearly completed bridge.
Taken along newly opened segment between US 421/Salem Parkway and US 158 by David Johnson, September 11, 2020:
Uncovered 2 Miles advance sign for NC 74 West (Future I-74 West) on US 421 North Salem Parkway (apparently Exit 227 is 2 miles from 224).
The newly uncovered 1-Mile advance overhead for the opened NC 74 West/Winston-Salem Northern Beltway exit.
The uncovered overhead exit sign along US 421 North/Salem Parkway with room to the left for a future I-74 East sign.
Driving along the two-lane ramp from US 421 toward the newly opened Beltway.
Noise walls parallel the right shoulder of the ramp from US 421 North as it merges with the completed Beltway lanes.
Lanes from both North and South US 421 about to merge onto Northern Beltway future I-74 West lanes.
After merging onto NC 74 West. The extreme left lane apparently will not open until more of the Beltway is completed.
First overhead sign gantry heading west, this has a 1 3/4 Miles advance sign for US 158.
View along new section of Beltway includes mountains in the distance along with much closer temporary mile marker.
The only current West NC 74 reassurance marker along the opened section of the Beltway.
View heading further northwest toward the US 158 exit.
The 1/2 mile advance overhead sign for the US 158 exit with the All Traffic Exit banner.
Overhead signage at the current western end of the Northern Beltway, the covered over US 311 exit sign already has its own All Traffic Exit banner, for the end of the year.
Taking the ramp to US 158 at the current end of the Beltway. Another temporary mile marker has been put up, for Mile 51, apparently NCDOT is not rounding up the number for this exit.
Overhead signage at the end of the ramp to US 158, only one arrow for North US 158.
Overhead signage at the NC 74 West ramp on US 158 West, a bigger sign will replace the NC 74 sign when I-74 is routed on the Beltway.
US 421 to US 158
Latest Photos taken by David Johnson, September 3, 2020:
Along the soon to be opened section between US 421/Salem Parkway and US 158:
Looking west from Walkertown Guthrie Road bridge toward soon to open temporary end of NC 74 Winston-Salem Beltway at US 158.
Looking east from the bridge along NC 74 and first overhead sign for US 421.
A zoomed image of the overhead signage at the current western end of the Beltway at US 158, notice the covered sign also includes an All Traffic Exit banner for the next segment of roadway.
Looking west to nearly complete C/D ramps along NC 74 East for the US 421/Salem Parkway interchange.
Looking northwest from current stub at eastern end of the current Beltway toward the soon to open interchange between NC 74 and US 421.
Closer view of overhead signage at beginning of NC 74 West at exit to US 421 North. The pull through is West NC 74 to East US 158.
Noise walls border soon to open ramp from NC 74 East to US 421 South Salem Parkway.
A panoramic shot of the soon open interchange between NC 74 and US 421.
Along US 158 West:
Traffic restricted to one lane approaching soon to open interchange.
A Junction NC 74 trailblazer approaching the interchange which will probably stay in place for the next 5 years.
New traffic signals on flash mode awaiting the opening of the Beltway/US 158 interchange.
Overhead signage at the future ramp to NC 74 East. There is room for a much large ramp sign when I-74 is completed.
Looking across US 158 East at ready to open ramp from NC 74 West.
Looking northwest beyond US 158 bridge showing section still under construction headed towards US 311.
From US 421/Salem Parkway:
Overhead signage in place, though covered over, on US 421 South awaiting opening of ramp to NC 74 West.
Noise wall along future ramp to NC 74 West from US 421 South Salem Parkway.
Overhead signs on US 421 South approaching the Beltway bridge and soon to be opened ramp to NC 74 East. Why is exit tab for Kernersville Road covered up?
Now on US 421/Salem Parkway heading north/west, the covered up overhead and gore signs at the soon to be opened ramp to NC 74 West.
Between US 158 and US 311, taken by David Johnson, September 11, 2020:
Panoramic shot looking at the Future I-74 Beltway being constructed west of US 158 from Williston Court.
Looking west toward US 311 interchange along Future I-74 Beltway from Williston Road bridge.
A closer look at the US 311 interchange from the Williston Road bridge.
Another view from Williston Road Bridge, a new VMS being put up heading east on Future I-74.
Another view looking west toward US 311 interchange along Future I-74 Beltway from the middle of the Williston Road bridge.
Between US 311 and Baux Mountain Road:
Looking east from near the completed US 311 bridge back toward Williston Road bridge.
Now looking west from US 311 bridge toward bridge being built for Dippen Road.
Now looking back east from US 311 bridge along the Future I-74 roadway.
Now looking west along Dippen Road following the Future I-74 roadway.
Further west along Dippen Road following the Future I-74 roadbed being graded.
Closer look along Dippen Road at the Future I-74 roadbed being graded.
View along Phelps Drive at site of Future I-74 bridge.
View along Phelps Drive looking east at site of Future I-74 roadway.
Now on Phelps Drive looking west at grading work continuing on site of Future I-74 Beltway.
Baux Mountain Parkway to NC 8/Germanton Road:
Now on NC 66/Old Hollow Road looking future bridge over Future I-74 Beltway.
NC 8/Germanton Road to NC 66 University Parkway:
View looking west from NC 66/Old Hollow Road at clearing and grading for Future I-74 ramp and roadway. Pilot Mountain can be seen in the distance.
Another look west from NC 66/Old Hollow Road at construction equipment clearing and grading for Future I-74 ramp and roadway.
Photos taken on February 7, 2020 by Site Contributor, J. Austin Carter:
Starting in the area of the future US 311 interchange and heading east (south):
Future I-74 roadbed being graded in vicinity of US 311.
Looking along Future I-74 / Winston-Salem Beltway roadbed heading (north)west from US 311.
New US 311 bridge being constructed over Future I-74 lanes.
Looking down future ramp from US 311 to I-74 East which appears to have been recently paved.
US 311 in vicinity of its future interchange with the I-74 Beltway.
End of future off-ramp to US 311 from I-74 East.
View looking south/east from US 311 along the Future I-74 Beltway toward US 158.
View from US 311 looking along Future I-74 West.
Now looking northwest toward Future US 311 interchange with the I-74 Beltway showing future westbound lanes paved.
New Dillon Farm Road bridge being built over the Future I-74 Beltway.
Future on-ramp from US 158 to I-74 East with concrete plant currently in the middle of the interchange.
Future on-ramp from US 158 to East I-74 now paved.
Looking across to off-ramp to US 158 from Future I-74 West showing the installation of overhead guide signs at the end of the ramp.
Looking north across Future I-74 Beltway lanes towards US 158 showing overhead gantry ready for signage.
Closer look at new overhead signage at end of future ramp from I-74 West to US 158. Looks like the sign on the right is missing an arrow.
View looking west beyond US 158 along future route the I-74 Beltway from Old Belews Creek Road.
Looking along Future I-74 East from Old Belews Creek Road bridge showing newly placed overhead sign for US 421 exit (and back of sign for US 158 exit westbound).
Looking west from Old Belews Creek Road bridge toward newly placed overhead sign for US 158 exit and tab for all traffic exit above.
Looking south toward US 421/Salem Parkway interchange with overhead exit and ramp signs installed.
The first advance sign for the US 158 exit on Future I-74 West will be at the 1 3/4 miles, seen from the vicinity of West Mountain Street.
The next advance sign for US 158 is for 1 1/4 miles. The empty bracket to the right I assume is for a right lane ends advisory sign.
Earlier photos taken on July 1, 2019 by Site Contributor, J. Austin Carter:
Traffic on US 52 North heading under bridge carrying ramp from US 52 South to NC 66, the construction signs in the distance for project upgrading US 52 for future I-74/Winston-Salem Northern Beltway interchange.
US 52 North at exit ramp to NC 65 work on Future Winston-Salem Beltway interchange in distance that includes new NC 65 bridge being constructed behind old one across both lanes of traffic.
Work for future ramps for the I-74/Winston-Salem Northern Beltway interchange along US 52 North beyond the NC 65 exit.
Future ramps from the Winston-Salem Northern beltway intersecting US 52 North around the 1-Mile advance sign for the Westinghouse Road exit.
Now heading south on US 52 (Future I-74 East) looking toward the Northern Beltway interchange work zone after the NC 65 exit.
Closer view of the start of the construction area which involves moving the NC 65 exit ramp for US 52 South.
Looking towards the new lane for moved NC 65 exit and newly installed guardrail behind orange construction barrels.
While the new ramp to NC 65 is open, landscaping work continues along the roadway.
Former NC 65 exit ramp blocked off by temporary barriers prior to new NC 65 bridge over US 52.
A 1/4 mile advance sign for the left NC 66 exit sits before new longer and wider NC 65 bridge nearing completion over US 52/Future I-74. (The NC 66 ramp is the approximate location the future Beltway will cross US 52).
Earlier Photos taken on April 21, 2019 by Site Contributor, J. Austin Carter:
US 158 traffic using new bridge over Future I-74/Winston-Salem Beltway.
Looking south from US 158 bridge along future I-74/Beltway concrete roadbed. Work has started on landscaping along the sides of the roadway.
Further along the US 158 bridge looking east showing progress in completing Future I-74 roadbed.
Now looking directly east/south from US 158 bridge towards Walkertown Guthrie Road with Business 40/US 421 interchange beyond.
Looking at under construction roadbed north of US 158 bridge, this section still not paved.
A look north/west toward the future US 158 interchange and beyond from Walkertown Guthrie Road bridge.
Looking south/east along future Beltway lanes from Walkertown Guthrie Road bridge.
Looking west/north from Walkertown Guthrie Road bridge along future I-74 roadway back to US 158.
Going further east, looking north/west back toward Walkertown Guthrie Road bridge.
Now looking south toward the future Business 40/US 421 interchange showing the built up ground for future Beltway lanes.
Looking north/west along built up graded roadbed for future I-74 lanes leading up hill from Business 40/US 421.
Looking from top of hill south and east back over future Business 40/US 421 interchange.
Another view looking down at the future Beltway interchange showing future flyover ramps to current Business 40 East, Future US 421/Salem Parkway South.
Earlier photos taken on December 13, 2018 by Site Contributor, J. Austin Carter:
Business 40 to US 158 Segment:
Taken after a December snowstorm, the view from Business 40 East (Future US 421 Salem Parkway) of flyover ramp for I-74/Beltway interchange with bridges to carry I-74 over the highway in the distance.
Looking north at roadway under construction to connect to flyover ramp over Business 40 East.
Now looking south at ramp under construction to connect flyover bridge to Future I-74 lanes.
Closer look at ramp bridge over Business 40 East. Appears to be still significant work to do, one of the reasons the opening has been pushed back to the end of next year instead of April 2019.
Close view of I-74 bridges over Business 40 East, as with the flyover ramp, there's still a lot of work to do here also to complete the bridges.
Looking across the Business 40/US 421 West lanes toward the future I-74/Beltway still under construction. A noise wall is going up along the future ramp to I-74 West.
Another look at the interchange construction area from across Business 40.
A noise wall is being constructed along the future ramp from I-74 to East Business 40.
Moving north to the vicinity of E. Mountain Street, the roadbed for I-74 is being built up to meet the existing bridge.
Looking east at the built up roadbed in the vicinity of E. Mountain Street.
Looking further east back toward the Business 40/US 421 interchange area.
Now further north, looking west from Walkertown-Guthrie Road bridge towards the future US 158 interchange.
Now looking east from the same spot back toward Business 40/US 421.
Looking back west toward US 158 at another angle showing completed US 158 bridge and work started on the next section to US 311 beyond.
Looking at another angle to the east, a noise wall under construction can be seen after the curve in the distance.
Looking to the east from the completed US 158 bridge back toward Walkertown-Guthrie Road.
Sign on US 158 bridge heading east indicating dedicated to Officer Stephen Levi Amos II.
US 158 to US 311 Section:
Looking west from Williston Road near site of future bridge over the Beltway, looking towards US 311.
Looking east from current Williston Road over future bridge under construction over I-74/Beltway lanes.
Another view west from site of new Williston Road bridge under construction. Road in distance is US 311.
Looking east again, over the frame of the future Williston Road bridge to the I-74/Beltway lanes under construction.
Previous Photos taken on April 1, 2018 by Site Contributor, J. Austin Carter:
Looking south toward the future interchange with Business 40/US 421 showing little progress in grading the roadway but construction proceeding on a flyover ramp for the Beltway exit.
A closer view of the new flyover ramp at the future Business 40/US 421 interchange beyond the US 421 roadway.
Looking north or west along the future Beltway alignment toward West Mountain Street showing lack or progress in grading this part of the roadway.
View of the Beltway bridge over West Mountain Street, which appears to be mostly complete, except for final grading.
View of concrete Beltway roadbed from completed Walkertown Guthrie Road bridge.
Looking south or east along the Beltway from the Walkertown Guthrie Road Bridge showing progress in grading along the roadbed completed the year before.
Looking north/west toward the future US 158 interchange from Walkertown Guthrie Bridge showing progress in extending the concrete roadbed toward the exit, some landscaping and on US 158 itself the construction of bridges to take the final alignment of the highway over I-74.
Previous Photos taken on October 11, 2017 by Site Contributor, J. Austin Carter:
Looking northwest toward US 158 from completed Walkertown-Guthrie Road bridge over Future I-74. There has been significant progress with placement of the concrete road bed.
A closer look at the new concrete roadbed for Future I-74 from Walkertown Guthrie Road looking towards the future US 158 interchange.
Looking now southeast from the completed Walkertown Guthrie bridge along I-74 roadway headed toward Business 40 showing progress in completing road surface.
Traveling south to near Business 40, view looking northwest toward bridge under construction over Mountain View Rd.
Closer look at progress grading Future I-74 Roadbed heading northwest toward bridge over Mountain View Road.
Looking south toward Business 40/US 421 showing grading underway for Future I-74/Beltway interchange.
Earlier Photos taken on April 13, 2017 by J. Austin Carter:
View of paved Future I-74/Beltway lanes just south of US 158.
Looking north toward US 158 across the future interchange construction zone, including the temporary concrete plant between the original and current US 158 alignment.
View southeast from completed Walkertown Guthrie Bridge over now paved Future I-74 East lanes.
Now looking north along graded Future I-74 lanes toward the nearly completed West Mountain Street and Railroad Bridge (photos of bridge below).
View looking south toward Future I-74/Business 40 (US 421 Salem Parkway) and progress in constructing the interchange (photos from Business 40 below).
Recent Photos taken on March 30, 2017:
Looking west Business 40/US 421/NC 150 entering the Winston-Salem Beltway construction zone.
Approaching site of future I-74/Beltway interchange with Business 40 showing clearing and early structure construction.
Still continuing west and approaching the grading to support future I-74/Beltway Bridges over Bus. 40/US 421/NC 150.
A closer look at construction going on to the south of the Eastbound lanes on Bus. 40/US 421/NC 150.
Looking north from Bus. 40/US 421/NC 150 along Future I-74/Beltway alignment showing construction of support structures for future bridges.
A closer look at the buildup of soil for the future crossing of I-74 West then I-74 East lanes over Business 40/US 421 and NC 150.
Heading now east on Bus. 40/US 421/NC 150 approaching the I-74/Beltway construction zone.
Looking northwest over Bus. 40/US 421/NC 150 at construction crane at site of future I-74 bridges.
Now further north, heading east on West Mountain Street approaching bridges being built to carry I-74/Beltway traffic over the roadway and railroad tracks.
Now on the east side of the bridge looking back from church parking lot on the old alignment of West Mountain Street, showing support structures for bridges largely in place.
Looking across both old and new alignments of West Mountain Street showing construction to complete grading of the I-74 lanes going on south of the bridges.
Looking west down railroad tracks showing bridge crossing both the tracks and the new alignment of West Mountain Street.
A closer look at the northern end of the bridge above what was the old alignment of West Mountain Street and showing further fill is needed before lanes can be paved to meet the bridge structure.
Now at the northern end of the project, looking west along US 158 approaching the interchange construction area. US 158 traffic has been realigned to the south through the work zone.
Further west on US 158 in construction area showing work has largely been completed in creating elevated areas for Future I-74 bridges.
Looking north of US 158 in the construction zone showing future ramp concrete structures covered over by tarps.
Now heading back east on US 158 looking down the hill to the Beltway interchange construction area showing how US 158 has been re-routed around the work zone.
Looking from south of US 158 at temporary concrete plant built in the future interchange work zone.
Looking south from US 158 over the alignment of I-74/Winston-Salem Beltway showing grading being completed.
Another view of the temporary concrete plant just east of the future I-74/Beltway lanes being graded south of US 158.
Here are a few photos of construction progress on the first segment of the Beltway taken by J. Austin Carter on August 27, 2016:
One of the many road closed barriers placed along residential streets along the corridor of the Northern Beltway due to the road's construction.
Future Beltway section being graded between Business 40 and US 158.
Part of newly constructed part of Beltway showing built-up roadway.
From West Mountain Street portion of new bridge being constructed for Beltway near temporary cement plant.
Looking at massive clearing and earth moving being done at site of future interchange between the Beltway and US 158, seen in the distance.
Future bridge being constructed along path of Northern Beltway.
View from bridge under construction shows the amount of earth moving being done along the I-74/Beltway corridor south of US 158.
Closer look at same bridge showing deck under construction over future Northern Beltway/I-74 near US 158.
Another scene of grading for future Beltway lanes east of Winston-Salem, here the future eastbound lanes are further along than the west.
Beltway construction being threaded between houses, seen in the middle and right.
A closer view of construction at the northern end of the project for the future interchange with US 158.
Here are a few more photos of construction progress on the first segment of the Beltway taken by J. Austin Carter on April 19, 2016:
Looking along West Business 40 showing clearing progress for future Beltway interchange.
Looking at construction crews working just north of Business 40 on Future Northern Beltway interchange.
Looking across Business 40 to view clearing for the interchange going on to the south.
Work is seen progressing in building future bridge supports and concrete pipes are ready for placing for site drainage.
Looking further north showing cleared corridor for I-74/Northern Beltway's path toward US 158.
Here's some previous photos taken by J. Austin Carter on December 14, 2015:
1. US 52 South from Westinghouse Road to NC 74 East
2. US
52 South through the project work zone from Westinghouse Road to
Hanes Mill Road
3. US 52 North through the project work zone from Hanes Mill Road
4. NC 74 Beltway from US 421 to US 52 North
Construction along and between I-40 and I-74
Traveling NC 74 West, including new section between NC 66 and US 52
NCDOT plans to build the Eastern Half of the Northern Beltway in 7 segments. The latest segment to have plans released is for the section from I-40 to the I-74 'US 311' Freeway, a contract let in October 2022. The plans indicated new exit numbers for US 52 (though not to be signed as I-74 quite yet), see I-74 Segment 3, and also for the exit off of I-77, see I-74 Segment 1. They also posted previous sign plans for the Beltway itself and for new exit numbers for the Future NC 192 freeway, now part of I-74 Segment 5. Here are a few examples of plans showing the changing of NC 74 to I-74 when the project is completed in 2026:
The current NC 74 related signage at ramps, such as this on US 158 West, will have East (or West) I-74 signs installed.
Plan of signage for US 52 North for Beltway exit prior to the signing of I-74 on it.
Signs to be placed along US 52 North at the Beltway interchange prior to I-74 being signed along it in 2026. Note the exit number on US 52, 117, the next exit NC 65 is Exit 118.
Current and replacement signage along US 421 South for when the Beltway is completed.
At the current other end of the Beltway current and future signage along US 421 South, Salem Parkway East.
Future signage along US 421 North, Salem Parkway west.
Signage at the future ramp to I-74 East along US 421 North.
Signage on I-40 West approaching future I-74/Beltway interchange.
Future signage in I-40 West at the Linville Road exit (notice the error in the exit tab, going west it should say Exit 227 B-A).
EARLIER PLANS
Here are earlier plans released for the US 421/Salem Parkway to I-40 contract let on December 21, 2021. The sign plans here include some of the signs to be featured in the last segment from I-40 to what the existing I-74 (Former US 311) freeway. Here's a sample of the exit signs, headed west to east:
The 1/4 Mile advance sign for the US 421/Salem Parkway exit. There will be auxiliary signs for the parkway itself.
The 1/2 mile advance for the next exit headed east, Kernersville Road.
The 1/2 mile advance for the I-40 exit headed east. There will be a C/D ramp for the eastbound exits, but not for traffic headed west.
Overhead sign plans for separate exit ramps for I-40 on the Beltway headed west.
The sign plans also included an exit for the last segment of the Eastern Beltway to be constructed:
The 1/4 Mile Advance sign for NC 192 East which will be the new route number for the current I-74 west of the future Beltway interchange.
This sign placement plan shows how close the I-40 exit will be to the end of the Beltway at current I-74.
Based on ramp sign and mile marker plans, it appears I-74 will be signed along the Beltway when it is completed to I-40:
Plan for overhead ramp signs along Kernersville Road have I-74 shields, not reference to NC 74. Notice also that the control city for I-74 West in Wytheville VA, not Mount Airy, currently the control city along US 52 North in Winston-Salem.
Plans for 1 and 1/2 mile markers show inclusion of I-74 shields.
Posted plans also included those along I-40 which also refer to I-74, not NC 74:
The plans for the overhead signs at the C/D ramp for the future I-74 Beltway exit on I-40 East. Notice the exit number discrepancy, 2 miles between Exits 201 and 198, not the biggest one, see below.
The sign plans on I-40 West feature a 1 mile gap between Exits 201 and 198.
Here's a plan of the signage at the split of ramps from I-40 to the I-74 Beltway (similar signage with an I-40 shield is on the C/D ramp from the Beltway headed east.
Here's what the current I-74 East signage on I-40 West will look like once the Beltway is completed:
Plan for the 2 Miles advance sign on I-40 West. The plans for I-40 East were not included, perhaps it will say "To I-74 East" unless they would prefer traffic to use the Beltway ramps.
MORE EARLIER SIGN PLANS
Based on a public relations request, AARoads Forum member Roadsguy obtained copies of the plans from NC 66 to US 311 and was kind to forward them to me. The plans featured updated signage for Exits 49 and 50 on I-74 East for when the Beltway opened west of US 311:
NEW-11/15/24 As can be seen on the US 311 sign, a future overlay with North is provided, indicating NCDOT was planning to further shorten the route's length, this time eliminating the route between the Beltway and US 52 in Winston-Salem. NCDOT received approval to do this at the Fall 2024 AASHTO meeting. There is no word yet on when the truncation will happen.
The plans for the exits between Baux Mountain Road and NC 66 match those of the signs seen in the photos above.
The plans for the NC 66 exit also show what the future I-74/US 52 interchange signage will look like when the ramp to US 52 South opens, and later when the western section of the Beltway is completed:
Note the To NC 65 included with the US 52 South exit. There will be no direct connection from I-74 to NC 65.
Plan for future ramp signage once I-74 is signed along the Beltway:
Plans for the second segment, from US 158 to US 311 were put on NCDOT's website on August 22, 2017, with a letting in October. The second segment will run almost 2 miles. Here's plans showing the new exit number for the US 311 exit:
Sign plan for US 311 interchange westbound at US 158 exit (already existing from previous contract, see plans below) showing it will be designated Exit 49.
Plan for new arrow-per-lane sign to be placed at US 158 exit when I-74 is completed east to US 311. Notice the lack of reference to Business 40 (seen on the earlier plan below) on the US 421 sign. In the spring of 2017, NCDOT announced that the official name for the Business 40 route in the future will be the US 421 Salem Parkway, implying that the Business 40 designation will be dropped.
Plans for construction of the first segment of the Beltway were put on NCDOT's website on August 19, 2014 as advertising for the project letting on October 21. The first segment will run 3 miles between Business 40/US 421 and US 158, Reidsville Road it will also include the building of approximately 1 mile of the Loop further eastward toward I-40 that will be completed in the future. The signing plans indicate the route will be temporarily signed as NC 74, until the route is connected to at least I-40. The NC 74 signs can be seen in this plan for the initial signage at the Business 40 exit:
Plan for signage on Business 40 East, showing temporary NC 74 designation, to be changed to I-74 when Loop is, at least, partially completed east to I-40.
Initial and future signs for I-74 East at the Business 40/US 421 Exit. Since these plans were published, NCDOT has announced it will remove the Business 40 designation from what will be called the US 421 Salem Parkway around 2020.
Signage plans for the US 158 exit ramp signage to I-74 East.
Signage planned for I-74 West at the US 421 interchange.
Plans for signage approaching I-74 along US 421 North at South Main St in Kernersville, the exit number is now 227.
Route shields to be featured on this segment of the Beltway. Though the signs for the Business 40 exit do not included NC 150, which is routed on the highway along with US 421, the ground signage still indicates its presence. Again, the plan is for the Business 40 designation to be removed from US 421 in 2020.
The plans indicate that the exit numbers along this segment will be 53 A&B for US 42 and 50 for US 158. The sign plan for the next segment to be constructed, from US 158 to US 311, indicates that US 311 will be Exit 49.
Improving
News for Eastern Section Construction in recent years
The remaining segments of the Beltway were unfunded, and their construction dates uncertain, until December 2014. That month NCDOT released their latest draft State Transportation Improvement Program (STIP) document, formally approved in June 2015, which listed all funded projects in the state from 2016 to 2025. In the 2018-2027 STIP released in August 2017, among Forsyth County projects to be funded, included all of the remaining six Beltway segments. Next in line was (Segment C) the 1.4 mile US 158 to US 311/Walkertown Road segment which was awarded on December 6, 2017 at a cost of $68 million, work started in January 2018 with a planned completion by November 2021.12 The two segments (AA and AB) to connect these completed Beltway segments to I-74/US 311, from Business 40/US 421 to I-40 and from I-40 to I-74/US 311, will together cost $273 million and will start in 2020 and 2021. Contracts for the other 3 segments, unfunded in the previous TIP, D, US 311 to Baux Mountain Road, E, Baux Mountain Road to NC 8, and F, NC 8 to US 52, all Design-Build projects, were put out to bid in March 24, 2018, delayed 5 months in October 2017, funded due to reforms to the 2015-17 state budget that added over $700 million in new moneys for transportation over the next two years, work is to be completed in 2021.14 A contract which will build the Beltway interchange with US 52 was let in August 2018, work then start in November 2018 with the project originally set to be completed in September 2022, now in the fall of 2023.4
The project has been further accelerated since, with work starting on the 2 mile section from US 158 to US 311 on January 20, 2018 with completion in December 2020.6 The letting of the remaining projects from US 311 to US 52, design-build contracts covering 6.9 miles from US 311 to just east of US 52 was delayed until March 2018, work started in April 2018 and the road opened to NC 66 in November 2022.
For the latest official information on the Beltway, go to NCDOT's Winston-Salem Northern Beltway project page.
*In November 2004, NCDOT released, as part of its Strategic Highway Corridors initiative, a map of existing and proposed Triad area highways showing an I-285 extending from I-85 in Lexington to I-40 in Winston-Salem with a note saying it would be extended to I-74 if US 52 was upgraded to interstate standards.18 Finally, in 2019, I-285 from I-85 to I-40 was signed, after all projects to upgrade the highway to interstate standards were completed. In May 2019, NCDOT got permission from AASHTO to designate US 52 from I-40 to the future Northern Beltway interchange as Future I-285. It is unknown at this time when projects to upgrade this part of the highway will be funded. For more information, visit my Future I-285 page.
**On the same SHC Triad map19 the western half of the Beltway, from US 52 (I-74) to I-40, is signed as:
(information on I-274 is on the Winston-Salem
Northern Beltway main page.)
***There seems to have been some confusion over the years as to the actual Eastern Beltway mileage. The 2004-2010 STIP listed the distance for the Beltway from US 52 to I-40 as 12.6 miles and the extension to US 311 as 1.6 miles (for a total of 14.2 miles). Then the subsequent STIP listed the entire length as 12.6 miles (used in the map below). The Strategic Corridors list says the total mileage is 16.2. A 2006 newspaper article listed the distance as 17.4 miles. The 2009-2015 STIP listed the project distance from US 52 to I-40 as 14.3 miles. The Draft STIP released in December 2014 and all subsequent STIPs, lists the combined mileage for projects U-2579 and U-2579A as 17.1 miles, so this is the mileage number I am using.
If anyone else has photos of the current roads in the vicinity of this segment, feel free to E-mail me.
A detailed map from 1999 showing part of the proposed I-74 route between Bus. 40 and US 311 in more detail: