Image of NC I-73 Shield, from Shield's Up! Segment 4

Portion of NCDOT 2021-2022 State Transportation Map Triad Inset showing path of I-73 along Bryan Blvd. in Greensboro

Where:  'I-73 Connector', and Bryan Blvd. from NC 68 to Greensboro Urban Loop (Future I-73/I-840)

Length:   4 Miles

Completion Date: July 2, 2017*

(*Segment from Loop to PTI Airport was Completed in 2009)

Jump to Construction Photos

Segment Info

I-73 travels on the 'I-73 Connector' from the 'NC 68-US 220 Connector' over another new alignment paralleling NC 68 south for a mile before traveling across that route and heading east for 3 miles to reach the I-840/Greensboro Urban Loop. This route replaced the original path of I-73 which was to follow an upgraded NC 68 to I-40 (see Segment History section below). The segment was constructed in two parts. Pre-existing Bryan Blvd. from the Loop to the PTI Airport exit was reconstructed to an interstate standard freeway between 2006 and 2009 (which included removing an exit to Inman Road just west of the Loop with a new bridge to constructed for that roadway later). The remaining section was to be built in 2016 once the modification of PTI Airport to serve as a FedEx Hub was completed. However, it was announced in late May 2013 that the timetable for construction of the I-73 Connector had been moved up to the Spring 2014, pending the completion of an environmental assessment by URS Corp. The I-73 construction project (Tip No. I-5110) would include building an additional taxiway for PTI Airport and developers of land adjacent to the airport, that could only be reached by the new taxiway, urged the timing of the project to be sped up so not to lose out on proposals by major manufacturing companies to build there. The NCDOT spokesman at the time indicated if the project started on schedule, it could be completed during 2015.12 In September 2013 NCDOT posted the letting list for its Design-Build Projects over the next year. The I-73 Connector project was now combined with the project to build the 'NC 68-US 220 Connector', TIP Project R-2413, Parts A and B, and the combined design-build contract was let in April 2014 and work started in early May. The project was awarded to a joint venture of  Flatiron Constructors and Blythe Development Co. for $176.6 million. The completion date for the entire project (from PTI Airport to US 220) was listed as October 2017.13 However, in January 2016, NCDOT officials indicated that the later date was for the taxiway not I-73, and that they planned to open the entire stretch of I-73 from the Airport to US 220 (see Segment 3) by the end of 2016.14 However, work and weather delays moved the final completion date for the I-73 Connector to July 2, 2017.15 A separate project to complete final upgrades to the Bryan Blvd/Greensboro Loop interchange was announced on July 9, 2015 (work that was originally part of the I-73 Connector project contract, but separated out before that was awarded). Work continued on updating signage into 2018. The project, awarded to Flatiron/Blythe for $5 million, began on September 8, 2015 and was competed in October 2016, with the exception of remaining work needed on the southbound ramp to I-840 along with planting, reforestation and permanent vegetation with the ramp work supposed to be completed as of late November 2016. In May 2016 the new Inman Road bridge was completed, and was opened to traffic in June 2016.16 The only other changes that have occurred since the road opened was the alteration of signage for the Greensboro Urban Loop after it was completed in July 2023. Plans for sign changes can be seen in Segment History section below, as well as recent photos in photos section.

"Drive" This Segment with Videos from RoadwayWiz made in the Summer of 2021

I-73 South from Exits 117 to 107 (Includes Segment 3)      I-73 North from Exits 107 to 117 (Includes Segment 3)


"Drive" This Segment Using Google Maps Street View

I-73 South: Heading under PTI Airport Taxiway Bridge prior to Airport Exit.

I-73 North: Merging with Bryan Blvd. from Greensboro Loop.

Segment Photos - Hover Over for Larger Size

Most Recent Photos taken by Strider along I-73 South in August 2023:

Image of 1 1/4 Mile advance sign for Greensboro Loop exit with new I-785 shield, replacing US 220 due to earlier 
        completion of Loop on I-73 South, photo by Strider, August 2023First advance sign for the Greensboro Loop at he PTI Airport exit with the addition of an I-785 shield, replacing US 220.


Image of 1/2 Mile advance sign for Greensboro Loop exit with new I-785 shield, replacing US 220 due to earlier 
        completion of Loop on I-73 South, photo by Strider, August 2023The 3/4 mile advance APL sign for the Bryan Blvd./Greensboro Loop split with addition of another I-785 shield.


Image of overhead ramp signage for Greensboro Loop exit with new I-785 shield due to earlier 
        completion of Loop on I-73 South, photo by Strider, August 2023The APL at the Greensboro Loop exit with addition of I-785 shield.


Image of overhead ramp sign for Greensboro Loop exit north with new I-785 shield and Raleigh control
        city due to earlier completion of Loop on I-73 South, photo by Strider, August 2023The exit sign for the I-840 West section of the Greensboro Loop has the addition of Raleigh as well as an I-785 shield.


Earlier Photos along I-73 North by Site Contributor, David Johnson in May 2019:

Image of overhead signage approaching Old Oak Ridge Road/PTI Airport exit on I-73 North in Greensboro, by David JohnsonOverhead signage on I-73 North/Bryan Blvd. approaching the Old Oak Ridge Road/PTI Airport exit.


Image of North I-73 reassurance marker along Bryan Blvd prior to Old Oak Ridge Road/PTI Airport interchange in Greensboro, by David JohnsonThe North I-73 reassurance marker following the merge with Bryan Blvd appears about 1/2 mile before the Old Oak Ridge Road/PTI Airport exit. On-ramp is original ramp from Old Oak Ridge Road.


Image of overhead signage for Old Oak Ridge Rd/PTI Airport exit on I-73 North after on-ramp from Old Oak Ridge Rd, by David JohnsonNext set of overhead signage and beginning of Exit Only Lane for Old Oak Ridge Road/PTI Airport exit on I-73 North.


Image of C/D ramp signage from I-73 North along lanes for Old Oak Ridge Road/PTI Airport exit in Greensboro, by David JohnsonSignage along C/D lanes for Old Oak Ridge Road/PTI Airport exit as seen from I-73 North lanes.


Image of ground mounted 1-mile advance sign for NC 150 South exit on I-73 North in Greensboro, by David JohnsonAlmost hidden by trees, the 1-Mile Advance sign for the NC 68 South exit.


Image of PTI taxiway bridge over I-73 North after 1/2 mile advance overhead sign for NC 150 South exit on I-73 North in Greensboro, by David JohnsonView of PTI Airport Taxiway Bridge over I-73 North lanes prior to NC 68 South exit.


Image of closeup view of PTI taxiway bridge of I-73 North in Greensboro, by David JohnsonA closer view of he Taxiway bridge and PTI Airport logo inserted into the bridge structure.


Image of overhead signage at ramp to NC 68 South on I-73 North in Greensboro, by David JohnsonThe overhead signs at the ramp to NC 68 South from I-73 North.


Image of North I-73 reassurance marker following off-ramp for NC 68 South exit in Greensboro, by David JohnsonThe North I-73 reassurance marker after the NC 68 South exit.


Image of overhead ramp sign for NC 68 North exit on I-73 North in Oak Ridge, by David JohnsonThe overhead ramp sign for the NC 68 North exit entering the city of Oak Ridge.


Earlier Photos, NCDOT finally added mile markers along the I-73 Connector in early March 2019, Photos by Strider:

Image of newly placed Mile 108.5 marker on I-73 North at start of PTI Airport exit off-ramp in Greensboro, by StriderNewly added mile marker on I-73 North at off-ramp to PTI Airport in Greensboro. The marker confirms the PTI exit number of 109 is correct, that mile marker by the interchange bridge in the distance.


Image of newly placed mile marker on I-73 South by PTI Airport exit onramp in Greensboro in March 2019, by StriderHeading southbound the marker for the same distance in the other direction, after the PTI Airport exit on-ramp. The markers continue along the ramp from the Connector to the Greensboro Loop.


New photo by Strider of new signage at exit from PTI Airport to I-73/Bryan Blvd. taken in February 2019:

Image of recently added overhead signage along PTI Airport exit road for I-73/Bryan Blvd., by Strider in Feb. 2019New overhead signage shows how this section of I-73/Bryan Blvd got its name as a connector between NC 68 and I-840. Only 1 of the control cities on the sign (Greensboro) can currently be reached using I-73.


Earlier photos taken of new I-73 signage around newly opened I-840 Segment at Bryan Blvd, taken by Strider in May through August 2018:

Image of recently placed I-73 North guide sign on overhead gantry at PTI Airport exit in Greensboro, by StriderI-73 North pull through sign at the PTI Airport exit (don't know when the exit sign will be modified to reflect the new airport name-Central North Carolina).


Image of new overhead signs approaching the I-73/I-840 Greensboro Loop on Bryan Blvd west, by StriderRecently placed advance overhead signage on Bryan Blvd heading west toward the Loop interchange, supplementing the ground mounted sign seen below.


Image of recently placed 3/4 mile overhead advance sign for Bryan Blvd exit on I-73 South at I-840 Greensboro Loop, by StriderThis overhead arrow-per-lane 3/4 Advance sign for Bryan Blvd. on I-73 South approaching the I-840 Greensboro Loop was put up in July.


New exit sign for I-73 North on Bryan Blvd. heading west toward the I-840 Greensboro Urban Loop, by StriderOn the other side of the Loop, this sign was put up on Bryan Blvd. heading west for I-73 North approaching I-840.


Image of not yet placed overhead Arrow-per-lane sign for I-73 South/Bryan Blvd exit, by StriderNew Arrow-per-Lane (APL) sign for Bryan Blvd exit at I-840 Greensboro Loop on I-73 South awaits placement on May 17.


Image of new Arrow-per-Lane sign placed on I-73 South for Bryan Blvd exit at I-840 Greensboro Urban Loop, by StriderFirst of two now placed overhead APL signs on I-73 prior to Bryan Blvd and the newly opened segment of I-840 Greensboro Loop to US 220.


Image of second new arrow-per-lane sign placed on I-73 South for Bryan Blvd exit at I-840 Greensboro Urban Loop, by StriderThe second of the new APL signs just prior to the exit ramp.


Image of newly placed overhead sign at Fleming Rd exit on Bryan Blvd West for I-73 and newly opened section of I-840 Greensboro
      Urban Loop, by StriderOn the other side of the Loop interchange is this new overhead sign for I-73 and I-840 on Bryan Blvd. west at the Fleming Road exit.


Photos taken of new I-73 signage around PTI Airport, taken by Strider on August 11, 2017:

Image of new overhead signage at ramps from Old Oak Ridge Rd to PTI Airport and I-73 North, by StriderNew overhead signs at the ramp leading from Old Oak Ridge Road splitting traffic bound for PTI Airport from I-73 North (the TO NC 68 explains why  you are directed to north to get to High Point).


Image taken of signage along PTI Airport roadway directing traffic to Old Oak Ridge Rd and Bryan Blvd, by StriderSignage leaving the Airport directing traffic to Old Oak Ridge Rd or Bryan Blvd/I-73.


Image of overhead signage for I-73 and Old Oak Ridge Rd leaving PTI Airport, by StriderNew overhead signs leaving PTI Airport at the ramp to Old Oak Ridge Road.


Image of overhead signage at split of ramp from PTI Airport to I-73 North or South, by StriderSignage at split of ramps for traffic exiting PTI Airport to either I-73 North to NC 68 or South to I-840 (Greensboro Loop).


Photos taken by Strider on July 18:

Image showing newly placed North I-73 reassurance marker on Bryan Blvd after Greensboro Loop exit ramp, by StriderNewly placed I-73 North trailblazer after Loop interchange on-ramp.


Image of newly placed NC 73 North 1/2 mile advance sign replacing portable VMS on I-73 North near Oak Ridge, by StriderThe 1/2 mile advance sign for the NC 68 North exit was finally placed a week after the road opened, replacing the portable VMS version.


Image of overhead signage at end of I-73 North Exit ramp to NC 68 near Oak Ridge, from StriderOverhead signage at bottom of ramp from the NC 68 North exit from I-73 North.


Image of overhead signage form Pleasant Ridge Rd intersection on NC 68 South, by StriderOverhead signage on NC 68 South for Pleasant Ridge Road put up between I-73 exits.


Photos taken by Strider and LC between July 1 and 3, 2017 just prior to and just after opening of I-73 roadway:

Image taken of ramp to Future I-73 South roadway from NC 68 North in Greensboro, by StriderView taken day before opening of I-73 from completed ramp from NC 68 North to I-73 South.


Image of ramp from NC 68 North to Future I-73 South near PTI Airport in Greensboro, photo by StriderFurther up the NC 68 North on-ramp showing signage for the PTI Airport exit on the unopened I-73 South lanes.


Image taken of signage on NC 68 North in Greensboro for newly opened I-73 Segment by PTI Airport, by StriderNew overhead sign on NC 68 North at former Bryan Blvd PTI Airport exit now indicating airport traffic should use just opened section of I-73.


Image taken of newly uncovered I-73 South overhead sign before ramp from NC 68 North in Greensboro, by StriderApproaching newly opened ramp to I-73 South from NC 68 North.


Image of new I-73 South roadway and 1/2 mile exit sign for PTI Airport in Greensboro, by StriderThe first exit sign after on-ramp from NC 68 North is the 1/2 mile advance for PTI Airport/Old Oak Ridge Road on the other side of the Taxiway Bridge.


Image taken of I-73 South roadway traveling under PTI Airport Taxiway Bridge, by StriderNow about to travel under PTI Airport Taxiway Bridge on newly opened section of I-73 South.


View of first Greensboro Loop exit sign approaching PTI Airport exit on I-73 South in Greensboro, by StriderApproaching the PTI Airport exit, and the first overhead signs for the approaching Greensboro Loop exit (the US 220 signs, according to sign plans, are supposed to be covered over until the I-840 section to the north is complete).


Image of gore sign for PTI Airport exit on newly opened section of I-73 South in Greensboro, by StriderThin gore sign at exit ramp to PTI Aiport/Old Oak Ridge Road on I-73 South.


Image of new overhead signs to direct traffic on PTI Airport exit from I-73 South in Greensboro, by LCFrom I-73 South, overhead signage directing traffic on the new PTI Airport/Old Oak Ridge Road exit.


Image of overhead signs after PTI Airport exit on-ramp to I-73 North in Greensboro, by LCNow turning around and driving on I-73 North, view of overhead signs prior to the PTI Airport/Old Oak Ridge Road exit and lane drop after Greensboro Loop on-ramp merge.


Image taken along on-ramp from PTI Airport exit to new section of I-73 North in Greensboro, by LCView starting the new section of I-73 North prior to the merge, on other side of barrier, of on-ramp from Old Oak Ridge Road and PTI Airport.


Image of I-73 North roadway, just opened, heading toward PTI Airport Taxiway Bridge in Greensboro, by LCHeading onto new section of I-73 North toward PTI Airport Taxiway Bridge.


Image taken of newly opened section of I-73 North traveling under PTI Airport Taxiway Bridge prior to NC 68 South exit in Greensboro, by StriderNow about to go under Taxiway bridge again approaching NC 68 South exit.


Image taken heading under PTI Airport Taxiway Bridge on I-73 North in Greensboro, by LCView traveling under the PTI Airport Taxiway Bridge on I-73 North.


Image of view taken looking back at PTI Airport Taxiway Bridge over I-73 North in Greensboro, by StriderLooking back along I-73 North toward the Airport Taxiway Bridge prior to the NC 68 exit.


Image of newly opened I-73 North roadway and variable messgage sign prior to NC 68 South exit in Greensboro, by LCView on other side of Taxiway Bridge showing VMS sign in median and marked lanes from NC 68 South exit.


Image taken of overhead exit signs for NC 68 exits on newly opened segment of I-73 North in Greensboro, by LCOverhead exit signs for both NC 68 exits on I-73 North. The NC 68 South exits has two lanes, I-73 turns north prior to the second exit.


Image taken of new I-73 North roadway approaching NC 68 South Exit Ramp bridge in Greensboro, by LCFurther down I-73 North approaching the bridge carrying NC 68 South traffic over I-73.


Image taken of I-73 North roadway curving on bridge taking it over NC 68 in Greensboro, by StriderI-73 North beginning its turn to parallel NC 68 after crossing over bridges before NC 68 North exit.


Image taken of portable Variable Message Sign acting as NC 68 North exit sign on I-73 North in Greensboro, by LCPortable VMS being used as temporary 1/2 Mile Advance sign for NC 68 North exit at Mile Marker 111.


Image taken of NC 68 roadway traveling under newly opened I-73 North near Oak Ridge, by LCLooking over I-73 North bridge toward NC 68 roadway and interchange below approaching exit ramp.


Image taken of overhead exit sign for NC 68 North exit approaching city of Oak Ridge on new segment of I-73 North, by StriderExit sign for NC 68 North Oak Ridge exit approaching end of newly completed segment of I-73


Image taken at bottom of ramp from newly opened I-73 North to NC 68 in Oak Ridge, by StriderView from bottom of exit ramp from I-73 North to NC 68 North, traffic can also take a left onto NC 68 South.


Image taken of overhead signs for I-73 on-ramps from NC 68 South in Oak Ridge, by StriderOverhead signage on NC 68 South for I-73 North and South ramps, both to the left.


Image taken of overhead exit sign for NC 68 South exit from newly opened segment of I-73 South in Greensboro, by StriderHeading back on I-73 South crossing NC 68 again and approaching NC 68 South exit.


Image taken of newly opened I-73 South approaching exit signs for NC 68 South and PTI Airport in Greensboro, 
      by StriderFurther south on new section of I-73 South approaching the NC 68 South exit and first sign for the PTI Airport/Old Oak Ridge Road exit.


Image of exit signage at NC 68 South interchange with newly opened I-73 South in Greensboro, by StriderOverhead signage for NC 68 South and PTI Airport/Old Oak Ridge Road at Exit 110 off-ramp.


Segment History

Original I-73 Routing Plan

The routing of this segment has changed since plans for I-73 were first proposed. Initially it was assumed I-73 was to be routed onto NC 68 south from the end of the NC 68-US 220 connector to I-40. Though NC 68 is a divided highway for this entire length, it is not actually a freeway for 1/3 of a mile between the I-40 interchange and the Triad Center Drive intersection (which has a stoplight). The freeway portion north of there is also not up to Interstate standards with narrow shoulders and insufficient ramp acceleration and deceleration lanes. The current interchange between NC 68 and I-40 would also have had to be vastly upgraded, something not done when I-40 was widened a few years ago.

Impetus for Routing Change

In May 2003, the Greensboro Urban Area Metropolitan Planning Organization announced major highway planning initiatives around the Piedmont Triad International Airport (PTIA). Their proposals included a new 6-lane freeway to start at a relocated Bryan Boulevard and running to the proposed eastern half of the Winston-Salem Northern Beltway (later dubbed the I-73/74 Connector, listed as an unfunded project in the 2009-2015 STIP) with an additional spur leading to I-40 west of Greensboro at the split of Interstate 40 and Business 40 and a new I-73 routing which, from the NC 68-US 220 connector, put I-73 briefly onto NC 68 and then onto Bryan Boulevard (the western part to be relocated due to the need for a new airport runway for the FedEx hub facility) to the Greensboro Urban Loop freeway (I-840). (For a map of these proposed highways and more about this Future NC Interstate, go look at my NC Future Interstates Site). The impetus for this new route was to avoid the expensive reworking of the NC 68 interchange with I-40 and to take I-73 traffic off of I-40 between Winston-Salem and Greensboro.1,2 In August 2003, NCDOT added all the Greensboro MPO PTIA area highway proposals to its list of Division projects, committing state funds to more fully study the proposals, and build them once approved.

Plans Affected by New Interchange Built for PTI Airport

In March 2004 NCDOT let the $44.3 million contract for the construction of the Bryan Boulevard relocation and the PTI Airport Authority gave permission to the contractor to start construction on April 23, 2004.3,4 The relocated highway opened in November 2006 and included a new, temporary, entrance to the airport. Eventually by the time the Hub opened in 2009 a permanent airport interchange involving four bridges and nine ramps was completed to connect Bryan Blvd to the PTI terminals.5 (The other roadways proposed by the Greensboro MPO, if built, won't be constructed until at least 2020.)

New I-73 Routing Plan Studied by NCDOT

Though NCDOT never announced a change in I-73's route, maps put out by NCDOT, both for their Strategic Highway Corridors initiative and regarding their US64/NC 49 corridor study showed Bryan Blvd between NC 68 and the Greensboro Loop as I-73. (To look at a Loop map and other connected projects,go to the NCDOT project map). And it was also shown in the map above from a report on the economic benefits of I-73 and I-74 (see the I-73/I-74 Links page), which says the routing information came from NCDOT. The 2009-2015 STIP, however, only listed a feasibility study in progress (Number FS-0507A) "To Determine Routing of Future I-73 in the Greensboro Area."6 At a June 2005 meeting in Greensboro when NCDOT announced the start of this study they said it could take two years to complete and would involve looking at four 15-mile corridors (two of which a spokesman said were almost likely to be ruled out, one of which was a route using US 220 south of Summerfield to the Greensboro Loop that would have required cutting through some of Greensboro's water supply lakes, the other was probably the routing along NC 68 to I-40), up to three miles of which would involve new construction. Greensboro officials stated at the time that they would like the study completed sooner, since the building of the FedEx hub had increased development pressures in the area and they would like to know as soon as possible what land should be preserved for I-73.9 The study was to produce a recommendation by July 2007, however, no formal announcement was ever made, and the feasibility study was still listed in the 2007 STIP.

New I-73 Routing Plan Eventually Revealed

A newspaper article in early August 2007 indicated that it was 'likely' I-73 would be routed on the Greensboro Urban Loop from US 220 to Bryan Blvd, as depicted in previous NCDOT documents.(7) At a public meeting in Summerfield later in September 2007 NCDOT officials discussed the two options for an I-73 interchange with NC 150 before local residents. This would only be needed if I-73 would be using the NC68-US 220 Connector.8 Finally, signs put up along the completed Greensboro Loop section in December 2007 referred to the route as either 'Future I-73/I-840' or 'I-40/I-73,' clinching the new route as official (see photo in Segment 5). Signs on Bryan Blvd at the the Loop interchange, however, only indicated 'To I-40, Winston-Salem.' A photo below shows that the new road built near the future Airport interchange may be up to Interstate standards, the interchange will be around the corner where a traffic lighted intersection currently exists. The roadway beyond the lights to the Greensboro Loop interchange appears to be built to interstate standards as well. The study's apparent recommendation came in October 2008, NCDOT and the Greensboro MPO agreed on a plan which takes I-73 off the Loop at Bryan Blvd then takes Bryan Blvd west about 1.8 miles beyond the airport interchange. Following this interchange, I-73 will continue west but be routed on a new freeway 1.2 miles long to an upgraded NC 68 where it will turn north where after less than a mile it will leave on the NC 68-US 220 connector (See I-73 Segment 3). The cost of upgrading all 3 miles between NC 68 and the Loop was estimated to be $144.3 million according to the 2014-2023 STIP released in September 2012.10

Construction Plans Provided First Clues as to Future I-73 Signage between Loop and NC 68 North

In July 2013, NCDOT released plans for constructing the next segment of the Greensboro Loop from Bryan Blvd to US 220/Battleground Ave to start in the fall of 2013. As part of the project, the exits on the I-73 portion of the Loop north of I-40 will be changed to reflect I-73 mileage. The exit number for W. Friendly Road will changed from 2 to 104 and I-73 and Bryan Blvd will become 107 northbound, remaining Exit 3 the other direction. The exit signs will also be updated along the current Bryan Blvd section between the Loop and the PTI Airport exit. The exit sign will read Old Oak Ridge Road/ PTI GSO Airport and will be given the exit number 109. I-73 North signage accompanying the exit 109 signage will list Martinsville, VA as a destination, or control, city. It is unknown whether NCDOT plans to change the exit signs and numbers along the existing roadways at the end of the project, or while the next segment of the Loop is being constructed.11 Here's a few images of the signage plans for Bryan Blvd, these signs started going up in April 2016, see the photo section for images of the first two signs shown below:

Section of singage plan for PTI Airport Exit off I-73, from NCDOT
Image of plans for future I-73 exit signs on Bryan Blvd.
Image of plans for I-73 signage on Bryan Blvd, from NCDOT

Construction Photos from Segment 4 (Hover over to Get Larger Image):

Latest Photos from June 29, 2017 from Strider

Image of nearly complete I-73 Connector roadway taken from Old Oak Ridge Rd bridge over Bryan Blvd, by StriderView from Old Oak Ridge Rd bridge over Bryan Blvd. showing I-73 near completion and the addition of exit signage on the future southbound roadway.


Image taken of new exit signage at PTI Airport exit off of Future I-73 South in Greensboro, by StriderZoomed view of new overhead exit signage on Future I-73 South at the PTI Airport exit (109). Some of the shields for Exit 107 may be covered up prior to the road opening.


Earlier Photos from June 4 and 8, 2017, courtesy of Strider:

Image taken of construction along closed section of Bryan Blvd in Greensboro showing progress in constructing Future I-73 Connector to NC 68, from StriderView from Old Oak Ridge bridge over Bryan Blvd. showing progress in paving Future I-73 lanes back toward Flyover Bridge that will connect I-73 to Bryan Blvd.


Image taken of closed section of Bryan Blvd as tie-in is being constructed to Future I-73 near PTI Airport in Greensboro, from StriderSimilar view to above, traffic can be seen on the left heading east toward PTI Airport on part of Bryan Blvd. that will be permanently closed after the I-73 Connector is complete.


Image taken of I-73 Connector construction seen from NC 68 North in Greensboro, by StriderNow the view from NC 68 North approaching the I-73 South interchange, the future NC 68 South ramp, now paved, can be seen on the left.


Image taken of overhead signs for I-73 interchanges with NC 68 near PTI Airport in Greensboro, from StriderOverhead sign assembly at Future NC 68 North ramp, also paved, to I-73 South with I-73 North Exit sign and awaiting I-73 South sign when work completed.


Image taken of ramp construction ant Future I-73 South and NC 68 North interchange in Greensboro, from StriderA closer look at the nearly completed NC 68 North ramp to I-73 South.


Image of construction at future NC 68 North exit ramp to I-73 South in Greensboro, from StriderAnother look at the Future I-73 South ramp area showing more landscaping work needs to be completed approaching the NC 68 South ramp bridge.


Image of new bridge being constructed for NC 68 South Ramp from I-73 North in Greensboro, by StriderCloser look at landscaping underway at Future I-73 North ramp to NC 68 South, with ramp bridge still being constructed over NC 68. Future I-73 bridges over NC 68 do not appear complete in the distance.


Image taken of future I-73 North and South bridges over NC 68 in Greensboro, from StriderCloser look at I-73 bridges shows work still needed on the bridge structure along with work in the median approaching the bridge. The new Pleasant Ridge Road intersection can be seen under the bridge.


Image taken of view looking across NC 68 and Future I-73 roadway in Greensboro, by StriderLooking across NC 68 South toward Future I-73 roadway showing guardrail installation has begun.


Image taken of view of Opened I-73 North ramp from NC 68 North in Greensboro, by StriderApproaching opened I-73 North Ramp from NC 68 showing work proceeding on unopened I-73 bridges over NC 68.


Previous Photo from May 20, 2017, courtesy of Strider:

Image taken from Old Oak Ridge Rd bridge over Bryan Blvd showing progress in connecting I-73 to existing roadway, from StriderLatest image of progress in creating link between existing Bryan Blvd. and remaining segment of I-73 continuing to NC 68. Appears to be some pavement put down by Taxiway Bridge.


Previous photos from May 8, 2017, courtesy of Strider

Image taken of construction along Bryan Blvd near PTI Airport to connect with future I-73 roadway, from StriderView from Ramp to PTI Airport of progress connecting section of Bryan Blvd closed to traffic on April 29 to the I-73 Connector roadway to NC 68.


Image taken of construction on Bryan Blvd near PTI Airport to connect to future I-73 roadway to NC 68, from StriderAnother view showing progress straightening the curve of Bryan Blvd to connect with the Future I-73 lanes going under the taxiway bridge. Project is scheduled to be complete by the end of June.


Earlier Photos from April 29, 2017, courtesy of Strider

Image taken of view from north NC 68 of nearly completed Future I-73 interchange, by StriderLooking north along NC 68 North showing overhead signage (covered) and lane striping and for Future I-73 interchange largely completed.


Image of View along NC 68 North in Greensboro of nearly completed interchange with I-73 North, by StriderA closer look at the future interchange, the only apparently item still to install prior to opening are signage for the ramps and exit signage for the I-73 lanes.


Previous Photos from March 30, 2017

Image showing construction of I-73 bridges at intersection of Pleasant Ridge Rd and NC 68 in GreensboroLooking west toward the intersection of Pleasant Ridge Road and NC 68 showing bridges being constructed for future I-73 lanes.


Image showing construction of I-73 bridges at intersection of Pleasant Ridge Rd and NC 68 in GreensboroView of the intersection of Pleasant Ridge Road and NC 68 showing bridges being constructed behind for future I-73 lanes and further behind for NC 68 South exit.


Image showing view along NC 68 North past intersection of Pleasant Ridge Rd, showing widening of NC 68 in GreensboroNow traveling north on NC 68 showing progress widening the roadway between the two I-73 exits.


Image showing widening of NC 68 betweent intersection of Pleasant Ridge Rd and I-73 Exit in GreensboroLooking further north on NC 68 showing widening continuing up to future I-73 North bridges.


Image showing construction of northern set of I-73 bridges from NC 68 North in GreensboroCloser view of almost completed bridges at future interchange between I-73 and NC 68 North.


Image showing construction of I-73 bridges at intersection of Pleasant Ridge Rd and NC 68 in GreensboroTraveling under Future I-73 North bridge over NC 68 with southbound bridge just beyond showing structure is mostly complete.


Image showing construction of Future I-73 South interchange with NC 68 North in GreensboroBeyond the bridges, now looking further north at future off-ramp from I-73 South to NC 68 North with traffic signals having been installed and widening nearly complete.


Image showing construction of I-73 bridges at future interchange with NC 68 South in GreensboroNow turning around and heading south on NC 68 showing the overhead sign for the Future I-73 North exit being installed, though covered over. The pull-through sign for NC 68 not yet installed.


Image showing construction progress on future I-73 North exit from NC 68 South in GreensboroFurther on NC 68 South approaching the future interchange with I-73 South.


Image showing signage for Future I-73 North interchange with NC 68 South in GreensboroBefore traveling under the I-73 bridges a second set of overhead signs has been installed, this including a pull-through for NC 68. It appears there will be two left lanes available for traffic accessing I-73 North.


Image showing construction along NC 68 South for I-73 Borth interchange in GreensboroBeyond the bridges are the installed traffic lights for the NC 68 South on-ramp to I-73 North.


Image showing widening of NC 68 South between I-73 interchanges in GreensboroAlong NC 68 South now between the two I-73 interchanges showing progress widening the roadway.


Image showing support posts for future signage along NC 68 in I-73 construction zone in GreensboroAlong the side of NC 68 South sat several support posts for future I-73 signage.


Image showing construction of future I-73 lane bridges south of intersection of Pleasant Ridge Rd and NC 68 in GreensboroLooking south at the intersection of NC 68 South and Pleasant Ridge Road at the bridges being built for Future I-73 lanes.


Image showing I-73 bridges being built over NC 68 south of Pleasant Ridge Rd in GreensboroNow traveling under the Future I-73 North lanes bridge with the southbound bridge after. The ramp bridge for NC 68 South traffic from I-73 North in the distance.


Image showing construction of I-73 NC 68 South Exit bridge from NC 68 South in GreensboroLooking closer at progress building the bridge to carry NC 68 South traffic from I-73 North.


Image showing exit signage along NC 68 South in Greensboro that will be used by I-73 traffic temporarily in 2017Beyond the construction zone on NC 68 South, showing the current overhead exit sign for Bryan Blvd. This exit will be changed to reflect PTI traffic to use I-73 South once completed between NC 68 and Bryan Blvd. by the Airport.


Image showing Bryan Blvd exit signage on NC 68 South, interchange to be used by I-73 traffic in GreensboroNow on Bryan Blvd. heading east, PTI traffic still used this route to access the airport until this part of Bryan Blvd. was closed when the I-73 portion was complete in July 2017.


Image showing signage for Future I-73 at PTI Airport off-ramp to Bryan Blvd. in GreensboroNow on the other side of the airport looking at the future ramp split for I-73 North access to PTI Airport and Oak Ridge Road traffic to Future I-73 North (current Bryan Blvd. West), sorry for the rain drops.


Image showing construction of I-73 PTI Airport Taxiway bridge from Ramp to Bryan Blvd. West in GreensboroView from the top of the Bryan Blvd. (Future I-73 North) on-ramp showing constuction ahead for the I-73 Connector to NC 68 and the PTI Taxiway Bridge.


Image showing construction of I-73 Connector and PTI Taxiway bridge from ramp to Bryan Blvd in GreensboroA closer look at the progress in completing the I-73 Connector to NC 68 and Taxiway Bridge from the PTI Airport on-ramp onto west Bryan Blvd.


Image showing construction of I-73 Connector and PTI Taxiway bridge from Bryan Blvd in GreensboroLooking closely at the PTI Taxiway bridge from Bryan Blvd. as the roadway turns south toward NC 68. Notice that paving has not begun on the I-73 lanes putting some doubt on May's proposed opening date.


Image showing I-73 trailblazers on Bryan Blvd East of the PTI Airport in GreensboroNow on to the completed section of Bryan Blvd. upgraded to interstate standards between PTI Airport/Old Oak Ridge Road and the Greensboro Urban Loop. Here are a pair of To I-73 South trailblazers heading east prior to the 1/2 mile advance sign for the Loop.


Image showing an I-73 trailblazer at interchange with the Greensboro Urban Loop on Bryan Blvd East in GreensboroJust prior to the Loop exit is another To I-73 South trailblazer. This will presumably be taken down when the I-73 Connector is completed and the signs are upgraded reflecting the official I-73 designation.


Image showing I-73 trailblazer at interchange ramp to Greensboro Urban Loop from Bryan Blvd East in GreensboroThe last To I-73 trailblazer is before the future split between traffic heading for I-840 East and I-73 South toward I-40.


Image showing overhead signage at future split of I-840 East and I-73 South on ramp from Bryan Blvd East in GreensboroA closer look of what will be the split for I-840 East and I-73 South traffic at the interchange with Bryan Blvd.


Previous Photos by Site contributor Strider from February 2017:

Image of view from NC 68 North near Pleasant Ridge Rd, showing grading of future I-73 ramp, from StriderNew photo taken on February 19 from NC 68 North showing progress grading future ramps for I-73 from the direction of Bryan Blvd.


Image of view along NC 68 South at northern I-73 bridges showing progress in constructing spans, from Strider From earlier in February, taken from NC 68 South, showing progress in building ramp bridges to and from I-73 North (NC 68-US 220 Connector) over the roadway.


Image of view looking south at Pleasant Ridge Rd showing progress in constructing I-73 main bridge, from Strideron NC 68 of progress building bridges for I-73 North over roadway, from StriderFurther south in NC 68 prior to Pleasant Ridge Road showing one bridge built over the roadway for the I-73 connector to Bryan Blvd., while others remain to be completed.


Image of view of PTI Airport Taxiway bridge being built over future I-73 lanes as seen from Bryan Blvd, from StriderOn the other side of the construction project, a closeup view of the PTI Taxiway bridge over the future I-73 lanes, as seen from Bryan Blvd.


Earlier Photos from Site contributor Strider from December 2016:

Image of I-73 construction seen from NC 68 North in Greensboro, by StriderLooking north on NC 68 entering I-73 construction zone showing progress in building ramps that will take I-73 across the highway.


Image of bridges being built to carry I-73 traffic over NC 68 in Greensboro, from StriderClose up view of bridge supporting structures being built near Pleasant Ridge Road for future I-73 bridges.


Image of new bridges being built for I-73 along NC 68 near Pleasant Ridge Road in Greensboro, from StriderLooking at bridges being built on opposite side of NC 68 near Pleasant Ridge Road with crane for placing supports above the roadway.


On the other side by Bryan Blvd:

Image of I-73 construction seen from Bryan Blvd near PTI Airport, by StriderView looking west on Bryan Blvd to start of Future I-73 Connector showing a clearer view of the Taxiway under construction now that a hill in front along the path of I-73 has been removed.


Image of construction of new I-73 roadway and PTI Airport Taxiway as seen from Bryan Blvd, by StriderCloser look from Bryan Blvd. at I-73 roadway and PTI Airport Taxiway bridge construction, photo taken by Strider on 12/28/16.


Previous Photos by Strider, date on lower right corner, starting in November 2016:

Image of future I-73 interchange under construction as seen from NC 68 North, by StriderView from NC 68 North approaching I-73 interchange area, work has recently been restarted in this area.


Image taken from NC 68 North showing progress in building I-73 South onramp to NC 68 South, by StriderFurther north on NC 68 looking across the highway at progress in building the future on-ramp from I-73 South to NC 68 South.


Image showing progress of building new I-73 interchange with NC 68 in Greensboro, from StriderAnother photo taken from NC 68 north showing the future widened roadway in vicinity of the Future I-73 interchange.


Image of nearly completed I-73 bridges over NC 68 in Greensboro, by StriderFurther north on NC 68 approaching nearly completed future I-73 bridges.


PREVIOUS PHOTOS

Bryan Blvd Area (Photos by Strider from October 2016):

Image of future I-73 roadway under construction as seen from on-ramp from PTI Airport exit on Bryan Blvd., by StriderView from the top of the ramp from Old Oak Ridge Rd to Bryan West (I-73 North) showing that the PTI Taxiway is about to be completed.


Image taken at end of Regional Road showing progress in building the NC 68 flyover bridge, by StriderNC 68 AREA-View at the north end of Regional Road where you can see the NC 68 South flyover taking shape that will take traffic to NC 68 south from I-73 North.


Image showing progress of building new I-73 bridge over Pleasant Ridge Road in Greensboro, from StriderTaken from NC 68 north facing the relocated Pleasant Ridge Rd intersection. Traffic has been taken off the old road so they can start working on the completing the main I-73 bridges that currently ends abruptly on the left side of the photo.


Image of new I-73 bridges being constructed over NC 68 north of Pleasant Ridge Road in Greensboro, by StriderTaken further north on NC 68 approaching the next set of I-73 bridges. The crews are working on placing the road decks on the bridges. To the right is the ramp to the US 220/NC 68 connector that should be open by the end of the year.


Image looking south on NC 68 at Pleasant Ridge Road showing future I-73 flyover bridge under construction, from StriderView from NC 68 South at the relocated Pleasant Ridge Road intersection showing the I-73 flyover bridges under construction that will carry I-73 over NC 68 to the I-73 connector to Bryan Blvd.


Image of ramp to Bryan Blvd from I-804, Future I-73 North showing paving project completed, from NCDOT Traffic cameraView from NCDOT Traffic Camera showing completion of paving project along Future I-73 North ramp from the I-840 Greensboro Loop to Bryan Blvd. Photo taken 8/18/16.


Image of partially completed paving upgrade of Bryan Blvd to become I-73 as seen from Inman Rd bridge. Photo by StriderView from Inman Road on August 20, 2016 showing recent paving on future I-73 Northbound lanes continuing from ramp from I-840 East onto Bryan Blvd. Work is to start on revising ramp from Bryan Blvd to I-840 Greensboro Loop West to contain two lanes later this month, photo by Strider.


Image of future I-73 roadway along Bryan Blvd. from Inman Rd Bridge, photo by StriderView from New Inman Road Bridge shows Bryan Blvd (Future I-73) northbound lanes being widening and paved for the ramp merge onto I-73 from I-840 East. Facing west toward Exit 109, the PTI-GSO Airport and Old Oak Ridge Rd interchange.


Image of Bryan Blvd (Future I-73) from Inman Road Bridge looking toward interchange with Greensboro Loop, Photo by StriderAnother view from new Inman Road Bridge, but facing East toward the future I-840 interchange (Exit 107) showing widening being done to future I-73 on-ramp.


View of construction progress for new PTI taxiway over I-73 Connector Roadway in Greensboro, photo by StriderView of Future I-73 North from PTI Airport exit on-ramp showing the PTI Taxiway over Future I-73 lanes in the distance nearly completed.


Image of new overhead signage showing I-73/I-840 Loop exit in Bryan Blvd. West, from MazdaStriderImage of new overhead signage put up in April 2016 that has first use of I-73 South and I-840 West for the South Loop exit. The blank space on left sign is for I-73 North. According to the sign plans above, Raleigh was to be covered over until I-840 was completed. Photo courtesy of MazdaStrider.


Image of new exit sign with I-73 Milepost Number for PTI Airport on Bryan Blvd West (Future I-73 North), from MazdaStriderAnother new overhead exit set after the Loop exit features the Future I-73 exit number for the PTI/Old Oak Ridge Rd Exit, Photo courtesy of MazdaStrider.




Image from Oak Ridge Rd showing nearly complete left bore of PTI Airport Taxiway over future I-73, from StiderView from Oak Ridge Rd/Airport exit by Strider on June 13, 2016 showing nearly complete left bore for future Airport Taxiway over I-73 with work on the right bore continuing.


Image of future pathway of I-73 being cleared where it will connect with Bryan Blvd. Photo by StriderView from on-ramp from PTI Airport Exit looking at cleared area for I-73 North and construction of new taxiway for PTI Airport, from Strider, May 2016.


Closer view of new I-73 alignment west of Bryan Blvd and construction activity related to PTI Airport Taxiway, from Strider May 
        2016Closer look at future I-73 alignment leaving Bryan Blvd with construction of PTI Airport taxiway in distance. Photo courtesy of Strider, May 2016.


Image of Future Pathway of I-73 being cleared where it will connect with Bryan Blvd., Photo by Strider.Looking west at clearing at eastern end of project area, I-73 will go straight onto the Connector as Bryan Blvd. curves to the left. (Photo courtesy of Strider, August 2015).


View from dead end of Regional Rd, showing equipment used for taxiway construction over Future I-73 lanes, from StriderLooking from now dead end of Regional Rd looking at construction equipment building the taxiway over the future I-73 highway lanes. Photo courtesy of Strider, May 2016.


Image of new bridge under construction as seen from Future I-73 North lanes, from StriderView from the future I-73 Northbound lanes looking at bridge being constructed over highway. Photo courtesy of Strider, May 2016.


Image looking east from I-73 Northbound lanes back towards PTI Airport showing clearing for future I-73 RoadwayView from future I-73 North Lanes looking east toward PTI Airport showing progress in grading roadbed.





Image from NC 68 North near Pleasant Ridge Rd. of the massive clearings for the 
interchange (and the reroute of Pleasant Ridge Rd), by Strider Traveling along NC 68 North, near Pleasant Ridge Rd. viewing the clearing for the future interchange with I-73 (and a rerouted Pleasant Ridge Rd).


Image showing the intersection of Pleasant Ridge and NC 68 and construction of bridge 
piers for I-73, photo by StriderLooking at the intersection of Pleasant Ridge and NC 68 and the start of construction of bridge piers for I-73 to go over NC 68 and Pleasant Ridge Rd.


Image of future Pleasant Ridge Rd where the reroute of will go under I-73, by StriderFrom the route of Future Pleasant Ridge Rd, the road will go under I-73. These three piers under construction will carry the NC 68 south ramp, I-73 Southbound lanes, and I-73 Northbound lanes.


View of Pleasant Ridge Road at the NC 68 intersection, showing the massive clearing 
underway where I-73 will turn east to connect with Bryan Blvd., photo by StriderLooking at Pleasant Ridge Road at the NC 68 intersection where you can see the massive clearing taken place where I-73 will turn to the east to connect with Bryan Blvd (avoiding the water tower?)


Image from North NC 68, view of construction of hill in preparation of Future I-73 
bridges over NC 68 and NC 68 interchange.Traveling farther north on NC 68, you can see the hill being made in order to build future I-73 bridges over NC 68 and for the future NC 68 North interchange.


Comment: If the freeways proposed by the Greensboro Urban Area Metropolitan Planning Organization between Bryan Blvd and I-40 and/or Bryan Blvd. to I-74 along the Winston-Salem Northern Beltway are constructed, why not give one an interstate designation such as I-273?

Image of I-73 NC shield from Shields Up!