Image of NC Interstate 73 shield, courtesy of Shield's Up! Segment 2

Portion of NCDOT 2021-2022 State Transportation Map showing I-73 Segment 2 in Guilford County

Where: US 220, From NC 68 to US 220-NC 68 Connector

Length: 4 Miles

Status: COMPLETE

Completion Date: Roadway-Dec. 2017, I-73 Signs-March 2018

Road Signed as: I-73 NC shield image from Shield's Up!   

Jump to Photos (NEW 11/1/22)

Segment Info

South of NC 68, US 220 was mostly a two-lane roadway. As part of a project that built the 'NC 68-US 220 Connector' north of Greensboro (Project No. R-2413, see Segment 3 below), NCDOT upgraded the highway to a four-lane freeway for about 4 miles between the NC 68 intersection and the Connector completed earlier in 2017 just south of the Haw River. Work on this segment, Contract R-2413C, started in May 20121 (delayed from 2010) and has fell significantly behind the project completion schedule which  was listed as January 25, 2018. As of March 15, 2018 the project was listed as 83.3% complete, only .3% more than in January.2 To illustrate the slow progress rate, in July 2013, more than 4 1/2 years ago, the project was 21.5% complete.3 In August 2015, NCDOT finally admitted the project would not be completed on time and pushed completion back to June 19, 2017.2 In June 2016, the completion date was pushed back again to January 25, 2018.2 However, a news report in early April 2017 indicated that NCDOT hoped to open the route by October 20174, an NCDOT official indicated in August 2017 that the hopeful date was October 18, but that was then delayed into late December.5 The two southbound lanes were opened as of December 21 from NC 68 to the US 220 exit, the two northbound lanes were opened on December 22. Though now open to traffic there still were no I-73 signs along the roadway at the beginning of February 2018.6 This was remedied by the installation of ground-mounted signs in late March 2018, the road was finished, but technically not complete. Adding I-73 exit tabs to the existing exit signs did not take place until April. Complicating completion on the route was a decision by NCDOT to change the plans at the northern end of the project from a re-worked intersection with NC 68 that included a traffic signal to a more complicated flyover ramp for US 220 South to cross over NC 68. NCDOT held a public meeting to inform the public in January 2014 from which planners were to resubmit the design for the interchange.7 NCDOT then decided to let this as a separate project, Contract C203645 awarded on June 16, 2015. Construction started on Sept. 16, 2015 and, as of March 7, 2018 was still was listed as 90.4% complete (a .1% increase since January, this project is also going slow, it was supposed to be 99.9% complete by that time though).8 Despite the project's slow pace, the future I-73 South roadway that it, along with the new off-ramp to NC 68, was opened in May 2017 (see photos below). The project plans, released on May 19, 2015, revealed the following design for the new interchange (based on other contract documents, the number for the NC 68 exit will be 123, while the NC 65 exit will be 122):

Image of signage plan for to be constructed US 220 NC 68 interchange in Rockingham 
County, courtesy of NCDOT







The NC 68 project was awarded on July 7, 2015 to Branch Highways Inc. out of Roanoke, VA for $14 million.10 The total cost for the entire project (right-of-way and construction) is now budgeted at around $223 million.11 Initially, the roadway was not to be built to Interstate standards, but only at a 60 MPH limited access highway. However, this changed when the Connector project to the south was advanced to be completed around the same time both segment are now to be signed as I-73, with a 65 MPH speed limit, when completed.12,13

The US 220 South ramp from I-73 South is a flyover bridge that goes over both the Haw River and then I-73 to its current alignment (for a link to the plans see I-73 Segment 3). Work to complete this flyover was completed during the fall of 2014 and US 220 traffic was rerouted onto it soon after (see photos below). The US 220 project was to be mostly completed before work on the Connector to NC 68 was finished, however this did not happen with the many project delays. (For an NCDOT diagram of the entire project go to the Project page.)

"Drive" This Segment with these Videos from RoadwayWiz made in the Summer of 2021

I-73 North from Exits 117 to 123 (Includes part of Segment 3)

I-73 South from Exits 123 to 117

"Drive" This Segment Using Google Maps Street View from October 2018

Beginning of I-73 South: Just North of NC 68 Exit

I-73/US 220 South: At NC 65 Exit Off-Ramp

I-73/US 220 North at US 158: At US 158 East On-Ramp

US 220 North at I-73 North: On US 220 North On-Ramp

Segment 2 Photos, Hover Over to get Larger Image.

Most Recent - Taken during road trip between Roanoke and Greensboro, October 14, 2022:

Image of auxiliary sign for PTI Airport at start of I-73 South in Rockingham County, October 2022An auxiliary sign for PTI Airport to use I-73 is placed before I-73 South starts at the NC 68 exit.


Image of first I-73 South mile marker prior to NC 68 exut in Rockingham County, October 2022The first South I-73 mile marker is in place before the NC 68 exit.


Image of overhead sign at NC 68 exit at start of I-73 South in Rockingham County, October 2022The overhead signs at the start of I-73 South at the NC 68 exit.


Image of 3/4 Mile advance sign for NC 65 exit on I-73 South in Rockingham County, October 2022The rather plain 3/4 mile advance sign for the NC 65 exit.


Image of overhead signage at NC 65 exit on I-73 South in Stokesdale, Rockingham County, October 2022It's a rather small overhead sign for the NC 68 exit.


Image of gore sign at NC 65 exit on I-73 South in Stokesdale, Rockingham County, October 2022The seemingly much larger gore sign at the NC 65 exit.


Image of 1 mile advance sign for the US 158 exit on I-73 South in Stokesdale, Rockingham County, October 2022The 1 Mile advance sign for the US 158 exit on I-73 and US 220 South.


Image of auxiliary sign for the US 158 exit on I-73 South in Stokesdale, Rockingham County, October 2022An auxiliary sign for Winston-Salem approaching the US 158 exit.


Image of overhead sign at US 158 exit on I-73 South in Stokesdale, Rockingham County, October 2022The overhead signs at the US 158 exit on I-73 and US 220 South, sorry for the truck.


Image of 1/2 mile advance overhead sign for US 220 exit on I-73 South in Rockingham County, October 2022The overhead signs prior to the split of I-73 South with US 220 South.


Image of overhead sign at NC 68 exit at start of I-73 South in Rockingham County, October 2022The overhead signage at the I-73 South/US 220 South split.


Earlier Photos

By Strider in December 2020:

Image of new blue services sign for US 158 exit on I-73/US 220 North in Summerfield, by Strider, December 2020Recently placed blue services sign for the US 158 exit on I-73 North.


Image of new ground mounted exit sign for NC 65 on I-73/US 220 North in Stokesdale, by Strider, December 2020Along with a new exit sign, though NC 65 is not worthy enough of a destination (the exit is in Stokesdale).


Image of median sign informing drivers of Entering the Roanoke River basin on I-73/US 220 North in Stokesdale, by Strider, December 2020This median sign announcing entry into the Roanoke River basin has replaced a similar one that was by the right shoulder, see photos below.


Previous Photos

By David Johnson in May 2019:

Image of first North I-73/US 220 reassurance markers just across the Rockingham County border, by David JohnsonNorth I-73/US 220 North just after the US 158 exit, the last exit in Guilford County.


Image of view on I-73/US 220 North just after US 158 exit, by David JohnsonThe first North I-73/US 220 reassurance markers in Rockingham County.


Image of temporary NC 65 trailblazer still in place instead of guide sign for NC 65 exit on I-73/US 220 North near Stokesdale, by David JohnsonThe temporary NC 65 trailblazer put up prior to the route opening (see photos below) has still not been replaced by a guide sign on I-73 North.


Image of gore sign at ramp to NC 65 on I-73/US 220 North near Stokesdale, by David JohnsonThe gore sign was placed in time for the road opening, and is still there.


Image of small guide sign for Roanoke River Basin on I-73/US 220 North near Stokesdale, by David JohnsonThere is also a small sign announcing that I-73/US 220 North (with post-NC 65 exit reassurance markers in distance) is entering the Roanoke River Basin.


Image of I-73 North traffic meeting on-ramp at end of NC 68 North in Rockingham County, by David JohnsonLooking toward current end of I-73 at the on-ramp from NC 68 in Rockingham County, and the reduction of the speed limit to 55 mph.


Earlier Photos by Site Contributor Strider taken on April 13, 2018:

Image of 1-mile advance sign for US 158 exit on I-73/US 220 North in Summerfield now with exit number tab, from StriderThe previously placed 1-Mile Advance sign for US 158 after the merge with US 220 North now has an exit tab.


Image of overhead signs at US 158 exit on I-73/US 220 North near Stokesdale now with exit number tabs, by StriderOverhead advance and exit signs at the US 158 exit on I-73/US 220 North also now have exit tabs. Meanwhile, for some reason the existing NC 65 sign's references to NC 68 South have been removed, possible to duplicate the information on the southbound signs.


Image of existing exit signs at off-ramp to NC 68 on I-73/US 220 South in Rockingham County, now with exit number tabs, by StriderNow headed southbound in Rockingham County, the overhead signs at the NC 68 South off-ramp also have new exit number tabs.


Image of I-73 and US 220 south reassurance markers beyond NC 68 South exit in Rockingham County, by StriderNewly placed I-73 South reassurance marker has been joined by a fairly large US 220 South marker on 2 posts beyond the NC 68 exit on-ramp.


Image of previously placed overhead signage at NC 65 exit on I-73/US 220 South near Stokesdale now with exit number tabs, by StriderOverhead signage at the NC 65 exit also with new exit number tabs. The NC 65 tab being wider than the sign below.


Image of previously placed overhead signage at US 158 exit on I-73/US 220 South near Stokesdale now with exit number tabs, by StriderOverhead signage for the US 158 exit with the new exit number tab, previously placed for the US 220 South exit.


Image of overhead signage at ramp to US 220 South on I-73 South in Summerfield, now with new exit number tabs, by StriderNew exit tabs also on sign for US 220 South exit ramp in Summerfield. Unclear as to what the extra supports over the I-73 pull-through sign are for.


Previous Photos taken on April 7, 2018:

Image of new exit 120 gore sign installed for US 158 exit on I-73/US 220 North in Summerfield, by StriderRecently installed Exit 120 gore sign for US 158 exit on I-73/US 220 North in Summerfield.


Image of newly installed Exit 122 gore sign for NC 65 to NC 68 exit on I-73/US 220 North near Stokesdale, by StriderAlso newly installed a Exit 122 gore sign northbound on I-73/US 220 for the NC 65 to NC 68 exit.


Image of 1/2 mile advance sign for NC 68 South exit on US 220 South in Rockingham County now with Exit 123 tab, by StriderClearer view of 1/2 mile advance sign for NC 68 South also with new Exit 123 tab. The overhead signs have not received exit tabs as of this time.


Image of new Exit 123 gore sign at ramp to NC 68 South on I-73/US 220 South in Rockingham County, by StriderNewly placed Exit 123 gore sign for NC 68 South exit at beginning of I-73 South.


Image of new destination mileage sign placed on I-73/US 220 South after NC 65 exit, by StriderAlso newly placed, this distance sign after the NC 65 exit on I-73/US 220 South.


Image of 1-mile advance sign for US 158 exit with new Exit 120 tab on I-73/US 220 North in Summerfield, by StriderFurther south, this 1-mile advance sign for the US 158 exit also has a new Exit 120 tab. (The overhead signs at the exit still need to have tabs installed).


Image of newly installed auxiliary sign with destination of Winston-Salem for US 158 exit on I-73/US 220 South in Summerfield, by StriderNewly installed auxiliary sign for Winston-Salem approaching the US 158 exit ramp.


Image of newly installed Exit 119 gore sign for US 220 South exit on I-73 South in Summerfield, by StriderLast new gore sign installed for Exit 119, US 220 South on I-73 South in Summerfield.


Earlier Photos by Site Contributor Strider taken on March 31, 2018:

Image of newly placed I-73 North reassurance marker following US 158 exit near Stokesdale, by StriderNewly placed North I-73 reassurance marker (no US 220 sign present, at least for now) after US 158 exit near Stokesdale.


Image of newly placed I-73 North reassurance marker following NC 65 exit near Stokesdale, by StriderAnother new reassurance marker follows the NC 65 exit. Some signage, including tabs for the exit signs still need to be placed.


Image of newly placed End (North) I-73 beyond merge with NC 68 north on US 220 North in Rockingham County, by StriderNewly placed End (North) I-73 sign after merge with NC 68 North on US 220 North, may be the most northern I-73 sign standing for a long time depending on whether VA commits to construct its section of the interstate.


Image of newly placed I-73 milemarker approaching NC 65 exit near Stokesdale, by StriderAlso in place are new I-73 mile markers, here southbound for Mile 122.5 approaching the NC 65 exit.


Image of I-73 and US 220 junction signs on NC 65 East approaching interchange near Stokesdale, by StriderI-73 signs have also been put up on approaching roadways, here on NC 65 East approaching the new exit ramps.


Image of I-73 trailblazers on NC 65 east approaching exit ramps to newly signed interstate, by StriderNew I-73 trailblazers along with pre-existing US 220 signs at interchange with NC 65 East.


Previous photos taken on December 11 and 21 and 29, 2017:

Driving northbound:

Image of completed US 220 (Future I-73) North lanes about to cross over Haw River bridge into Summerfield, by StriderView just after merge of US 220 North with Future I-73 showing both lanes now open crossing the Haw River bridge.


Image of newly opened left lane on US 220/Future I-73 North beyond US 158 exit in Summerfield, by StriderView of completed lanes further north after US 158 exit, heading toward NC 65.


Image of newly opened US 220/Future I-73 lanes north of NC 65 exit near Stokesdale, by StriderNow approaching the NC 65 exit on-ramp heading toward NC 68, this was the last section that had to be completed before both lanes could be opened.


Image showing completed lanes of US 220/Future I-73 North approaching NC 68 on-ramp in Rockingham County, by StriderFrom the newly opened left-lane of US 220 (Future I-73) North showing rumble strips and guide rails installed along the center median.


Image of approaching merge between US 220/Future I-73 North lanes and ramp at end of NC 68 North in Rockingham County, by StriderApproaching merge between NC 68 and US 220 North at what will be the end of I-73 North in Rockingham County.


Image of sign marking the end of US 220 North freeway beyond NC 68 in Rockingham County, by StriderSign marking the official end of the US 220 freeway about 1/4 mile after the merge of he ramp from NC 68 North.


Turning around and heading back south:

Image of NC 68 north interchange with US 220 (Future I-73) North from US 220 South lanes, by StriderOverview of the merge between US 220 (End of Future I-73 North) and ramp from NC 68 North as seen from US 220 South approaching NC 68 South exit.


Image of new overhead signs for NC 65 and US 158 exits on US 220/Future I-73 South near Stokesdale, by StriderOverhead signs at NC 65 exit on US 220/Future I-73 South placed in January 2018, awaiting I-73 exit tabs.


Image of overhead sign gantry awaiting NC 65 and US 158 exit signs on US 220/Future I-73 South near Stokesdale, by StriderPrevious photo from December of newly placed overhead sign gantry awaiting signs at NC 65 exit ramp on US 220 (Future I-73) South in Stokesdale.


Image of opened lanes heading south toward Haw River bridge on US 220/Future I-73 South in Summerfield, by StriderView looking south over completed lanes heading toward Haw River bridge and current start of I-73 South.


Image of exit signs and numbered exit tabs awaiting installation along Future I-73 in Guilford County, by StriderStorage area further south along US 220 holds yet to be installed exit signs and I-73 mileage exit tabs.


New signage installed between US 220 and US 158:

Image of newly placed overhead 1-Mile advance sign for US 158 exit on US 220/Future I-73 North in Summerfield, by StriderNew 1-Mile advance sign for the US 158 exit on US 220 North just after merge of I-73 in Summerfield, the sign has an Exit Only Tab for the additional 3rd lane from the US 220 North on-ramp.


Image of new overhead 1/2 mile advance sign for US 158 on US 220/Future I-73 North in Summerfield, by StriderFurther north a nearly identical 1/2 Mile advance sign for US 158.


Image of new overhead signs prior to I-73/US 220 South split in Summerfield, by StriderNo heading south, the new overhead signs southbound for US 220 South exit. This US 220 1/2 mile advance sign has the I-73 Exit number tab, not present on the other overhead signs.


Image of overhead signage at exit ramp for US 220 South on I-73 South in Summerfield, by StriderOverhead signage at the US 220 South exit off-ramp, this sign does not yet have an exit tab.


Image of newly placed overhead signs for US 158 and NC 65 exits on US 220/Future I-73 North in Stokesdale, by StriderOverhead signage placed on US 220 (Future I-73) North in mid-December for the US 158 and NC 65 exits.


Image of newly place overhead signs for US 158 and US 220 exits on US 220/Future I-73 North in Stokesdale, by StriderHeading back south at US 158 these overhead signs were also placed in mid-December. They do not have I-73 exit tabs. Note both southbound lanes are open.


Construction Photos for this Segment

Taken on October 22, 2017:

Image of US 220 highway north of merge with I-73 and completed bridge over the Haw River, by StriderView of completed I-73 North roadway approaching bridge over Haw River beyond merge with US 220 North.


Image of US 220 highway north with completed I-73 lanes after completed bridge over the Haw River, by StriderClimbing the hill after the Haw River on completed I-73 North roadway approaching US 158 exit.


Image of US 220 highway north with completed I-73 roadway approaching US 158 exit ramp in Summerfield, by StriderNow approaching US 158 where exit signs have still not been put up and area is marked with US 220 and 158 trailblazers.


Image of US 220 highway north and completed I-73 lanes approaching bridge over US 158, by StriderThe completed I-73 North roadway continues beyond US 158 exit at site of former traffic crossover from North to completed South lanes.


Image of US 220 highway north and completed I-73 lanes approaching NC 65 exit, by StriderHeading further north on US 220 approaching completed NC 65 exit showing median guide rails have been installed.


Image of US 220 highway north and completed I-73 lanes near NC 65 exit in Summerfield, by StriderView on US 220 North at completed NC 65 exit ramp where a temporary gore sign has been placed in the future right-hand lane.


Image of US 220 highway north and completed I-73 lanes just north of NC 65 exit in Summerfield, by StriderContinuing on completed Future I-73 North roadway beyond NC 65 exit at site of completed on-ramp.


Image of US 220 highway north and completed I-73 lanes before the NC 68 exit in Rockingham County, by StriderStill further north on US 220 approaching the NC 68 exit showing construction barrels now on both sides of the highway.


Image of Future end of I-73 North at NC 68 showing continued work needed on highway shoulders before 
          route can be completed, by StriderView at what will be the end of I-73 North at the NC 68 on-ramp. The final pavement is down, work still needs to be completed on shoulder in this area.


Now heading back southbound:

Image of US 220 South roadway prior to NC 68 exit in Rockingham County, by StriderOn US 220 South roadway approaching NC 68 exit. Future I-73 North roadway lanes still not repainted to reflect one-way status.


Image of US 220 South roadway after NC 68 exit in Rockingham County with lines still painted for former 2-lane roadway, by StriderBeyond the NC 68 exit, Future I-73 South lanes still striped for 2-lane travel. VMS is temporary exit sign for NC 65.


Image of US 220 lanes striped for 2-lane travel not as Future I-73 South in Rockingham County, by StriderTraffic on US 220 South prior to the NC 65 exit is shifted to the Future I-73 South left-hand lane.


Image of US 220 South just after NC 65 exit showing construction progress on Future I-73 South lanes in Summerfield, by StriderView just prior to NC 65 on-ramp showing completed Future I-73 South lanes heading toward US 158.


Image of US 220 South in Summerfield showing completion of Future I-73 South lanes in this area, by StriderFurther south after the completed noise wall US 220 South traffic still uses Future I-73 South lanes heading up hill to the US 158 exit.


Image of US 220 South at site of former traffic crossover in I-73 South construction zone in Summerfield, by StriderApproaching US 158 exit, currently only marked by a trailblazer, at site of former cross-over to Future I-73 North lanes for US 220 South traffic.


Image of US 220 South prior to US 158 on-ramp to future I-73 South lanes in Summerfield, by StriderNow beyond the US 158 bridge approaching the interchange on-ramp and heading south toward the Haw River.


Image of US 220 South heading downhill from US 158 exit showing new pavement for I-73 South lanes being placed on roadway, by StriderHeading down hill toward Haw River and US 220 South exit showing new pavement having been placed in Future I-73 South left lane.


Image of US 220 South lanes being paved prior to competion of I-73 South prior to Haw River in Summerfield, by StriderRight lanes await final paving on US 220 to become I-73 South, no exit signage, still only trailblazers, yet for US 220 South as off-ramp approaches.


Previous Photos by Strider taken on September 30, 2017:

Image taken of newly paved future I-73 North lanes approaching NC 68 on US 220 North in Rockingham County, by StriderView taken on US 220 North approaching NC 68. Final pavement for Future I-73 North lanes has been placed with northbound traffic shifted over to the new lanes.


Image of US 220 North approaching NC 68 with widening project almost complete for I-73 North in Rockingham County, by StriderTemporary left lane markings along US 220 North approaching NC 68. Final shoulder work appears to be underway.


Image of Future I-73 North lanes approaching NC 68 on-ramp along US 220 North in Rockingham County, by StriderUS 220 North traffic using Future I-73 North left lane approaching on-ramp from NC 68 North. Shoulder work continues prior to and beyond exit ramp.


Image of US 220 North under construction at end of widening project work zone in Rockingham County, by StriderWidening work continues for about a 1/2 mile beyond NC 68 on-ramp which will be the northern end of I-73 for the foreseeable future.


Image taken of US 220 North from US 220 South (Future I-73 South) lanes prior to NC 68 exit in Rockingham County, by StriderView taken from US 220 South of Future I-73 North NC 68 on-ramp merge. Southbound roadway lane markers still reflect previous two-way traffic.


Image of US 220 South lanes being prepared for I-73 South traffic beyond NC 68 exit in Rockingham County, by StriderHeading south on US 220 beyond NC 68 exit. Future I-73 South lanes look ready except for need to repaint lane markings between right and currently closed left lanes.


Image from US 220 South approaching Future I-73 exit with NC 65 in Guilford County, by StriderFurther south on US 220 approaching NC 65 exit. Exit signs have still not been put up with the ramp entrance marked by just an NC 65 trailblazer. Again, lanes appear ready except for proper lane striping.


Image taken of US 220 South approaching Future I-73 exit with US 158 in Guilford County, by StriderView of US 220 South approaching US 158 interchange and former traffic shift. Median guide rails have been placed in this section.


Previous photos taken on May 20, 2017:

Image taken of newly opened I-73 proceeding south from US 220 South interchange in Summerfield, by StriderLooking south on US 220 just prior to the Haw River showing opening of I-73 connector roadway to NC 68. There currently are no exit signs at the interchange, just trailblazers (on the left behind the 3rd orange barrel) as the case with the NC 65 interchange to the north.


Previous photos taken on April 11, 2017:

Image taken of overhead exit signage above US 220/Future I-73 South at NC 68 exit in Rockingham County, by StriderView from US 220 South now shifted onto Future I-73 South lanes over NC 68 of overhead signage for new exit ramps opened for NC 68 and NC 65, exit tabs will be added later.


Image taken from US 220 South approaching newly opened off-ramp to NC 65 from Future I-73 South, by StriderView on US 220 South now on Future I-73 South lanes between NC 68 and NC 65 showing NC 65 trailblazer temporarily marking the new off-ramp.


Image of US 220 traffic using Future I-73 South lanes from NC 65 bridge, by StriderView from completed NC 65 bridge looking south showing US 220 traffic using Future I-73 Southbound lanes and completed on and off-ramps heading toward US 158.


Image of US 220 South traffic using Future I-73 Southbound lanes between NC 65 and US 158 in Guilford County, by StriderView heading further south on US 220 between NC 65 and US 158 showing traffic using Future I-73 lanes next to completed sound barrier wall.


Image of view along US 220 North just beyond US 158 interchange in Guilford County, by StriderNow heading back northbound, traffic is now using the Future I-73 North bridge over US 158, with the exit ramps open the temporary signals have been removed from the wires ahead.


Image taken on US 220 North prior to former lane shift for traffic on Future I-73 South lanes in Guilford County, by StriderFurther north on US 220 beyond US 158 at what was the shift of traffic to the original US 220 lanes, now shifted to the new Future I-73 South lanes while the old US 220 lanes are reconstructed for northbound traffic.


Image of view of construction of Future I-73 North lanes from US 220 North in Guilford County, by StriderFrom US 220 North showing work starting on removing hill under former US 220 lanes to match the grade of the Future I-73 South lanes.


Image of new NC 65 and NC 68 trailblazer to mark recently opened off-ramp from US 220 North from Future I-73 South lanes, by StriderNew NC 65/NC 68 South trailblazer marks temporary off-ramp from Future I-73 South lanes to newly opened NC 65 off-ramp from northbound lanes. To match the future exit sign, there should be a 'To' between the NC 65 and 68 shields. With the opening of the NC 68 South off-ramp there is no longer direct access to NC 68 from US 220 North.


Image of recently opened off-ramp to NC 65 from US 220 North using Future I-73 South lanes, from StriderCloser look at newly opened ramp to NC 65 from Future I-73 Northbound lanes from US 220 North.


Image of recently completed NC 65 bridge from US 220 North using Future I-73 South lanes, from StriderHeading under the new NC 65 bridge on US 220 North using Future I-73 Southbound lanes.


Image of construction of I-73 North from US 220 North using Future I-73 South lanes beyond NC 65, from StriderFurther north beyond NC 65 on US 220 showing work starting on creating Future I-73 Northbound lanes.


Image from US 220 using recently opened Future I-73 South lanes approaching NC 68 interchange, from StriderView approaching NC 68 from US 220 North now using Future I-73 Southbound lanes.


Image from recently opened bridge over NC 68 from US 220 North using Future I-73 South lanes, from StriderView from heading across new bridge over NC 68 that will carry Future I-73 Southbound lanes. Old US 220 to carry I-73 North traffic below.


Image of recently opened off-ramp to NC 65 from US 220 North using Future I-73 South lanes, from StriderView from end of NC 68 North approaching new bridge for Future I-73/US 220 South traffic with newly opened NC 68 ramp on left. Trailblazer for South US 220 has been removed on the right.


Image of recently paved US 220 North beyond NC 68 on-ramp in Rockingham County, from StriderNow back on US 220 North beyond the NC 68 North on-ramp approaching the end of the construction zone. Perhaps some day I-73 will make it the 30 miles to Martinsville.


Image of recently opened off-ramp to NC 65 from US 220 North using Future I-73 South lanes, from StriderHeading back south, the view of US 220 traffic using the newly opened Future I-73 South lanes prior to the new NC 68 exit.


Photos taken by the Webmaster on March 30, 2017:

Image of I-73 ramp construction at intersection of US 220 and NC 68Looking east at current intersection of NC 68 with US 220 showing completed bridge for Future I-73/US 220 South traffic and ramp to left which will carry traffic to NC 68 South.


Image of new US 220 (Future I-73) roadway south from end of NC 68 NorthLooking south from NC 68 toward future I-73/US 220 roadway which will carry southbound lanes upon completion of new interchange.


Image of travelling under new I-73 South bridge at end of NC 68 North at US 220About to travel under the completed Future I-73/US 220 South bridge prior to NC 68 North meeting US 220.


Image of view looking south along current US 220 roadway which will become northbound lanes after NC 68 interchange project is 
        completedLooking south on current US 220 roadway paralleling new I-73/US 220 South lanes. This will become the northbound lanes merging with NC 68 traffic when interchange project is completed.


Image of view looking south along current US 220 roadway just after NC 68 intersection showing progress building 
        future I-73 South lanesLooking south on current US 220 roadway just after the NC 68 intersection. Work is proceeding on building new southbound lanes on other side of guardrail.


Image of view looking south along current US 220 roadway approaching NC 65 intersection showing progress building new south 
        I-73 lanesFurther south approaching existing distance sign, paving going on to the right of the orange barrels for new southbound lanes. Once these are completed traffic will shift over so hill in the distance can be graded down to match elevation of the new lanes.


Image of view looking south along current US 220 roadway which will become northbound lanes after NC 68 interchange project is 
        completedFurther south on current US 220 approaching NC 65, progress on the new southbound roadway here cannot be seen due to the concrete barriers. The northbound lanes here to will need to be rebuilt.


Image of view looking south along current US 220 roadway near NC 65 intersection showing temporary signageSome of the temporary signage on current US 220 South for NC 65. Though ramps are built, traffic from NC 65 uses traffic signals to enter US 220. (Photos of ramps below).


Image of view looking south along current US 220 roadway at nearly complete NC 65 bridge over the future interstateHeading south on US 220 toward the nearly completed NC 65 bridge over the future I-73/US 220 North lanes.


Image of view looking north along US 220 roadway at current intersection with NC 65 at future northbound on-ramp.Now looking north at current NC 65 intersection with traffic signals managing access to US 220.


Image of view looking west over nearly completed NC 65 bridge over US 220 roadwayLooking west toward nearly completed NC 65 bridge over future I-73/US 220 lanes. Traffic uses future northbound on-ramp beyond the current construction.


Image of view looking at construction at future NC 65 ramp to I-73/US 220 North in Guilford CountyTraffic on NC 65 West directed to use future on-ramp to I-73/US 220 North to access US 220 in both directions.


Image of view looking south down future I-73 North off-ramp to NC 65, currently under constructionLooking south from top of future I-73 North off-ramp to NC 65. Ramp is not currently open to traffic.


Image of view looking west over nearly completed NC 65 bridge over Future I-73/US 220 freeway in Guilford CountyLooking west from top of Future I-73 North off-ramp over nearly completed NC 65 bridge.


Image of view looking north down future I-73/US 220 North on-ramp from NC 65, now used by traffic in both directionsView of NC 65 Future On-ramp to I-73/US 220 North, now used by traffic also accessing NC 65.


Image of view travelling down Future I-73/US 220 North on-ramp from NC 65 in Guilford CountyDriving down the Future I-73/US 220 North on-ramp from NC 65 to access US 220 South.


Image of view at end of Future I-73/US 220 North on-ramp from NC 65 in Guilford CountyView at the end of the Future I-73/US 220 North ramp, which is blocked off for northbound traffic which must take a right at the temporary traffic lights.


Image of view from US 220 South of nearly completed NC 65 bridge in Guilford CountyAnother view of the open NC 65 bridge over Future I-73/US 220 work is continuing in the future south lanes.


Image of view northbound on US 220 looking at approaching NC 65 bridge, almost completedLooking northbound at approach to NC 65 bridge and unopened future off-ramp from I-73/US 220.


Image of view looking north along US 220 at I-73 construction progress between US 158 and NC 65 in Guilford CountyView Northbound farther from NC 65 showing work in future southbound lanes continuing and beginning of sound barrier walls, see below for more.


Image of Future I-73 sign on US 220 North betwen US 158 and NC 65 in Guilford CountyStill northbound, here is the one Future I-73 sign along this segment of US 220.


Image of view looking south along US 220 just beyond NC 65 bridge showing construction progressView looking south again beyond NC 65 on US 220 South showing traffic using future northbound lanes and former left turn lane for NC 65 blocked off.


Image of view of newly erected sound barrier walls along Future I-73/US 220 South lanes in Guilford CountyLooking from US 220 South to new sound barrier walls having been placed along Future I-73/US 220 South lanes.


Image of view of southern section of sound barrier walls along Future I-73/US 220 South lanes in Guilford County The sound barrier walls continue on approaching the US 158 interchange.


Image of northbound view along US 220 looking at newly installed sound barrier walls along Future I-73/US 220 South lanesReversing direction and looking at the installed sound barriers from US 220 North.


Image of view of I-73 construction along US 220 North in Guilford County after US 158 interchangeView looking north from bottom of hill after US 158 interchange showing progress in completing the Future I-73/US 220 South lanes.


Image of view along US 220 North approaching US 158 interchange showing progress of constructing I-73 in Guilford CountyHeading back south on US 220 approaching US 158 interchange showing work continuing on Future I-73 South lanes.


Image of view from US 220 South showing traffic switching between completed Future I-73 North and South lanesApproaching US 158 US 220 traffic is switched from completed Future I-73 North to I-73 South lanes to go over completed segment of US 158 bridge.


Image taken along US 220 of traffic on Future I-73 South bridge over US 158 in Guilford CountyBoth directions of US 220 traffic using Future I-73 South bridge over US 158. Future Northbound bridge appears near completion.


Image of view of temporary traffic lights allowing US 158 traffic to access US 220 North in Guilford CountyWhile South US 220 traffic can use completed US 158 off-ramp, northbound traffic must use connection from future South on-ramp to connect to US 220 North. Truck on the right is using the completed on-ramp.


Image of US 220 trailblazer along US 158 East approaching under construction interchange with Future I-73 in Guilford CountyTraffic on US 158 East is directed via this trailblazer to Future I-73 South on-ramp to connect to US 220.


Image of view up completed Future I-73 On-Ramp from US 158 in Guilford CountyLooking up completed on-ramp that will take traffic to I-73/US 220 South when work on the interchange is completed.


Image taken of new I-73 bridge over US 158 in Guilford CountyAnother look at completed Future I-73 South bridge over US 158 beyond on and off-ramps.


Image of view of completed on and off-ramps for Future I-73 South at US 158 in Guilford CountyView of traffic signals placed on US 158 at location of Future I-73 South on and off-ramps.


Image taken of new US 158 on-ramp to Future I-73/US 220 North in Guilford CountyView from temporary turn around to US 220 North of end of completed South on-ramp from US 158 to US 220 and Future I-73 South.


Image of view looking south on US 220 from just beyond US 158 interchange in Guilford CountyLooking south toward Haw River from just beyond US 158 exit shows progress in completing southern end of segment with potential cross over for future I-73/US 220 North traffic when Segment 3 opens in April.


Image of view south toward Future I-73/US 220 South interchange from hill overlooking Haw River in Guilford CountyContinuing south, the Future I-73/US 220 South interchange comes into view. Guardrail work along the Future I-73 lanes appears completed.


Image of completed Haw River bridges for Future I-73 traffic at US 220 interchange in Guilford CountyGetting closer to the interchange with view of completed Haw River bridges and work proceeding to add median guardrails to the Future I-73 South lanes.


Image of nearly complete Future I-73 and US 220 South interchange in Guilford CountyCloser view of bridges and interchange shows lane markings now placed on Future I-73 North lanes.


Image of completed US 220 South ramp departing from Future I-73 South Lanes near Haw River in Guilford CountyUS 220 traffic departs on Future off-ramp from I-73 South. Road closed barriers and orange barrels should not be there for too much longer.


Previous Photos: Taken by Strider in February 2017:

Image of view from NC 68 North of bridge construction for new I-73/US 220 interchange, by StriderLooking north toward the end of NC 68 showing completed future I-73/US 220 South bridge over roadway and future NC 68 South off-ramp.


Image of view from US 220 North of progress building new flyover bridge for I-73 South at NC 68, from StriderView from US 220 South approaching current NC 68 intersection showing nearly completed ramp towards the I-73/US 220 flyover bridge.


Image of closer view of future I-73/US 220 ramp over NC 68 and progress completing guardrail work, from StriderCloser view of new I-73/US 220 South ramp bridge over NC 68 showing progress in completing landscaping and guardrail work.


Image of view from US 220 South toward future US 158 interchange showing progress in paving southbound lanes, from StriderView from future northbound lanes looking south toward future US 158 interchange showing progress in paving future I-73 southbound lanes now flanked by sound walls.


Image of view closer to US 158 from US 220 South showing progress in completing future interchange, from StriderView from US 220 South closer to US 158 showing progress in completing the connection between the new southbound lanes and the existing roadway.


Image of view looking south on US 220 approaching future interchange with I-73 across the Haw River, from StriderView further south on US 220 approaching the future I-73 interchange showing median guardrails are being installed but that line painting is still needed for future northbound lanes.


Image of view close to future I-73/US 220 interchange from US 220 South showing progress constructing guardrails.

Previous Photos: Taken by Strider in mid to late November 2016:

Image of construction along US 220 for future I-73 at US 158 interchange, by StriderView from US 220 North on Future I-73 Southbound lanes facing toward the US 158 interchange showing the paved Future I-73 Northbound lanes awaiting lane striping.


Image from US 220 Northbound showing end of completed Future I-73 Southbound lanes and switch of traffic to Future I-73
          North lanes, north of US 158 interchange, photo by StriderView from US 220 North showing end of completed I-73 Southbound lanes and traffic shifting to existing US 220 roadway while remaining south I-73 lanes are constructed.


Image of Future I-73 Southbound lanes being paved from current US 220 North roadway north of US 158 interchange, by StriderLooking at paving taking place for Future I-73 South lanes from US 220 North. I-73 North lanes will use existing US 220 roadbed but will need to be rebuilt to Interstate standards after southbound lanes are completed and traffic shifted over.


Image of noise barriers being built next to future I-73 Southbound lanes near interchange with NC 68 from US 220 North, by StriderView from US 220 North of sound walls being built along Future I-73 Southbound lanes approaching interchange with NC 68.


Image of Future I-73 roadway and bridge under construction at US 220 and NC 68 intersection in Rockingham County, by StriderLooking north along US 220 approaching the future NC 68 interchange, and what will be the temporary end of I-73 North showing work continuing on building future I-73 South lanes and completed new bridge over NC 68.


Image showing completed bridge that will take I-73/US 220 South over NC 68 in Rockingham County, by StriderCloser view of completed bridge that will take I-73/US 220 South over NC 68.


Image looking south on US 220 showing progress in constructing future I-73 Southbound lanes after NC 68 intersection, by StriderLooking south on US 220 after NC 68 intersection showing work grading future I-73 South lanes, complicated by need to cut down small hill seen in the distance.


Image showing view from US 220 Southbound approaching nearly completed future interchange with I-73 near Haw River, by StriderAt the southern end of the segment, looking south on the completed I-73 southbound lanes approaching the future I-73/US 220 interchange by the Haw River.


Image looking at nearly completed future interchange between I-73 and US 220 near Haw River in Guilford County, by StriderA closer look at the interchange, showing most of the work is complete, the only thing needed are to paint the northbound lanes, re-stripe the south lanes, and add exit signage.



Previous Photos: Taken by Strider in mid-October 2016:

Image of construction along US 220 for future I-73 at US 158 interchange, by StriderEarlier photos, dates at the bottom:

View from US 220 North facing facing the US 158 interchange showing that the I-73 Northbound lanes are complete and paved. The off ramp to US 158 is also paved (out of frame).



Image of construction along US 220 North for future I-73 beyond US 158, by StriderView continuing north on US 220 past US 158 showing the southbound lanes of I-73 being prepared to be paved. Farther north near the NC 65 bridge, the road is paved. (NC 65 bridge is still not open despite it being fully paved).


Closer look of future I-73 lanes being readied to be paved north of US 158 on US 220, by StriderCloser look on US 220 North of US 158 showing the southbound I-73 lanes being prepared for pavement.


Image from US 220 North approaching future interchange with NC 68 showing construction progress, by StriderOn US 220 North approaching future NC 68 interchange. In the distance, the future I-73 southbound lanes are being paved. However, to the immediate left beyond the jersey barrier the road is not even graded yet.


Image of completed bridge at future I-73/NC 68 interchange in Rockingham County, by StriderView of complete bridge at the NC 68 interchange that will take I-73/US 220 traffic over NC 68.


Image looking south over future I-73/NC 68 interchange in Rockingham County, by StriderLooking south on US 220 toward the NC 68 interchange showing that US 220 is now the through route. The approaches to the bridge for Future I-73 South are still under construction.


Image of Future I-73/US 220 interchange looking south on US 220 toward Haw River Bridge, from StriderLooking south at the future I-73/US 220 interchange and the bridges over the Haw River showing that the future lanes are paved and ready for a line painting.


Previous Photos: Taken by Strider in August 2016:

Image of construction along US 220 for future I-73, by StriderView from US 220 North facing I-73 north partial interchange (Exit 119), the northbound lanes of US 220 are already paved while the I-73 lanes are in process of being paved as well.


Image of construction along US 220 for future I-73, by StriderView driving further north on US 220 near US 158 interchange (Exit 120). You can see I-73 northbound lanes are in process of being paved.


Image of construction along US 220 for future I-73, by StriderHeading north past the US 158 interchange, showing the future southbound lanes are being paved.


Image of construction along US 220 for future I-73, by StriderHere's a closer look past the US 158 interchange, they finally have begun doing work on the future I-73 southbound lanes.


Image of construction along US 220 for future I-73, by StriderDriving south on US 220, approaching the future I-73/US 220/NC 68 interchange (Exit 123), the bridge is halfway complete and the roadway approaches to the bridge is already graded.


Image of construction along US 220 for future I-73, by StriderA closer look at the future I-73/US 220/NC 68 interchange (Exit 123) showing the graded future roadway and the future I-73 bridge.


Image of construction along US 220 for future I-73, by StriderAt the other end of the project, looking at the Future I-73/US 220 interchange (Exit 119). You can see the pavement on US 220 north coming down to I-73, and the I-73 lanes are being paved.


Previous Photos: Taken by Strider in July 2016:

Image of construction at future NC 68 interchange with I-73, by StriderBridge supports being placed at site of future NC 68/I-73 Interchange.


Image of construction along US 220 for Future I-73 near NC 65 interchange, photo by StriderLooking South along US 220 just after Future NC 65 interchange showing work recently re-started on grading future roadway.


Image of construction at future I-73 interchange with US 220 near the Haw River, photo by StriderLooking South prior to Future US 220/I-73 partial interchange showing indications that crews are preparing to pave the highway.


Image of new bridge for Deboe Road under construction for future NC 68 interchange with I-73 in Rockingham County, from StriderPhotos Taken in June 2016:

Close look at new bridge being constructed to take traffic on Deboe Road over future I-73 roadway looking south.


Image of future I-73 NC 68 interchange as seen in distance from road paralleling US 220 North in Rockingham County, from StriderView in distance of construction progress at future I-73 interchange with NC 68.


Previous Photos taken by Strider, May 2016:

Image of US 220 North approaching future I-73 interchange, from StriderView from US 220 North approaching the future I-73 interchange with the NC 68-US 220 Connector, the future northbound on-ramp has not been completed.


Image of future I-73 lanes graded under US 220 South off-ramp bridge, by StriderView across current US 220 using future I-73 South off-ramp showing grading of future I-73 lanes to the south of the bridge.


Image looking south along US 220 toward future I-73/US 220 interchange, from StriderLooking south toward Haw River and progress in constructing the future I-73/US 220 South interchange beyond. Though the bridges over the Haw River are complete, much work remains in constructing the roadbed for I-73.


Image of US 220 North prior to NC 65 intersection showing I-73 construction progress, from StriderView along northbound US 220 just prior to current US 158 interchange showing progress in building new northbound lanes to the right.


Image of completed I-73 bridges over US 158, by StriderView looking along US 158 East toward completed Future I-73 bridges over US 158 and showing further construction needed to complete new US 158 westbound roadway.


Image of future southbound lanes for I-73 under construction along US 220, from StriderLooking north along US 220 north toward NC 65 exit showing still incomplete roadbed for future I-73 Southbound lanes.


Image of Future I-73 sign along US 220 beyond NC 65 exit, from StriderFuture I-73 sign recently put up between US 158 and NC 65 exits along US 220 North. Probably should be Future I-73 Corridor since similar signs appear on completed freeways.


Image of completed NC 65 bridge over US 220/Future I-73 North, from StriderView of completed NC 65 interchange bridge over US 220 and Future I-73 Northbound Lanes.


Image of clearing and construction for new NC 68 interchange on I-73, from StriderView on US 220 North approaching NC 68 intersection showing progress in building new interchange at northern end of I-73.


Image of construction for I-73 at current intersection of US 220 and NC 68, from StriderView of new lanes being added just north of current NC 68/US 220 intersection to accommodate new interchange.


Image of construction on future I-73 NC 68 interchange from access road along US 220 North, from StriderView looking south from access road parallel to US 220 North at progress in constructing new I-73 interchange with NC 68.


Photos taken by Strider, January 2015:

Image of I-73 construction as seen from US 220 North near Summerfield, NC Photo by StriderStarting on US 220 North, approaching the future interchange with I-73 near the Haw River, future NB lanes being paved, traffic shifting to new lanes in distance.


Image of new US 220 Bridge over Haw River at future I-73 interchange near Summerfield, 
NC. Photo by StriderLooking from a new frontage road being built along US 220 South, this is the completed US 220 South bridge over the Future I-73 that both directions of US 220 are currently using.


Image of future I-73 NB lanes under construction across the Haw River, photo by StriderView of completed future I-73 South bridge over the Haw River and future I-73 North lanes under construction, from future NB frontage road.


Image of closer view of I-73 construction across the Haw River near Summerfield, NC, 
photo by StriderCloser view of the future I-73 Northbound lanes under construction near the Haw River.


View of traffic on US 220 using completed future I-73 SB lanes near Summerfield, NC, 
Photo by StriderView heading north on US 220 showing traffic using the completed future I-73 Southbound lanes.


Image of future I-73 North lanes under construction near Summerfield, NC, photo by 
StriderUnique view looking forward and back of US 220 traffic about to cross future I-73 southbound bridge with future I-73 lanes under construction in the distance.


Image of travelling north on US 220 on future I-73 SB lanes approaching US 158, photo
by StriderHeading further north on US 220 using the future I-73 Southbound lanes approaching the US 158 interchange.


Image of I-73 construction along US 220 North approaching the US 158 interchange near 
Summerfield, NC, photo by StriderFurther north on US 220 near the US 158 interchange, the gas station to the right is currently cut off from US 220, but an access road is being built to connect it to the new parallel frontage road that ends just before the US 158 off-ramp.


Image of US 220 traffic using future I-73 SB bridge over US 158 near Summerfield, NC, 
photo by StriderUS 220 traffic crossing over US 158 on future I-73 Southbound bridge. The future northbound span is under construction after the original US 220 bridge was demolished.


Image of US 220 traffic now using future I-73 NB lanes north of the US 158 interchange 
near Summerfield, NC, Photo by StriderUS 220 traffic switches to use the future I-73 Northbound lanes after the US 158 interchange.


Image of traffic on US 220 North just south of future NC 65/I-73 interchange, photo by 
StriderApproaching the future NC 65 interchange on US 220 North. The off-ramp is paved but not open. The future NC 65 bridge under construction can be seen in the distance.


Turning around at the future NC 68 interchange and heading back south:

View of progress constructing I-73 on US 220 South just south of NC 68 intersection, 
photo by StriderNow heading south on US 220 here's the view of construction progress, slowed by design changes, just south of the NC 68 intersection.


Image approaching the future NC 65 bridge over I-73 on US 220 South, photo by StriderView of future NC 65 bridge under construction from US 220 South. The intersection is currently controlled by 2 traffic lights, the first just behind the photo and the second beyond the bridge and seen in the photo above.


Image of future southbound lanes for I-73 being graded between NC 65 and US 158, photo 
by StriderView along US 220 South between NC 65 and US 158 using future I-73 northbound lanes and future southbound lanes being graded.


Image of US 220 South at future I-73/US 158 interchange near Summerfield, NC, photo by
StriderUS 220 South at the US 158 interchange. The southbound ramp is complete and open to traffic, drivers wanting to access US 158 northbound must turn left and yield at the southbound ramp.


Image of US 220 South approaching the Haw River and completed  future I-73 bridges, 
near Summerfield, NC, photo by StriderUS 220 South descending toward the Haw River with the future I-73 South/US 220 interchange bridges in the distance.


Image of US 220 crossing the new I-73 US 220 exit ramp bridge over the Haw River, photo
by StriderCrossing the recently opened future I-73 South, US 220 off-ramp bridge over the Haw River temporarily carrying US 220 traffic.


Image of US 220 traffic crossing future US 220 South off-ramp bridge over I-73 near 
Summerfield, NC, photo by StriderView of US 220 traffic crossing newly opened future US 220 South bridge over the future I-73 (US 220-NC 68 Connector) freeway. Though work on the Connector has started, nothing has started at this end yet.


Previous Photos. A couple taken by Lyn Hay, Greensboro News Record on February 1, 2014:

Image of US 220 widening construction progress for I-73, Lyn 
Hay Greensboro News Record, 2/1/14US 220 traffic traveling through I-73 construction site north of Greensboro.


Image of progress widening US 220 to become I-73, Lyn Hay 
Greensboro News Record, 2/1/14 Progress on constructing future Haw River bridges for I-73.


Below are photos taken in December 2012 and April 2013 (Courtesy of Strider):

Photo of I-73 Bridge Construction near future interchange with US 220, courtesy 
of StriderThis photo shows construction progress on the future I-73 South bridge across the Haw River from US 220 North. (4/3/13)


Photo of I-73 Construction Clearing from US 220 North, courtesy of 
StriderThis photo shows progress clearing the path for I-73 from US 220 North across the Haw River from the future I-73 interchange. (4/3/13)


Photo from US 220 North showing I-73 Construction between future interchange 
with US 220 and US 158, courtesy of StriderThis photo shows progress clearing the future I-73 roadbed between the future US 220 interchange and US 158. (4/3/13)


Photo of I-73 Construction near interchange with US 158, courtesy of 
StriderThis photo shows progress clearing the future I-73 South road bed a mile south the US 158 interchange on US 220 North. (4/3/13)


Photo of I-73 Construction near US 220 North interchange with US 158, courtesy 
of StriderThis photo shows clearing the I-73 road bed approaching the current US 220 interchange with US 158. (4/3/13)


Photo of I-73 Construction near interchange of US 220 North and US 158, courtesy 
of StriderThis photo shows progress clearing areas near the future I-73 interchange for US 158 from US 220 North. (4/3/13)


Photo from US 220 South approaching Haw River and Construction of future 
interchange with I-73, courtesy of StriderThis photo shows the future I-73 freeway road bed from US 220 South approaching the location of the future bridge across the Haw River. (4/3/13)


Photo of I-73 Construction showing Future I-73 South Ramp from US 220 South, 
courtesy of StriderThis photo shows the future I-73 South ramp that will use the future bridge over the Haw River. (4/3/13)


Photo of US 220 Construction near future interchange with I-73, courtesy of 
StriderThis photo shows the future I-73 South road bed (the US 220 South ramp will go across this roadway via future bridge). (12/9/12)


Photo of Future I-73/US 220 Lanes north of Greensboro, Dec. 2012,
Courtesy of StriderView showing the proposed US 220/ I-73 bridges across the Haw River. The current US 220 will apparently become a part of frontage road once this construction is all done. US 220 will be moved on the new lanes (with I-73). (12/9/12)


Photo of future I-73 offramp for US 220, Dec. 2012, courtesy of StriderThis picture shows the visible future US 220 South ramp on the far right, where it will curve to the right, then left to across the future I-73 roadbed, then back to its current alignment. The construction on this section really sped up in the last couple months. (12/9/12)


Photo of US 220 construction progress north of Greensboro near US 158, 
Dec. 2012, courtesy of StriderThis photo was taken near the US 158 interchange. Not much is going on here except the blasting and dragging of the rocks to make a room for the roadbed. There are a few houses behind the construction trucks. What they will do about these houses once the road is open to traffic is unknown. (12/9/12)


Photo of US 220 widening construction near US 158 north of Greensboro, Dec. 
2012, courtesy of StriderProgress in clearing land near the future US 158 interchange. (12/9/12)


Photo of clearing work for US 220 widening project near US 158, Dec. 2012, 
Courtesy of StriderAnother view of progress in clearing the future roadbed near the US 158 interchange. (12/9/12)


Photo of progress clearing land for the US 220 Widening Project at Future 
US 158 interchange, Dec. 2012, Courtesy of StriderThis picture was taken at the US 158 interchange. Not much is going on there either, except clearing of the trees. (12/9/12)






.


Photos of segment before construction showing what US 220 looked like as of November 2009 (all photos courtesy of Bonnie Wilcox, except where noted).:

Photo of US 220 near the future location of the interchange with the 
NC 68 Connector, Nov. 2009This is looking at US 220 North, at the bottom of the hill is the Haw River. Somewhere between the green sign in the distance and the River is supposedly where the NC68-US 220 Connector will tie into US 220. North of there the road will be upgraded to a freeway with a 60 mph design speed.


Photo of the existing US 158/US 220 Interchange that is to be upgraded
during widening project, Nov. 2009The existing interchange for US 158, Stokesdale, Winston-Salem. The interchange will be rebuilt to accomodate a modern four lane interstate.


Photo of current intersection between US 220 and NC 65 to be upgraded to
and interchange, Nov. 2009Going north the next interchange will be with NC 65, Stokesdale, Reidsville. This is currently an at-grade intersection.


Photo of US 220/NC 68 intersection prior to widening construction, Nov. 2009This is the view of US 220 North approaching the NC 68 intersection. Going south, currently NC 68 continues straight as a 4-lane highway while US 220 traffic has to make a left turn across NC 68 traffic. This will initially be rebuilt so that US 220 (I-73) will be the primary roadway and there will be a signalized intersection to allow NC 68 North traffic to turn onto US 220. (2/09)


Other US 220 Widening

NCDOT also has another contract (R-2309) to widen US 220 south of the Connector to Horsepen Creek Road that is going on at the same time as the widening north of the Connector. This southern part will be constructed to expressway standards and have a 45 MPH speed limit. For a look at the highway section to be widened see photos below. Many area residents objected to this planned widening feeling that it is unnecessarily wide and costly, especially since the road already goes through several residential areas and crosses lakes that are currently part of Greensboro's water supply. An NCDOT spokesman insisted the widening is necessary because US 220 is one of North Carolina's Strategic Highway Corridors.13 The statement though is wrong, currently the corridor applies only to where US 220 is to become I-73. Since I-73 is not using this part of US 220, but rather the Connector (see a fuller discussion on the I-73 Segment 4 page) it seems likely that less traffic, and definitely fewer trucks, will use this part of US 220 than NCDOT's estimates show. Local citizens efforts to press NCDOT for a more reasonable solution seem not to have been successful.14 Much of this widening work was completed in late August 2017 with the opening of the section from Horsepen Creek Road north 1.5 miles to Owl's Roost Road.15

Photo of US 220 in area to be widened for I-73, Dec. 2009, courtesy of 
Bonnie WilcoxThe view of US 220 North at the current end of the widened 4-lane section. The rest of the route to the Connector is to be widened as well, if NCDOT does not change its mind in response to citizen concerns. As you can see in the distance, several new traffic signals have already been added to the highway.


Photo of US 220 in area to be widened not related to I-73, Dec. 2009, 
Courtesy of Bonnie WilcoxAnother view of the current US 220 North as it travels through the Cape Fear River Basin and over several lakes used as Greensboro's water supply.