Image of NC Interstate 73 shield, courtesy of Shield's Up! Segment 2

Section of NCDOT State Transportation Map with I-73 Segment 2, US 220 north of Summerfield

Where: US 220, From NC 68 to US 220-NC 68 Connector

Length: 4 Miles

Needed: Upgrade Highway to Interstate Freeway

Project Started: April 2012

Completion Date: October 18, 2017

Existing Road Signed as:  Image of Future I-73 sign installed along US 220 in Guilford County

Jump to Photos

Segment Info

South of NC 68, US 220 is mostly a two-lane roadway. As part of a project that will build the 'NC 68-US 220 Connector' north of Greensboro (Project No. R-2413, see Segment 3 below), NCDOT is upgrading the current highway to a four-lane freeway for about 4 miles between the NC 68 intersection and the Connector to be built just south of the Haw River. Work on this segment, Contract R-2413C, started in May 20121 (delayed from 2010) and has fallen significantly behind the project completion schedule. As of April 15, 2017 the project was listed as 74.4% complete, far behind a schedule that would have completed the route by December 27, 2016.2 To illustrate the slow progress rate, in July 2013, more than 3 1/2 years ago, the project was 21.5% complete.3 In August 2015, NCDOT finally admitted the project would not be completed on time and pushed completion back to June 19, 2017.2 In June 2016, the completion date was pushed back again to January 25, 2018.2 However, a news report in early April 2017 indicated that NCDOT hoped to open the route by October 2017, an NCDOT official indicated in August 2017 that the hopeful date was October 18.4 Much progress has been made in the past couple months though with the future NC 65 and US 158 off-ramps being opened to traffic (see photos below). Complicating factors was a decision by NCDOT to change the plans at the northern end of the project from a re-worked intersection with NC 68 that included a traffic signal to a more complicated flyover ramp for US 220 South to cross over NC 68. NCDOT held a public meeting to inform the public in January 2014 from which planners were to resubmit the design for the interchange.5 NCDOT then decided to let this as a separate project, Contract C203645 awarded on June 16, 2015. Construction started on Sept. 16, 2015 and, as of April 7, 2017 was 67.4% complete (this project is also going slow, it was supposed to be 94.2% complete by that time though).6 Despite the project being only 2/3 complete, enough work has been completed on the future I-73 South roadway that it, along with the new off-ramp to NC 68, was opened in May 2017 (see photos below). The project plans, released on May 19, 2015, revealed the following design for the new interchange (based on other contract documents, the number for the NC 68 exit will be 123, while the NC 65 exit will be 122):

Image of signage plan for to be constructed US 220 NC 68 interchange in Rockingham 
County, courtesy of NCDOT






Sign Plans for This Segment

Contributor Strider sent me these photos of the hard copy plans he has of future exit signs along this Segment, heading North to South:7

Plan of future exit signage at NC 68 exit off of I-73 South, from StriderPlans for exit and gore signs for NC 68 interchange on I-73 South.


Plans for future signage for US 158 and NC 65 exits on I-73 South, from StriderPlans for exit signs for US 158 and NC 65 along I-73/US 220 North. Since there is no exit to NC 68 South northbound, traffic is told to use NC 65.


Plan of exit sign for US 158 on I-73 South near Stokesdale, from StriderPlans for US 158 Exit Sign, as noted in the plans, the current exit sign will not be replaced, just a new exit tab will be placed on top.


Plan for 1/2 mile advance exit sign for US 220 on I-73 South near Summerfield, from Strider1/2 mile advance signage for US 220 exit on I-73 South near the Haw River, note I-73 pull through for Airport traffic.


Plans for overhead signage at US 220 exit off of I-73 South in Summerfield, from StriderPlans for signage at the US 220 exit, current US 220 traffic is using the future 2-lane off-ramp as the route for through traffic.


The NC 68 project was awarded on July 7, 2015 to Branch Highways Inc. out of Roanoke, VA for $14 million.8 The total cost for the entire project (right-of-way and construction) is now budgeted at around $223 million.9 Initially, the roadway was not to be built to Interstate standards, but only at a 60 MPH limited access highway. However, this changed when the Connector project to the south was advanced to be completed around the same time both segment are now to be signed as I-73, with a 65 MPH speed limit, when completed.10,11

The US 220 South ramp from I-73 South will be a flyover bridge that will go both over the Haw River and then over I-73 to its current alignment (for a link to the plans see Segment 3, below). Work to complete this flyover was completed during the fall of 2014 and US 220 traffic was rerouted onto it (see photos below). The US 220 project was to be mostly completed before work on the Connector to NC 68 was finished, however with the current delays, this might not happen since the Connector work is to be completed by April 2017. (For an NCDOT diagram of the entire project go to the Project page.)

"Drive" This Segment Using Google Maps Street View from July 2016

US 220 South at Beginning of Construction Zone: Just South of NC 68 Intersection

US 220 South at NC 65: On Future I-73 NB Roadway

US 220 North at US 158: On Future I-73 SB Roadway at US 158 On-Ramp

US 220 North at Future I-73 South Interchange: On Future US 220 South Ramp

Segment 2 Construction Photos, Hover Over to get Larger Image.

For other photos, check out NCDOT's US 220 Widening Project Flickr Page

Most Recent Photos by Site Contributor Strider on May 20, 2017:

Image taken of newly opened I-73 proceeding south from US 220 South interchange in Summerfield, by StriderLooking south on US 220 just prior to the Haw River showing opening of I-73 connector roadway to NC 68. There currently are no exit signs at the interchange, just trailblazers (on the left behind the 3rd orange barrel) as the case with the NC 65 interchange to the north.


Previous photos taken on April 11, 2017:

Image taken of overhead exit signage above US 220/Future I-73 South at NC 68 exit in Rockingham County, by StriderView from US 220 South now shifted onto Future I-73 South lanes over NC 68 of overhead signage for new exit ramps opened for NC 68 and NC 65, exit tabs will be added later.


Image taken from US 220 South approaching newly opened off-ramp to NC 65 from Future I-73 South, by StriderView on US 220 South now on Future I-73 South lanes between NC 68 and NC 65 showing NC 65 trailblazer temporarily marking the new off-ramp.


Image of US 220 traffic using Future I-73 South lanes from NC 65 bridge, by StriderView from completed NC 65 bridge looking south showing US 220 traffic using Future I-73 Southbound lanes and completed on and off-ramps heading toward US 158.


Image of US 220 South traffic using Future I-73 Southbound lanes between NC 65 and US 158 in Guilford County, by StriderView heading further south on US 220 between NC 65 and US 158 showing traffic using Future I-73 lanes next to completed sound barrier wall.


Image of view along US 220 North just beyond US 158 interchange in Guilford County, by StriderNow heading back northbound, traffic is now using the Future I-73 North bridge over US 158, with the exit ramps open the temporary signals have been removed from the wires ahead.


Image taken on US 220 North prior to former lane shift for traffic on Future I-73 South lanes in Guilford County, by StriderFurther north on US 220 beyond US 158 at what was the shift of traffic to the original US 220 lanes, now shifted to the new Future I-73 South lanes while the old US 220 lanes are reconstructed for northbound traffic.


Image of view of construction of Future I-73 North lanes from US 220 North in Guilford County, by StriderFrom US 220 North showing work starting on removing hill under former US 220 lanes to match the grade of the Future I-73 South lanes.


Image of new NC 65 and NC 68 trailblazer to mark recently opened off-ramp from US 220 North from Future I-73 South lanes, by StriderNew NC 65/NC 68 South trailblazer marks temporary off-ramp from Future I-73 South lanes to newly opened NC 65 off-ramp from northbound lanes. To match the future exit sign, there should be a 'To' between the NC 65 and 68 shields. With the opening of the NC 68 South off-ramp there is no longer direct access to NC 68 from US 220 North.


Image of recently opened off-ramp to NC 65 from US 220 North using Future I-73 South lanes, from StriderCloser look at newly opened ramp to NC 65 from Future I-73 Northbound lanes from US 220 North.


Image of recently completed NC 65 bridge from US 220 North using Future I-73 South lanes, from StriderHeading under the new NC 65 bridge on US 220 North using Future I-73 Southbound lanes.


Image of construction of I-73 North from US 220 North using Future I-73 South lanes beyond NC 65, from StriderFurther north beyond NC 65 on US 220 showing work starting on creating Future I-73 Northbound lanes.


Image from US 220 using recently opened Future I-73 South lanes approaching NC 68 interchange, from StriderView approaching NC 68 from US 220 North now using Future I-73 Southbound lanes.


Image from recently opened bridge over NC 68 from US 220 North using Future I-73 South lanes, from StriderView from heading across new bridge over NC 68 that will carry Future I-73 Southbound lanes. Old US 220 to carry I-73 North traffic below.


Image of recently opened off-ramp to NC 65 from US 220 North using Future I-73 South lanes, from StriderView from end of NC 68 North approaching new bridge for Future I-73/US 220 South traffic with newly opened NC 68 ramp on left. Trailblazer for South US 220 has been removed on the right.


Image of recently paved US 220 North beyond NC 68 on-ramp in Rockingham County, from StriderNow back on US 220 North beyond the NC 68 North on-ramp approaching the end of the construction zone. Perhaps some day I-73 will make it the 30 miles to Martinsville.


Image of recently opened off-ramp to NC 65 from US 220 North using Future I-73 South lanes, from StriderHeading back south, the view of US 220 traffic using the newly opened Future I-73 South lanes prior to the new NC 68 exit.


Photos taken by the Webmaster on March 30, 2017:

Image of I-73 ramp construction at intersection of US 220 and NC 68Looking east at current intersection of NC 68 with US 220 showing completed bridge for Future I-73/US 220 South traffic and ramp to left which will carry traffic to NC 68 South.


Image of new US 220 (Future I-73) roadway south from end of NC 68 NorthLooking south from NC 68 toward future I-73/US 220 roadway which will carry southbound lanes upon completion of new interchange.


Image of travelling under new I-73 South bridge at end of NC 68 North at US 220About to travel under the completed Future I-73/US 220 South bridge prior to NC 68 North meeting US 220.


Image of view looking south along current US 220 roadway which will become northbound lanes after NC 68 interchange project is 
        completedLooking south on current US 220 roadway paralleling new I-73/US 220 South lanes. This will become the northbound lanes merging with NC 68 traffic when interchange project is completed.


Image of view looking south along current US 220 roadway just after NC 68 intersection showing progress building 
        future I-73 South lanesLooking south on current US 220 roadway just after the NC 68 intersection. Work is proceeding on building new southbound lanes on other side of guardrail.


Image of view looking south along current US 220 roadway approaching NC 65 intersection showing progress building new south 
        I-73 lanesFurther south approaching existing distance sign, paving going on to the right of the orange barrels for new southbound lanes. Once these are completed traffic will shift over so hill in the distance can be graded down to match elevation of the new lanes.


Image of view looking south along current US 220 roadway which will become northbound lanes after NC 68 interchange project is 
        completedFurther south on current US 220 approaching NC 65, progress on the new southbound roadway here cannot be seen due to the concrete barriers. The northbound lanes here to will need to be rebuilt.


Image of view looking south along current US 220 roadway near NC 65 intersection showing temporary signageSome of the temporary signage on current US 220 South for NC 65. Though ramps are built, traffic from NC 65 uses traffic signals to enter US 220. (Photos of ramps below).


Image of view looking south along current US 220 roadway at nearly complete NC 65 bridge over the future interstateHeading south on US 220 toward the nearly completed NC 65 bridge over the future I-73/US 220 North lanes.


Image of view looking north along US 220 roadway at current intersection with NC 65 at future northbound on-ramp.Now looking north at current NC 65 intersection with traffic signals managing access to US 220.


Image of view looking west over nearly completed NC 65 bridge over US 220 roadwayLooking west toward nearly completed NC 65 bridge over future I-73/US 220 lanes. Traffic uses future northbound on-ramp beyond the current construction.


Image of view looking at construction at future NC 65 ramp to I-73/US 220 North in Guilford CountyTraffic on NC 65 West directed to use future on-ramp to I-73/US 220 North to access US 220 in both directions.


Image of view looking south down future I-73 North off-ramp to NC 65, currently under constructionLooking south from top of future I-73 North off-ramp to NC 65. Ramp is not currently open to traffic.


Image of view looking west over nearly completed NC 65 bridge over Future I-73/US 220 freeway in Guilford CountyLooking west from top of Future I-73 North off-ramp over nearly completed NC 65 bridge.


Image of view looking north down future I-73/US 220 North on-ramp from NC 65, now used by traffic in both directionsView of NC 65 Future On-ramp to I-73/US 220 North, now used by traffic also accessing NC 65.


Image of view travelling down Future I-73/US 220 North on-ramp from NC 65 in Guilford CountyDriving down the Future I-73/US 220 North on-ramp from NC 65 to access US 220 South.


Image of view at end of Future I-73/US 220 North on-ramp from NC 65 in Guilford CountyView at the end of the Future I-73/US 220 North ramp, which is blocked off for northbound traffic which must take a right at the temporary traffic lights.


Image of view from US 220 South of nearly completed NC 65 bridge in Guilford CountyAnother view of the open NC 65 bridge over Future I-73/US 220 work is continuing in the future south lanes.


Image of view northbound on US 220 looking at approaching NC 65 bridge, almost completedLooking northbound at approach to NC 65 bridge and unopened future off-ramp from I-73/US 220.


Image of view looking north along US 220 at I-73 construction progress between US 158 and NC 65 in Guilford CountyView Northbound farther from NC 65 showing work in future southbound lanes continuing and beginning of sound barrier walls, see below for more.


Image of Future I-73 sign on US 220 North betwen US 158 and NC 65 in Guilford CountyStill northbound, here is the one Future I-73 sign along this segment of US 220.


Image of view looking south along US 220 just beyond NC 65 bridge showing construction progressView looking south again beyond NC 65 on US 220 South showing traffic using future northbound lanes and former left turn lane for NC 65 blocked off.


Image of view of newly erected sound barrier walls along Future I-73/US 220 South lanes in Guilford CountyLooking from US 220 South to new sound barrier walls having been placed along Future I-73/US 220 South lanes.


Image of view of southern section of sound barrier walls along Future I-73/US 220 South lanes in Guilford County The sound barrier walls continue on approaching the US 158 interchange.


Image of northbound view along US 220 looking at newly installed sound barrier walls along Future I-73/US 220 South lanesReversing direction and looking at the installed sound barriers from US 220 North.


Image of view of I-73 construction along US 220 North in Guilford County after US 158 interchangeView looking north from bottom of hill after US 158 interchange showing progress in completing the Future I-73/US 220 South lanes.


Image of view along US 220 North approaching US 158 interchange showing progress of constructing I-73 in Guilford CountyHeading back south on US 220 approaching US 158 interchange showing work continuing on Future I-73 South lanes.


Image of view from US 220 South showing traffic switching between completed Future I-73 North and South lanesApproaching US 158 US 220 traffic is switched from completed Future I-73 North to I-73 South lanes to go over completed segment of US 158 bridge.


Image taken along US 220 of traffic on Future I-73 South bridge over US 158 in Guilford CountyBoth directions of US 220 traffic using Future I-73 South bridge over US 158. Future Northbound bridge appears near completion.


Image of view of temporary traffic lights allowing US 158 traffic to access US 220 North in Guilford CountyWhile South US 220 traffic can use completed US 158 off-ramp, northbound traffic must use connection from future South on-ramp to connect to US 220 North. Truck on the right is using the completed on-ramp.


Image of US 220 trailblazer along US 158 East approaching under construction interchange with Future I-73 in Guilford CountyTraffic on US 158 East is directed via this trailblazer to Future I-73 South on-ramp to connect to US 220.


Image of view up completed Future I-73 On-Ramp from US 158 in Guilford CountyLooking up completed on-ramp that will take traffic to I-73/US 220 South when work on the interchange is completed.


Image taken of new I-73 bridge over US 158 in Guilford CountyAnother look at completed Future I-73 South bridge over US 158 beyond on and off-ramps.


Image of view of completed on and off-ramps for Future I-73 South at US 158 in Guilford CountyView of traffic signals placed on US 158 at location of Future I-73 South on and off-ramps.


Image taken of new US 158 on-ramp to Future I-73/US 220 North in Guilford CountyView from temporary turn around to US 220 North of end of completed South on-ramp from US 158 to US 220 and Future I-73 South.


Image of view looking south on US 220 from just beyond US 158 interchange in Guilford CountyLooking south toward Haw River from just beyond US 158 exit shows progress in completing southern end of segment with potential cross over for future I-73/US 220 North traffic when Segment 3 opens in April.


Image of view south toward Future I-73/US 220 South interchange from hill overlooking Haw River in Guilford CountyContinuing south, the Future I-73/US 220 South interchange comes into view. Guardrail work along the Future I-73 lanes appears completed.


Image of completed Haw River bridges for Future I-73 traffic at US 220 interchange in Guilford CountyGetting closer to the interchange with view of completed Haw River bridges and work proceeding to add median guardrails to the Future I-73 South lanes.


Image of nearly complete Future I-73 and US 220 South interchange in Guilford CountyCloser view of bridges and interchange shows lane markings now placed on Future I-73 North lanes.


Image of completed US 220 South ramp departing from Future I-73 South Lanes near Haw River in Guilford CountyUS 220 traffic departs on Future off-ramp from I-73 South. Road closed barriers and orange barrels should not be there for too much longer.


Previous Photos: Taken by Strider in February 2017:

Image of view from NC 68 North of bridge construction for new I-73/US 220 interchange, by StriderLooking north toward the end of NC 68 showing completed future I-73/US 220 South bridge over roadway and future NC 68 South off-ramp.


Image of view from US 220 North of progress building new flyover bridge for I-73 South at NC 68, from StriderView from US 220 South approaching current NC 68 intersection showing nearly completed ramp towards the I-73/US 220 flyover bridge.


Image of closer view of future I-73/US 220 ramp over NC 68 and progress completing guardrail work, from StriderCloser view of new I-73/US 220 South ramp bridge over NC 68 showing progress in completing landscaping and guardrail work.


Image of view from US 220 South toward future US 158 interchange showing progress in paving southbound lanes, from StriderView from future northbound lanes looking south toward future US 158 interchange showing progress in paving future I-73 southbound lanes now flanked by sound walls.


Image of view closer to US 158 from US 220 South showing progress in completing future interchange, from StriderView from US 220 South closer to US 158 showing progress in completing the connection between the new southbound lanes and the existing roadway.


Image of view looking south on US 220 approaching future interchange with I-73 across the Haw River, from StriderView further south on US 220 approaching the future I-73 interchange showing median guardrails are being installed but that line painting is still needed for future northbound lanes.


Image of view close to future I-73/US 220 interchange from US 220 South showing progress constructing guardrails.

Previous Photos: Taken by Strider in mid to late November 2016:

Image of construction along US 220 for future I-73 at US 158 interchange, by StriderView from US 220 North on Future I-73 Southbound lanes facing toward the US 158 interchange showing the paved Future I-73 Northbound lanes awaiting lane striping.


Image from US 220 Northbound showing end of completed Future I-73 Southbound lanes and switch of traffic to Future I-73
          North lanes, north of US 158 interchange, photo by StriderView from US 220 North showing end of completed I-73 Southbound lanes and traffic shifting to existing US 220 roadway while remaining south I-73 lanes are constructed.


Image of Future I-73 Southbound lanes being paved from current US 220 North roadway north of US 158 interchange, by StriderLooking at paving taking place for Future I-73 South lanes from US 220 North. I-73 North lanes will use existing US 220 roadbed but will need to be rebuilt to Interstate standards after southbound lanes are completed and traffic shifted over.


Image of noise barriers being built next to future I-73 Southbound lanes near interchange with NC 68 from US 220 North, by StriderView from US 220 North of sound walls being built along Future I-73 Southbound lanes approaching interchange with NC 68.


Image of Future I-73 roadway and bridge under construction at US 220 and NC 68 intersection in Rockingham County, by StriderLooking north along US 220 approaching the future NC 68 interchange, and what will be the temporary end of I-73 North showing work continuing on building future I-73 South lanes and completed new bridge over NC 68.


Image showing completed bridge that will take I-73/US 220 South over NC 68 in Rockingham County, by StriderCloser view of completed bridge that will take I-73/US 220 South over NC 68.


Image looking south on US 220 showing progress in constructing future I-73 Southbound lanes after NC 68 intersection, by StriderLooking south on US 220 after NC 68 intersection showing work grading future I-73 South lanes, complicated by need to cut down small hill seen in the distance.


Image showing view from US 220 Southbound approaching nearly completed future interchange with I-73 near Haw River, by StriderAt the southern end of the segment, looking south on the completed I-73 southbound lanes approaching the future I-73/US 220 interchange by the Haw River.


Image looking at nearly completed future interchange between I-73 and US 220 near Haw River in Guilford County, by StriderA closer look at the interchange, showing most of the work is complete, the only thing needed are to paint the northbound lanes, re-stripe the south lanes, and add exit signage.



Previous Photos: Taken by Strider in mid-October 2016:

Image of construction along US 220 for future I-73 at US 158 interchange, by StriderEarlier photos, dates at the bottom:

View from US 220 North facing facing the US 158 interchange showing that the I-73 Northbound lanes are complete and paved. The off ramp to US 158 is also paved (out of frame).



Image of construction along US 220 North for future I-73 beyond US 158, by StriderView continuing north on US 220 past US 158 showing the southbound lanes of I-73 being prepared to be paved. Farther north near the NC 65 bridge, the road is paved. (NC 65 bridge is still not open despite it being fully paved).


Closer look of future I-73 lanes being readied to be paved north of US 158 on US 220, by StriderCloser look on US 220 North of US 158 showing the southbound I-73 lanes being prepared for pavement.


Image from US 220 North approaching future interchange with NC 68 showing construction progress, by StriderOn US 220 North approaching future NC 68 interchange. In the distance, the future I-73 southbound lanes are being paved. However, to the immediate left beyond the jersey barrier the road is not even graded yet.


Image of completed bridge at future I-73/NC 68 interchange in Rockingham County, by StriderView of complete bridge at the NC 68 interchange that will take I-73/US 220 traffic over NC 68.


Image looking south over future I-73/NC 68 interchange in Rockingham County, by StriderLooking south on US 220 toward the NC 68 interchange showing that US 220 is now the through route. The approaches to the bridge for Future I-73 South are still under construction.


Image of Future I-73/US 220 interchange looking south on US 220 toward Haw River Bridge, from StriderLooking south at the future I-73/US 220 interchange and the bridges over the Haw River showing that the future lanes are paved and ready for a line painting.


Previous Photos: Taken by Strider in August 2016:

Image of construction along US 220 for future I-73, by StriderView from US 220 North facing I-73 north partial interchange (Exit 119), the northbound lanes of US 220 are already paved while the I-73 lanes are in process of being paved as well.


Image of construction along US 220 for future I-73, by StriderView driving further north on US 220 near US 158 interchange (Exit 120). You can see I-73 northbound lanes are in process of being paved.


Image of construction along US 220 for future I-73, by StriderHeading north past the US 158 interchange, showing the future southbound lanes are being paved.


Image of construction along US 220 for future I-73, by StriderHere's a closer look past the US 158 interchange, they finally have begun doing work on the future I-73 southbound lanes.


Image of construction along US 220 for future I-73, by StriderDriving south on US 220, approaching the future I-73/US 220/NC 68 interchange (Exit 123), the bridge is halfway complete and the roadway approaches to the bridge is already graded.


Image of construction along US 220 for future I-73, by StriderA closer look at the future I-73/US 220/NC 68 interchange (Exit 123) showing the graded future roadway and the future I-73 bridge.


Image of construction along US 220 for future I-73, by StriderAt the other end of the project, looking at the Future I-73/US 220 interchange (Exit 119). You can see the pavement on US 220 north coming down to I-73, and the I-73 lanes are being paved.


Previous Photos: Taken by Strider in July 2016:

Image of construction at future NC 68 interchange with I-73, by StriderBridge supports being placed at site of future NC 68/I-73 Interchange.


Image of construction along US 220 for Future I-73 near NC 65 interchange, photo by StriderLooking South along US 220 just after Future NC 65 interchange showing work recently re-started on grading future roadway.


Image of construction at future I-73 interchange with US 220 near the Haw River, photo by StriderLooking South prior to Future US 220/I-73 partial interchange showing indications that crews are preparing to pave the highway.


Image of new bridge for Deboe Road under construction for future NC 68 interchange with I-73 in Rockingham County, from StriderPhotos Taken in June 2016:

Close look at new bridge being constructed to take traffic on Deboe Road over future I-73 roadway looking south.


Image of future I-73 NC 68 interchange as seen in distance from road paralleling US 220 North in Rockingham County, from StriderView in distance of construction progress at future I-73 interchange with NC 68.


Previous Photos taken by Strider, May 2016:

Image of US 220 North approaching future I-73 interchange, from StriderView from US 220 North approaching the future I-73 interchange with the NC 68-US 220 Connector, the future northbound on-ramp has not been completed.


Image of future I-73 lanes graded under US 220 South off-ramp bridge, by StriderView across current US 220 using future I-73 South off-ramp showing grading of future I-73 lanes to the south of the bridge.


Image looking south along US 220 toward future I-73/US 220 interchange, from StriderLooking south toward Haw River and progress in constructing the future I-73/US 220 South interchange beyond. Though the bridges over the Haw River are complete, much work remains in constructing the roadbed for I-73.


Image of US 220 North prior to NC 65 intersection showing I-73 construction progress, from StriderView along northbound US 220 just prior to current US 158 interchange showing progress in building new northbound lanes to the right.


Image of completed I-73 bridges over US 158, by StriderView looking along US 158 East toward completed Future I-73 bridges over US 158 and showing further construction needed to complete new US 158 westbound roadway.


Image of future southbound lanes for I-73 under construction along US 220, from StriderLooking north along US 220 north toward NC 65 exit showing still incomplete roadbed for future I-73 Southbound lanes.


Image of Future I-73 sign along US 220 beyond NC 65 exit, from StriderFuture I-73 sign recently put up between US 158 and NC 65 exits along US 220 North. Probably should be Future I-73 Corridor since similar signs appear on completed freeways.


Image of completed NC 65 bridge over US 220/Future I-73 North, from StriderView of completed NC 65 interchange bridge over US 220 and Future I-73 Northbound Lanes.


Image of clearing and construction for new NC 68 interchange on I-73, from StriderView on US 220 North approaching NC 68 intersection showing progress in building new interchange at northern end of I-73.


Image of construction for I-73 at current intersection of US 220 and NC 68, from StriderView of new lanes being added just north of current NC 68/US 220 intersection to accommodate new interchange.


Image of construction on future I-73 NC 68 interchange from access road along US 220 North, from StriderView looking south from access road parallel to US 220 North at progress in constructing new I-73 interchange with NC 68.


Photos taken by Strider, January 2015:

Image of I-73 construction as seen from US 220 North near Summerfield, NC Photo by StriderStarting on US 220 North, approaching the future interchange with I-73 near the Haw River, future NB lanes being paved, traffic shifting to new lanes in distance.


Image of new US 220 Bridge over Haw River at future I-73 interchange near Summerfield, 
NC. Photo by StriderLooking from a new frontage road being built along US 220 South, this is the completed US 220 South bridge over the Future I-73 that both directions of US 220 are currently using.


Image of future I-73 NB lanes under construction across the Haw River, photo by StriderView of completed future I-73 South bridge over the Haw River and future I-73 North lanes under construction, from future NB frontage road.


Image of closer view of I-73 construction across the Haw River near Summerfield, NC, 
photo by StriderCloser view of the future I-73 Northbound lanes under construction near the Haw River.


View of traffic on US 220 using completed future I-73 SB lanes near Summerfield, NC, 
Photo by StriderView heading north on US 220 showing traffic using the completed future I-73 Southbound lanes.


Image of future I-73 North lanes under construction near Summerfield, NC, photo by 
StriderUnique view looking forward and back of US 220 traffic about to cross future I-73 southbound bridge with future I-73 lanes under construction in the distance.


Image of travelling north on US 220 on future I-73 SB lanes approaching US 158, photo
by StriderHeading further north on US 220 using the future I-73 Southbound lanes approaching the US 158 interchange.


Image of I-73 construction along US 220 North approaching the US 158 interchange near 
Summerfield, NC, photo by StriderFurther north on US 220 near the US 158 interchange, the gas station to the right is currently cut off from US 220, but an access road is being built to connect it to the new parallel frontage road that ends just before the US 158 off-ramp.


Image of US 220 traffic using future I-73 SB bridge over US 158 near Summerfield, NC, 
photo by StriderUS 220 traffic crossing over US 158 on future I-73 Southbound bridge. The future northbound span is under construction after the original US 220 bridge was demolished.


Image of US 220 traffic now using future I-73 NB lanes north of the US 158 interchange 
near Summerfield, NC, Photo by StriderUS 220 traffic switches to use the future I-73 Northbound lanes after the US 158 interchange.


Image of traffic on US 220 North just south of future NC 65/I-73 interchange, photo by 
StriderApproaching the future NC 65 interchange on US 220 North. The off-ramp is paved but not open. The future NC 65 bridge under construction can be seen in the distance.


Turning around at the future NC 68 interchange and heading back south:

View of progress constructing I-73 on US 220 South just south of NC 68 intersection, 
photo by StriderNow heading south on US 220 here's the view of construction progress, slowed by design changes, just south of the NC 68 intersection.


Image approaching the future NC 65 bridge over I-73 on US 220 South, photo by StriderView of future NC 65 bridge under construction from US 220 South. The intersection is currently controlled by 2 traffic lights, the first just behind the photo and the second beyond the bridge and seen in the photo above.


Image of future southbound lanes for I-73 being graded between NC 65 and US 158, photo 
by StriderView along US 220 South between NC 65 and US 158 using future I-73 northbound lanes and future southbound lanes being graded.


Image of US 220 South at future I-73/US 158 interchange near Summerfield, NC, photo by
StriderUS 220 South at the US 158 interchange. The southbound ramp is complete and open to traffic, drivers wanting to access US 158 northbound must turn left and yield at the southbound ramp.


Image of US 220 South approaching the Haw River and completed  future I-73 bridges, 
near Summerfield, NC, photo by StriderUS 220 South descending toward the Haw River with the future I-73 South/US 220 interchange bridges in the distance.


Image of US 220 crossing the new I-73 US 220 exit ramp bridge over the Haw River, photo
by StriderCrossing the recently opened future I-73 South, US 220 off-ramp bridge over the Haw River temporarily carrying US 220 traffic.


Image of US 220 traffic crossing future US 220 South off-ramp bridge over I-73 near 
Summerfield, NC, photo by StriderView of US 220 traffic crossing newly opened future US 220 South bridge over the future I-73 (US 220-NC 68 Connector) freeway. Though work on the Connector has started, nothing has started at this end yet.


Previous Photos. A couple taken by Lyn Hay, Greensboro News Record on February 1, 2014:

Image of US 220 widening construction progress for I-73, Lyn 
Hay Greensboro News Record, 2/1/14US 220 traffic traveling through I-73 construction site north of Greensboro.


Image of progress widening US 220 to become I-73, Lyn Hay 
Greensboro News Record, 2/1/14 Progress on constructing future Haw River bridges for I-73.


Below are photos taken in December 2012 and April 2013 (Courtesy of Strider):

Photo of I-73 Bridge Construction near future interchange with US 220, courtesy 
of StriderThis photo shows construction progress on the future I-73 South bridge across the Haw River from US 220 North. (4/3/13)


Photo of I-73 Construction Clearing from US 220 North, courtesy of 
StriderThis photo shows progress clearing the path for I-73 from US 220 North across the Haw River from the future I-73 interchange. (4/3/13)


Photo from US 220 North showing I-73 Construction between future interchange 
with US 220 and US 158, courtesy of StriderThis photo shows progress clearing the future I-73 roadbed between the future US 220 interchange and US 158. (4/3/13)


Photo of I-73 Construction near interchange with US 158, courtesy of 
StriderThis photo shows progress clearing the future I-73 South road bed a mile south the US 158 interchange on US 220 North. (4/3/13)


Photo of I-73 Construction near US 220 North interchange with US 158, courtesy 
of StriderThis photo shows clearing the I-73 road bed approaching the current US 220 interchange with US 158. (4/3/13)


Photo of I-73 Construction near interchange of US 220 North and US 158, courtesy 
of StriderThis photo shows progress clearing areas near the future I-73 interchange for US 158 from US 220 North. (4/3/13)


Photo from US 220 South approaching Haw River and Construction of future 
interchange with I-73, courtesy of StriderThis photo shows the future I-73 freeway road bed from US 220 South approaching the location of the future bridge across the Haw River. (4/3/13)


Photo of I-73 Construction showing Future I-73 South Ramp from US 220 South, 
courtesy of StriderThis photo shows the future I-73 South ramp that will use the future bridge over the Haw River. (4/3/13)


Photo of US 220 Construction near future interchange with I-73, courtesy of 
StriderThis photo shows the future I-73 South road bed (the US 220 South ramp will go across this roadway via future bridge). (12/9/12)


Photo of Future I-73/US 220 Lanes north of Greensboro, Dec. 2012,
Courtesy of StriderView showing the proposed US 220/ I-73 bridges across the Haw River. The current US 220 will apparently become a part of frontage road once this construction is all done. US 220 will be moved on the new lanes (with I-73). (12/9/12)


Photo of future I-73 offramp for US 220, Dec. 2012, courtesy of StriderThis picture shows the visible future US 220 South ramp on the far right, where it will curve to the right, then left to across the future I-73 roadbed, then back to its current alignment. The construction on this section really sped up in the last couple months. (12/9/12)


Photo of US 220 construction progress north of Greensboro near US 158, 
Dec. 2012, courtesy of StriderThis photo was taken near the US 158 interchange. Not much is going on here except the blasting and dragging of the rocks to make a room for the roadbed. There are a few houses behind the construction trucks. What they will do about these houses once the road is open to traffic is unknown. (12/9/12)


Photo of US 220 widening construction near US 158 north of Greensboro, Dec. 
2012, courtesy of StriderProgress in clearing land near the future US 158 interchange. (12/9/12)


Photo of clearing work for US 220 widening project near US 158, Dec. 2012, 
Courtesy of StriderAnother view of progress in clearing the future roadbed near the US 158 interchange. (12/9/12)


Photo of progress clearing land for the US 220 Widening Project at Future 
US 158 interchange, Dec. 2012, Courtesy of StriderThis picture was taken at the US 158 interchange. Not much is going on there either, except clearing of the trees. (12/9/12)






.


Photos of segment before construction showing what US 220 looked like as of November 2009 (all photos courtesy of Bonnie Wilcox, except where noted).:

Photo of US 220 near the future location of the interchange with the 
NC 68 Connector, Nov. 2009This is looking at US 220 North, at the bottom of the hill is the Haw River. Somewhere between the green sign in the distance and the River is supposedly where the NC68-US 220 Connector will tie into US 220. North of there the road will be upgraded to a freeway with a 60 mph design speed.


Photo of the existing US 158/US 220 Interchange that is to be upgraded
during widening project, Nov. 2009The existing interchange for US 158, Stokesdale, Winston-Salem. The interchange will be rebuilt to accomodate a modern four lane interstate.


Photo of current intersection between US 220 and NC 65 to be upgraded to
and interchange, Nov. 2009Going north the next interchange will be with NC 65, Stokesdale, Reidsville. This is currently an at-grade intersection.


Photo of US 220/NC 68 intersection prior to widening construction, Nov. 2009This is the view of US 220 North approaching the NC 68 intersection. Going south, currently NC 68 continues straight as a 4-lane highway while US 220 traffic has to make a left turn across NC 68 traffic. This will initially be rebuilt so that US 220 (I-73) will be the primary roadway and there will be a signalized intersection to allow NC 68 North traffic to turn onto US 220. (2/09)


Other US 220 Widening

NCDOT also has another contract (R-2309) to widen US 220 south of the Connector to Horsepen Creek Road that is going on at the same time as the widening north of the Connector. This southern part will be constructed to expressway standards and have a 45 MPH speed limit. For a look at the highway section to be widened see photos below. Many area residents objected to this planned widening feeling that it is unnecessarily wide and costly, especially since the road already goes through several residential areas and crosses lakes that are currently part of Greensboro's water supply. An NCDOT spokesman insisted the widening is necessary because US 220 is one of North Carolina's Strategic Highway Corridors.10 The statement though is wrong, currently the corridor applies only to where US 220 is to become I-73. Since I-73 is not using this part of US 220, but rather the Connector (see a fuller discussion on the I-73 Segment 4 page) it seems likely that less traffic, and definitely fewer trucks, will use this part of US 220 than NCDOT's estimates show. Local citizens efforts to press NCDOT for a more reasonable solution seem not to have been successful.13

Photo of US 220 in area to be widened for I-73, Dec. 2009, courtesy of 
Bonnie WilcoxThe view of US 220 North at the current end of the widened 4-lane section. The rest of the route to the Connector is to be widened as well, if NCDOT does not change its mind in response to citizen concerns. As you can see in the distance, several new traffic signals have already been added to the highway.


Photo of US 220 in area to be widened not related to I-73, Dec. 2009, 
Courtesy of Bonnie WilcoxAnother view of the current US 220 North as it travels through the Cape Fear River Basin and over several lakes used as Greensboro's water supply.