Misc. Massachusetts Highway Photos
A. US 3 Sign Replacement, Burlington to Tyngsboro, 2021-2024 (UPDATED
7/30/24)
Signs along the
US 3/Northwest Expressway are being replaced under a contract started
back in 2021. Only in early 2024 have the overhead signs along the route
started to go up. As of late July all but 1 overhead sign had been
replaced, work still needed on ground-mounted signs, including most gore
signs and reassurance markers. The photos will be grouped by exit
heading north, with northbound exits shown first:
*Photos taken on
July 28, 2024:
EXIT 72 (SB) -
Interstate 95/Route 128
The overhead
signs were the first to be replaced on US 3 in February 2024:
All the new
signs, starting with the 2 Miles advance above are arrow-per-lane style.
The indicated the exit for I-95 South has one lane that is Exit Only
while those wanting to stay on US 3, should go straight. There were no
Route 128 shields or trailblazers in place with the new signs.
The 1 Mile
advance version of the APL sign. It might have been simpler to just give
the I-95 South ramp an exit number so US 3 does not exit off itself. But
MassDOT prefers to have both ramps with numbers.
Now the 1/2 Mile
advance APL. Other than a reduced speed, there is no indication that the
expressway actually ends after the I-95 South ramp.
The APL
approaching the I-95 (Route 128) South ramp. You can now see warning
signs in the distance regarding the need to exit at the I-95 North/US 3
South ramp. This is the last new sign.
EXIT 73 - Route
62
All the overhead
signs for this exit were replaced between May and July:
*The new 1 Mile
advance sign headed north.
*The new 1/2 Mile
advance sign.
*The new sign at
the exit itself, the gore sign had not been replaced. Turning around...
*The new 1 Mile
advance sign headed south, as with the previous sign it shares a gantry
with a VMS.
*The new 1/2 Mile
advance sign, all by itself.
*The exit sign,
with the first advance for the I-95 exits in the distance.
The overhead ramp
sign for US 3 North on MA 62 West in Burlington put up in late February.
EXIT 76 - Concord
Road
All the overhead
signs for this exit were replaced between May and July:
*The new 1 Mile
advance sign headed north.
*The new 1/2 Mile
advance sign by a noise wall.
*And the new exit
sign, again still with old gore sign. In the other direction...
*The new 1 Mile
advance sign headed south.
*Birds have
already found a new place to perch on the new 1/2 Mile advance sign.
Notice the Mile 77.6 marker to the right. The exit is at Mile 77, many
of the exit numbers seem to be 1 mile off where they should be.
*The new exit
sign headed south. Also no new gore sign, only partly visible in
distance.
*They also have
not replaced the reassurance markers yet south of I-495.
EXIT 78 - Treble
Cove Road
All the overhead
signs for this exit were replaced between May and July:
*The new 1 Mile
advance sign headed north, near an old North US 3 reassurance marker.
*The new 1/2 Mile
advance sign.
*The new exit
sign, but old gore sign.
*Closeup of the
old gore sign, with new exit number overlay. The staging area beyond the
ramp still has some new signs to be installed. Turning around...
*The new 1 Mile
advance sign headed south, behind a blue commuter services info sign.
*The new 1/2 Mile
advance sign.
*The new exit
sign with the old gore sign once again.
EXIT 79 - Route
129
All the overhead
signs, but the 1 Mile advance sign for this exit were replaced between
May and July. That sign is to be mounted on an existing I-495 sign
gantry, the other signs in this direction are in photos for I-495 below.
Turning around...
*The 1 Mile
advance headed south, just after the first on-ramp from I-495/Lowell
Connector.
*The 1/2 Mile
advance after the second on-ramp from I-495.
*The exit sign
and old gore sign for Route 129.
EXITS 80 / 81 A -
Lowell Connector / I-495 North (NB)
New advance signs
southbound were installed in early March, most signs northbound were put
up in April.
*The new 2 Miles
advance sign went up later in May or June. Notice the one remaining old
overhead sign for the Route 129 exit in the distance.
*The 1 mile
advance sign is paired with the 1/2 mile advance for the Route 129 exit.
*The 1/4 mile
advance sign before older diagrammatic that is not being replaced for
the I-495 South/Route 110 exit.
The diagrammatic
advance signs are not being replaced in this direction, but new signs at
the exit were installed in April, photo by Paul Schlichtman.
EXITS 81 B/C -
Interstate 495 South / Route 110
Along the C/D
ramp northbound:
The new signs
were put up along the C/D ramp in April.
The new 2-sign
cantilever at the I-495 South exit on the C/D ramp.
The new exit sign
for the MA 110 exit at the end of the C/D ramp.
EXITS 81 C-B-A
(SB) Route 110 / Interstate 495
The only new
signs placed so far for the I-495 and Route 110 exits are the 2 Miles
advance diagrammatic, above and the similar 1 Mile advance sign.
The 1 Mile
advance diagrammatic. Followed by...
The new 1/2 Mile
advance sign, put up in April. Many states, encourage by the new federal
MUTCD, are phasing out these type of signs, but apparently MassDOT still
likes them. Signage in the C/D lane heading south was replaced after May
5.
*The first C/D
ramp sign for the Route 110 exit.
*The overhead
signs at the I-495 South exit.
*The last C/D
ramp sign for the I-495 North exit.
Additional new
signage:
The new auxiliary
sign for the Lowell Connector southbound prior to the I-495/Route 110
C/D lanes.
EXIT 84 - Route 4
All the overhead
signs had been placed by early May.
The new overhead
signs for the MA 4 exit were put up in April, the new signs also include
information about Drum Hill Road. The 1 Mile advance.
The 1/2 Mile
advance.
The exit ramp
includes an exit only lane, in both directions.
The only new sign
for this exit is the gore sign. Noted by its lack of yellow Old Exit
sign underneath. Turning around...
The new 1 Mile
advance headed south.
The new 1/2 Mile
advance. The auxiliary sign for UMass Lowell is old, has an overlay for
the new milepost exit number.
The new exit sign
also with an exit only lane, useful for the Drum Hill Road Rotary at the
end of the ramp.
EXIT 86 -
Route 40
All but the exit
signs had been placed by early May. Those were put up between May and
July.
The new 1 Mile
advance sign for the Route 40 exit headed north.
The new 1/2 Mile
advance sits behind the recently placed new North US 3 reassurance
marker seen before.
*The later
installed exit sign, notice it is at milepost 87. Turning around...
The 1 Mile
advance sign for the Route 40 exit headed south.
The new 1/2 Mile
advance sign, the old exit sign can be seen in the distance.
*The new exit
sign put up during the summer.
*The new gore
sign for the Route 40 exit.
The view of one
of the project staging areas along US 3 North in Westford. Still looked
like a lot more gantries needed to be put up in May.
*The same view in
July, a few signs and gantries still remain to be installed.
EXIT 88 -
Westford Road
All the overhead
signs were up for this exit as of early May.
The new 1 Mile
advance sign for the Westford Road exit headed north, just over the town
line.
The 1/2 Mile
advance sign for Westford Road put up in March.
The new exit sign
for Westford Road, the gore sign has not been changed, still having an
Old Exit number plaque. Turning around...
New image of 1
Mile advance sign on US 3 South in early March. The other new signs in
this direction were put up in April.
The new 1/2 Mile
advance sign for the Route 40 exit headed north.
The new exit sign
for the Westford Road headed south. The gore sign here appears to be
new.
Other signage:
The new Entering
Westford sign after the Westford Road exit.
EXIT 90 - Route
113
Most of the
advance signs were put up by May, the others by July.
*One of the last
new signs to be put up north of I-495, the 1 Mile advance for Route 113.
Again, based on the mile marker the exit number should be 91, not 90.
The 1 Mile
advance sign for the Route 113 exit in Tyngboro(ugh). This was the first
sign for the exit put up in this direction.
The new auxiliary
sign for the Park and Ride lot at the Route 113 exit.
The new overhead
sign at the Route 113 exit also includes the 1 Mile advance for the last
Massachusetts exit.
The new gore sign
for the Route 113 exit. Turning around....
*One of the two
signs put up during the summer in this direction, the 1 Mile advance for
Route 113.
The 1/2 Mile
advance sign on US 3 South. This was still the only new sign for this
exit in this direction as of early May.
*The exit sign
for Route 113, also put up in June or July.
Other Signs:
*The first new
sign put up in this direction, crossing the border from New Hampshire.
EXIT 91 -
Middlesex Road (NB)
All signs were up
for this exit as of early May.
The new 1/2 Mile
advance sign for the Middlesex Road exit now includes a reference to the
Daniel Webster Highway which the road becomes after crossing the border.
There is also a 1 Mile advance sign for the first New Hampshire exit
which previously had no advance signs in Massachusetts.
The new overhead
signs at the Middlesex Road/D.W. Highway ramp also include a 1/2 Mile
advance for the first New Hampshire exit and a pull through for US 3
North with a Everett Turnpike logo.
*The gantry of
the US 3 on-ramp from Middlesex Road now has its US 3 South ramp sign.
The older gantry that was placed earlier along the ramp had been taken
down.
The new gantry on
the ramp from Middlesex Road was missing the US 3 South sign in March.
The old sign gantry at the beginning of the ramp had not yet been taken
down.
And Most
Importantly...The new Speed Limit 65 Signs put up the week of July 22:
*The first new
sign on US 3 North in Burlington.
*The second to
last new sign on US 3 South in Burlington after the Concord Road exit.
B. I-295 Sign Replacement,
Attleboro, 2023-2024
Signs were
replaced along the 4 mile segment of I-295 in Massachusetts during a
project that took place in 2023 and 2024. This project began on April
13, 2023 and since it only replaced the signage, not the supports, and
being only 2 exits, was nearly completed by May 2024. Signs, by exit
heading north from the Rhode Island border, all photos taken on April
29, 2024:
EXITS 2 A/B
The 1 Mile
advance overhead for the US 1 exit heading north. Because the support
post was not replaced, the Old Exits 1 A-B sign was not removed, though
it's been 2 years since the exit renumbering.
The 1/2 Mile
advance overhead for the US 1 South exit.
The overheads at
the US 1 South exit. It doesn't appear the gore sign has been replaced
since the Old Exits 1 A-B plaque is still attached.
The exit sign for
US 1 North.The gore sign here appears new, since there is no Old Exit
plaque. The sign shares the gantry with the first I-95 exits advance
sign, more on that later. Turning around for some signs heading south:
The 1 Mile
advance overhead for the US 1 exits. The Old Exits 1 A-B sign was not
removed here either.
The 1/2 Mile
advance in this direction is for the US 1 North exit.
The overhead
signs at the US 1 North exit. Again the gore sign for this exit does not
appear new since there is the Old Exit plaque.
A closeup of the
US 1 South exit sign and the apparent new gore sign behind it.
The reassurance
markers, if they are to be replaced, had not been as of late April, this
shield has been here, based on Google Maps Street View, since at least
2012.
There was a new
I-295 Ends (in) 1 1/4 Miles sign after the US 1 North on-ramp. If the
sign is correct I-295 then is 3.65 miles long in Massachusetts.
EXITS 4 A/B
The replacement
of the 1 Mile advance diagrammatic overhead for the I-95 exits. Largely
the same as the old sign, these sign types are losing popularity around
the country (and are not recommended by federal sign guidelines), but
apparently not in Massachusetts.
The new 1/2 Mile
advance diagrammatic. All the ground mounted yellow freeway end warning
signs appeared to be new.
The 1/4 Mile
advance overheads with yellow Exit Only tabs at the bottom.
The overheads at
the split of ramps for I-95 North and South. It appears the sign
replacement project has not yet restored the I-295 shields to the End
I-295 signs, these have been missing since at least 2016.
A pair of new
gore signs at the I-95 South ramp. Work has begun on a southbound ramp
rehab project that will close one lane of I-95 South for several months
starting in late May.
The new version
of the ramp curve 25 MPH warning sign. This sign is rarely seen on
interstates, though, because of canceled freeway projects in
Massachusetts, this is one of two seen along the I-95 corridor south of
Boston.
C. US 1 Sign Replacement, Chelsea
to Danvers, 2020-2024
Signs along US 1
between Chelsea and Danvers are being replaced under a rather slow sign
replacement project that began in January 2020 and was still not
complete as of May 2024. The project included replacing overhead and
ground mounted signs and their supports along US 1 and its intersecting
roadways. This included both most of Northeast Expressway north of the
Tobin Bridge and the six-lane roadway between the Expressway and I-95 in
Danvers, including the interchange with I-95 and Route 128 in Peabody.
The project was listed by MassDOT as being over 90% complete in early
May. Photos here are displayed in reverse chronological order, latest
first.
NEW - Sign photos
on US 1 North taken May 5, 2024:
Advance signage
for the Route 16 East and Webster Avenue exits after the Chelsea curves
put up earlier in the year.
1/4 Mile advance
signage for the Lynn Street exit at the end of the Northeast Expressway
also put up earlier.
New overhead
signage at the first Lynn Street exit as US 1 North is about to enter
Malden.
New overhead
signage for the second Lynn Street exit currently with 2 advisory Speed
Limit 20 MPH signs.
A 2 advance sign
cantilever for each of the Essex Street 'exits' just across the Saugus
line put up earlier this year.
New and old
signage at the Main Street exit still are both up as they were earlier
in the year, along with an old gore sign for the first Main Street exit.
A left-side 1
Mile advance sign for I-95 North also put up earlier.
Another left-side
1 Mile advance sign, this for the I-95 South and Route 128 (I-95 North)
exit also from earlier in the year.
A closer look at
the recently placed ground mounted guide signs at the turnaround after
the first I-95 ramp.
Overhead sign at
the split of the US 1 North and I-95 North ramps put up in early 2024.
It appears most
of the new signage has been put up on US 1 North between the I-95 exits
in Peabody and Danvers:
The first in a
series of left-side overhead signs for ramps along US 1 North, here for
Peabody Street.
The Mass. guide
or paddle sign at Lowell Street ramp itself.
The left-side 3/4
Mile advance sign for the Route 114 exits.
A new auxiliary
sign along the left lane for Route 114 East.
Overhead signs
for the Centre Street and Route 114 exits after crossing the Danvers
line.
The new overhead
signs at the East Route 114 exit.
Another left-hand
side overhead for a right-side exit for Route 114 West in Danvers.
New left-side 2
sign cantilever 1/2 and 1/4 Mile advance signs for the Centre Street and
Popes Lane 'exits'.
The 1 Mile
advance sign for the Route 62 exits along with the exit sign for the
Centre Street.
The recently
placed 1/2 Mile advance sign for the Route 62 East exit.
Overhead signs at
the ramp for Route 62 East.
Overhead signs at
the Route 62 West exit feature a Left Exit tabbed 3/4 Mile advance sign
for the next I-95 North exit.
The new 1000 Feet
advance sign for the left I-95 North ramp.
The gantry at the
I-95 North ramp features at North US 1 pull through sign.
Approaching the
ramp taking you back to US 1 South and the I-95 South exit.
The new
diagrammatic overhead 1000 Feet advance sign for the I-95 South ramp on
US 1 South.
The signs at the
I-95 South ramp, and US 1 South pull through sign, the other signs on US
1 South will be documents on the next trip.
New Signs along
US 1 South from Lynnfield to Chelsea, taken on March 3, 2024:
Not a new sign,
but a better image of the Route 129 West/Walnut Street guide signs in
Lynnfield at Mile Marker 58.
The guide sign is
not new, but the overhead for the second Walnut Street ramp is. Notice
the first guide sign does not have a reference to Route 129 West, unlike
in the photo above.
The gantry here
is not new, put up with a new VMS a few years ago, but the 1 Mile
advance for Main Street may be. The VMS is warning drivers of the first
Sumner Tunnel closure of the year.
The first Main
Street sign is not new, but the ones in the distance are, replacing
bridge mounted versions.
A closeup of the
new pair of signs at the second Main Street ramp that includes a 1/2
mile advance for Essex Street (shouldn't this say 'Exits'?), also a
portable VMS with a Sumner Tunnel Closed message.
The new second
Main Street 'exit' gore sign currently paired with the older paddle gore
sign version, plus 2 Ramp speed advisories. The signs in the distance
have not been replaced.
The first Essex
Street exit sign and gore sign in the distance, again the next pair of
signs are still the old bridge mounted versions.
The only Route 99
exit sign to be replaced so far, this 2 sign cantilever at the exit
ramp, notice how long the gantry is extended but still can't quite reach
entirely over the exit ramp.
The new 1 Mile
advance for the Lynn Street exits after the Route 99 exit.
A pair of new
advance signs for both Route 60 and Lynn Street, if these were to have
numbers the milepost suggests they would be 53 and 54 A/B.
The overhead
auxiliary sign for the Route 60 exit. Those heading to Logan this day
hopefully know the Sumner Tunnel is closed for on the way back.
The advance
distance for the new second Lynn Street exit is 700 Feet.
The new sign
indicating (or is it warning?) drivers are about to enter Revere.
The Route 60 exit
sign has been there a few months, but the old overhead sign behind it
has now been taken down.
One of the new
South US 1 reassurance markers on the Northeast Expressway.
The rest of the
signs were replaced in the fall and can be found among the photos below.
Sign Photos along
US 1 North taken by Jay Hogan in February 2024:
The exit sign for
Webster Avenue at mile marker 51 put up last summer.
Closeup of the
Route 16 East 1000 Feet advance sign also put up last summer.
The new overhead
Route 16 East exit and gore signs.
New advance
signage for the Route 60 and Sargent Street exits, also replacing bridge
mounted signage.
New overhead
signage at the ramp Sargent Street in Revere.
New signage at
the Route 60 exit which includes and advance for the Lynn Street exits
at the end of the Northeast Expressway.
While it appears
that all signage has been replaced along the Northeast Expressway
portion of US 1, the same cannot be said for the section between Route
60 and I-95/Route 128, there are still several signs needing
replacement, or here, at the second Lynn Street exit, only the
cantilever assembly had been put up.
The new 1 Mile
advance for the Essex Street exits at the start of the non-freeway
section of US 1 in Malden.
Close up of exit
signage for Essex Street, old bridge mounted signs beyond still in
place.
New overhead
signage at the Main Street exit in front of older bridge mounted signage
on US 1 North in Saugus.
Close up of new
advance signage for closely spaced off-ramps approaching Walnut Street.
New overhead sign
for the Route 129 West ramp supported by longer standing West Route 129
trailblazer.
New overhead
advance sign for the Route 129 East ramp with an Exit Only lane banner.
A closeup of the
overhead advance signage approaching the Route 129 East ramp in
Lynnfield.
A closeup of the
previously placed advance signage for the I-95 and Route 128 exits.
A ground mounted
guide sign for the I-95 South/(I-95/) Route 128 North ramp for traffic
entering from the Route 129 West ramp.
Another left lane
overhead 2 sign cantilever with the 1/2 Mile advance for the I-95 North
ramp heading towards Danvers.
NEW SIGNS
SOUTHBOUND, TAKEN ON NOVEMBER 5, 2023:
The overhead sign
at the intersection with Route 129 East/Salem Street on the ramp to US 1
South from I-95/Route 128 North in Lynnfield.
The next new
overhead sign southbound is the 1 Mile advance for the Route 129
West/Walnut Street exit. The first of several overhead signs placed in
the median supporting signs in both directions.
The 1/2 mile sign
for Route 129 West/Walnut Street is a ground mounted guide sign at Mile
Marker 58.
The exit/guide
sign for the Walnut Street exit.
The 1/4 mile
advance sign for the Lynn Fells Parkway exit. Another median placed
overhead sign.
The ground
mounted exit sign for the Lynn Fells Parkway just before Kelly's Roast
Beef in Saugus. The bridge mounted signs in the distance have not been
replaced.
The new 1/4 mile
advance sign for the Main Street exit sits behind the old overhead
gantry southbound.
A rare right side
mounted sign for both the Main Street exit and the 1/2 mile advance sign
for the Essex Street exit.
A small 1/4 mile
advance ground mounted sign for the Route 99 exit with a new South US 1
reassurance marker beyond.
The new overhead
signs, more left side placed at the Route 99 South exit, the original
alignment for US 1 South.
Two types of
signs for the Lynn Street exit. A ground mounted advance and overhead
exit sign in the distance.
The new exit sign
for the Route 60 exit stands in front of the old sign, while the old is
in front of the exit sign in the northbound direction.
The new 1 mile
advance sign for the Route 16 exit after the start of the Northeast
Expressway. It was decided not to place new milepost exit numbers
adopted in Massachusetts in 2020 along the expressway due to its short
distance, this could be Exit 51.
The new 1/2 mile
advance sign for the Route 16 exit.
The new exit sign
for the Route 16 exit comes along with a Speed Limit 45 sign.
The last new sign
is the 3/4 Mile advance sign for the Carter Street exit in Chelsea, this
could be Exit 50. The rest of the signs to the Tobin Bridge were
replaced when tolls became electronic in the late 2010s.
New Signs Seen
Heading Northbound, 9/10/23
The new overhead
exit sign for the Webster Avenue exit. Other signs for this exit has not
been replaced at this time.
The one new
overhead advance sign for the Route 16 exit has the distance in feet,
1000 feet.
A new gantry
awaits the overhead exit sign for the Route 16 exit. The gore sign is
new, as is the Entering Revere sign seen in the distance.
One of the new
North US 1 reassurance marker along the Northeast Expressway.
A support post
for the future 1 Mile advance sign for the Sargent Street exit stands
before the existing sign that also had the old Route 16 exit sign in the
other direction.
One of the new
supports for the future Route 16 1/2 mile advance sign can be seen in
the other direction. Signs for the Route 60 and Sargent Street exits had
not been replaced.
The new support
post for future Route 60 and Sargent Street exits heading northbound.
The new
cantilever 1/4 Mile advance sign for the Lynn Street exit sits behind
the old overhead sign at the end of the Northeast Expressway.
The new Entering
Saugus sign approaching Route 99 heading north.
The new overhead
exit sign for the Essex Street exit. The other bridge mounted signs had
not been replaced.
The new median
3/4 Mile advance sign for the Lynn Fells Parkway exit with the old sign
gantry behind.
The new two-sign
cantilever at the Lynn Fells Parkway exit, with 1/2 Mile advance sign
for the Route 129 (West)/Walnut Street exit.
The new median
cantilever with 3/4 Mile advance sign for the Route 129 East exit.
The new 1/4 Mile
advance sign for the I-95 South/Route 128 North exit with a Mile 60
marker behind.
The last new sign
northbound for the I-95 South/Route 128 North and I-95 North exits as of
the fall of 2023.
D. Kilby Street intersection Safety
Improvements, Fall 2021 to Spring 2022
The intersection
of Kilby Street with Chief Justice Cushing Highway (Route 3A) in Hingham
has been the scene of many bad accidents over the years involving cross
traffic. Once guarded by traffic signals, first placed in the late 1950s
with the rerouting of then Route 128 from East Street to Kilby then
along Route 3A South back to East Street, restored to its original
alignment in 1970, was, in the 1980s, replaced with flashing red (Kilby)
and yellow (3A) lights. Years of study resulted in the town and state
finally agreeing to modify the intersection to improve safety by
preventing traffic on Kilby from crossing Route 3A. The plan was to
create two right turn only intersections with a flexi-post barrier down
the middle of 3A. Traffic wanting to access East Street/Route 228 could
use the signalized Summer Street intersection nearby. Here's the final
plan, however, the proposed flexi-posts seen here were never installed:
Work started in
September 2021. Here are photos documenting progress in construction
which is supposed to be completed by the end of November, latest photos
first.
Latest Photos,
taken 11/30/21:
Permanent signage
was installed in the two traffic islands the week before Thanksgiving,
including reflectors facing oncoming traffic.
The newly paved
sidewalk along Route 3A South heading for the location of the new
crosswalk, which will be painted once the final layer of pavement is put
down, this though may have to wait until spring. The installation of the
planned flexi-post barrier down the middle of the roadway has to wait
until the final paving.
Looking across
Route 3A at the new sidewalk along the northbound lane, this currently
leads to nothing since painting the new crosswalk also has to wait until
the final paving is completed.
Earlier Photos
Taken 11/13/21:
New pedestrian
crossing signals set up at site of future crosswalk to the north of the
intersection.
Traffic islands
on both sides for Route 3A have been filled in with concrete. This
design will allow emergency vehicles to cross over them, but hopefully
dissuade other types from doing the same.
The future
sidewalks on both sides of the intersection await paving.
Looking across to
the Kilby Street at Route 3A North intersection showing barrels and
cones still around the new traffic island and temporary No Turn signage,
a police car was on Kilby Street in the other direction in case drivers
thought of ignoring the new no turn rules.
Taken 11/4/21:
Newly installed
Right Turn Only Sign approaching Route 3A headed east on Kilby Street.
Closer look at
landscaped corner of Kilby Street and Route 3A and temporary No Turn
signs on new traffic island, being ignored by many vehicles, including
SUV seen heading up Kilby.
Closer look at
new traffic island at the intersection of Route 3A South and Kilby
Street.
Looking along
Route 3A headed south on Kilby Street showing sidewalk construction for
new crosswalk, also temporary No Left Turn sign.
Taken October 11,
2021:
Curbing has been
placed around reconstructed corners of Kilby Street's intersection with
Route 3A South.
Curbing being
placed along Route 3A North as well and grading being done for new
sidewalk.
Site of future
sidewalk to new crosswalk to the north of Kilby Street.
Taken on
September 11/18, 2021:
Only initial work
had started on project allowing photos of what the intersection looked
like before reconstruction, here looking south across Kilby Street east
of Route 3A.
On the western
side of the intersection, the start of reconstructing the corners for
right turns only.
Looking east
across the intersection at traffic barrels and cones in place in the new
work zone.
Equipment stored
at the northwestern side of the intersection, for construction of future
sidewalk and new crosswalk.
A closer look at
dug out northwest corner with old flashing yellow signal still remaining
in the work zone.
E. Derby Street Reconstruction in
Hingham (2018-2021)
This project,
constructed under 2 different contracts between the fall of 2018 and
spring of 2021, rebuilt Derby Street between the Route 53 (Whiting
Street) intersection and the Route 3 interchange. As part of the project
the road was widened to add bicycle lanes, new traffic signals were put
up at the Route 3 ramps and at the intersection with Old Derby Street,
which was revised to add left turn lanes and that the road met Derby
Street at the same point. The intersection with Route 53 was also
redesigned so there is now also a dedicated left turn lane onto Route 53
North and Gardner Street. Work started on the Cushing Street to Route 3
portion in 2018 while the remainder from Cushing Street to Route 53 was
started in the spring of 2019. Work was completed west of Cushing Street
in the summer of 2020. While work on the Whiting/Gardner Street
intersection continued until May 2021 mainly due to slow progress in
removing remaining utility poles from widened right-of way in
2020. In October 2020 the contractor had to wait until the
received an Extra Work Order to proceed. Work then restarted in late
October and the supports for the new traffic signals were put up in
early December. The remainder of work, however, waited until the weather
warmed up in late March and April 2021 with the first project of
updating the signage. The final acts of repaving the road, redoing the
lane markings and revising the traffic signals occurred in May, with
completion just before the Memorial Day weekend. The project was
completed in late July with the addition of new guide signs at the Derby
and Whiting Street intersection. Here are photos taken in the 2
construction areas, latest photos first:
Latest photo
taken on July 31 and August 3, 2021:
The first of two
new style MassDOT guide signs on Derby Street approaching Whiting
Street. This one replaced a Route 53 South guide sign, and includes both
directions and a reference to Route 228. The destination in for 53 South
is Hanover, though the auxiliary sign on Route 3 lists Norwell.
The second of the
two new guide signs on Derby Street heading east. This one replaces the
previously erroneous South Route 53/228 sign. A 228 shield remains but
this time accurately accompanied by a 'To' label.
The new guide
sign on Whiting Street heading north. This one basically replaces the
previously one but has a Route 3 shield. The additional one approaching
the intersection has not been replaced, at least at this time.
A more
traditional new 'paddle' guide sign was also placed at the intersection
of Gardner and Whiting Street positioned to be seen from traffic
entering the intersection headed east on Gardner Street, guess they
assume they can figure out Route 53 South goes the other direction.
Taken earlier on
June 18, 2021:
This final photo
shows the painted bike lane heading from Whiting Street/Route 53 North
onto Derby Street and installed North Route 53 reassurance marker beyond
the intersection.
Taken on May 27,
2021:
The final
pavement and lane striping on Derby Street headed east just beyond
Cushing Street.
The final lane
striping includes a dedicated left-turn lane for Recreation Park Road as
seen on Derby Street headed east.
The beginning of
the new dedicated left-turn lane for traffic headed for Whiting Street
(Route 53) North and Gardner Street east.
The new traffic
signal at the new left-turn lane for traffic headed for Whiting Street
(Route 53) North and Gardner Street east.
Taken on April
4-11, 2021:
New signage
placed in early April include a Right Lane Turn only sign (and
corresponding Bike Lane sign), and more importantly, a To Route 3
trailblazer to replace the former erroneous Route 228 North one,
matching the information on the guide signs.
Along with new
signs, a new median was being placed on Whiting Street and at the end of
Derby Street.
Construction
barrels have reappeared along Derby Street approaching Whiting Street,
along with new signage.
Among the new
signage, a hint of things to come, a Left Turn Only lane sign.
New median being
placed at the end of Derby Street, however existing paddle/guide sign
has not been replaced.
New Gardner
Street signs have also been placed at the end of Derby Street, plus a
new South Route 53 reassurance marker beyond, hidden in photo by
telephone pole with older sign on it.
The new To Route
3 trailblazer southbound at the Derby Street intersection has already
been partially bent. (New South Route 53 reassurance marker referred to
above can be seen in the distance across the intersection).
The new To Route
3 trailblazer heading west on Derby Street. (End of new median can be
seen on the left). The new sign was knocked down in May and reposted,
but the Route 3 shield remained bent until late July.
Taken December
13, 2020:
Looking north
along Whiting Street (Route 53) toward the Derby Street intersection
after the new traffic signal supports were put in on either side of the
roadway.
Earlier Photos
Taken December 6,
2020:
The rest of the
sidewalk along the southbound lanes of Whiting Street, Route 53, were
installed in late November.
Taken November 8,
2020:
One of two new
foundations placed for future traffic signals at corner of Whting (Route
53) and Gardner Streets.
Taken September
27, 2020:
View along
Whiting Street, Route 53 South, after the Derby/Gardner Streets
intersection showing recent removal of last utility poles in widened
roadway.
A closer view of
the area now cleared of the last utility pole which will allow final
paving and the completion of the sidewalk.
Looking at the
cleared southbound lanes of Route 53 heading north toward Derby Street.
Earlier Photos,
taken August 18, 2020:
One utility pole
remains, along with guide sign in widened Derby Street right-of-way
approaching the Gardner Street/Whiting Street (Route 53) intersection.
Two of the
remaining utility poles along Route 53 South were removed in early
August, the South 53 reassurance marker was moved to one of the new
poles with no more gap where a Route 228 shield was taken down.
This last old
pole headed south still remains and its removal is preventing the
completion of the sidewalk and final paving of the widened
Derby/Gardner/Whiting Streets intersection.
Earlier Photos
taken on August 2, 2020:
Looking east
after Cushing Street. The remaining utility poles in the widened Derby
Street right-of-way were removed in late July.
Equipment and
traffic barrels still remain in widened eastbound Derby Street roadway
approaching Whiting Street (Route 53).
Looking at the
intersection of Derby Street with Whiting (Route 53) and Gardner Street
shows little progress in removing remaining utility poles and building
new sidewalk (or removing outdated guide sign).
Photos taken on
July 11, 2020:
Looking east on
Derby Street at widened roadway still awaiting removal of utility poles
before final reconstruction can begin.
Two remaining
utility poles straddle both sides of Derby Street approaching Whiting
Street (Route 53)/Gardner Street intersection along with construction
equipment.
Curbing and
grading still not completed heading east approaching the Whiting Street
(Route 53) and Gardner Street intersection. Note guide sign also in
widened roadway and will need to be removed (or better replaced with one
with only Route 53 shield).
View along
Whiting Street, Route 53 heading north relatively unchanged since June
except for the removal of the long-standing North Route 228 trailblazer.
Photos taken
between May 20 and and June 1, 2020:
Not much progress
seen in moving utility poles from photograph taken a week before.
More curbing has
been placed along right side of Derby Street just prior to Whiting
Street intersection, also new traffic and pedestrian signals have been
placed upon supports seen in photos below.
Closer look at
widened Whiting Street (Route 53) waiting for utility poles to be
removed to allow for final paving.
Work still
remains to complete sidewalk along Route 53 after the intersection, and
the removal of utility poles.
Looking across
Whiting Street from Gardner Street showing construction of sidewalks
continuing and installation of new pedestrian signals.
Looking east in
vicinity of Recreation Road showing much work still needed along south
side of Derby Street (and utility poles still need to be moved on left).
Sidewalk work
continues along the south side of the road approaching Whiting
Street/Route 53.
Work also
continues on sidewalk on other side of Gardner Street intersection with
utility pole removal needed here also.
Looking west now
along Derby Street headed toward Cushing Street, showing need to remove
remaining utility poles now in highway right-of-way.
Earlier Photos
Photo taken on
March 15, 2020:
Photo shows
resumption of work at Derby/Whiting and Gardner Streets intersection
after the winter hiatus. Utility workers (out of frame to the left) are
moving utility pole wires from the old to new poles. Work was halted
again in early April.
Earlier Photos
taken December 8, 2019:
Traffic is backed
up from activated traffic lights (beyond new traffic signals ahead
advisory sign) at the end of the ramp to Derby Street from Route 3
South. There is a 'No Turn on Red' sign at the end of the ramp
preventing traffic proceeding, like it used to, when there was no
traffic coming.
The activated red
light at the end of the ramp for traffic heading left onto Derby Street.
Traffic on Sunday
morning backed up on ramp from Route 3 South due to 'No Turn on Red'
sign on pole to new activated traffic signal.
The new lane
alignment on the Benjamin Lincoln Bridge carrying Derby Street traffic
over Route 3 is 2 lanes eastbound and one westbound, the bridge, only
rebuilt several years ago, was not widened.
The final lane
configuration between Route 3 and Old Derby Street provides 2 through
lanes in both directions, 2 left turn lanes eastbound and 1 westbound
and 1 right turn only lane in each direction.
A look at the
completed realigned intersection with Old Derby Street headed east on
Derby Street including striping for new bike lane across the
intersection.
Traffic backed
up from existing signals at entrance to Derby Street Shoppes.
Earlier photos
from November 2019:
Newly activated
traffic signals the Monday before Thanksgiving, notice the new lane ends
sign after the westbound on-ramp.
The newly
activated green traffic signal, traffic backed up due to continued ramp
construction on other side of bridge.
A little more
than 2 weeks earlier:
Temporary lane
striping placed on final paved section of Derby Street headed west prior
to Old Derby Street intersection, traffic signals still on flash mode.
New Junction
Route 3 trailblazer in front of flashing traffic signals. The sign is
after the guide signs for Route 3 North (see photos below), disregard
the October date.
A few days
earlier:
Final paving has
started at the ramps to Route 3 South, heading west on Derby Street.
Final paving
proceeding on the Benjamin Lincoln bridge, traffic in both directions
using westbound lanes during the work.
Traffic signals
still on flash mode at Route 3 North off-ramp during final paving
operations.
View of eastbound
signage at Route 3 North ramp from westbound lanes carrying two-way
traffic during final paving operations.
Earlier Photos
from October 2019
Traffic signals
at end of ramp from Route 3 South now activated on flash mode while
signals for ramp to eastbound Derby Street are yet to be installed.
Closeup of new
guide signs at split of ramp from Route 3 South, sign behind reflector
is for Industrial Park.
While initial
final paving has taken place on Derby Street, no pavement yet on
Benjamin Lincoln Bridge nor lane markings for 2 eastbound travel lanes.
New traffic
signals at the Route 3 North ramps also in flash mode, with left turn
lane striped for on-ramp.
1 day earlier...
The new
traffic signals at Derby Street in flash mode (photographed when off)
heading toward the Route 3 North ramps.
The new signals
at the Route 3 North off-ramp caught in the act of flashing yellow.
About a week
earlier...
View of Derby
Street heading east after Cushing Street showing installation of new
sidewalk along south side of road.
Cisterns and
other construction equipment stored on south side of widened Derby
Street between existing road and new sidewalk approaching the Route
53/Whiting Street intersection.
More work is
needed at Derby and Whiting/Gardner intersection before new sidewalk can
be built. Notice that the removed guide sign at the intersection has
been restored.
Heading north on
Route 53 approaching the Derby and Gardner Street intersection, the
widened portion has been given an initial paving by Dunkin' Donuts.
Earlier Photos
from September 2019:
Temporary lane
markings placed before final paving begins on Derby Street at Route 3
South ramps in late September.
Preliminary
paving stops at beginning of Benjamin Lincoln bridge over Route 3,
bridge lane markings do not match surrounding road's.
Some paving has
started along the shoulders after the placement of new guardrails just
east of Benjamin Lincoln Bridge.
Preliminary
paving of lines leading to Old Derby Street has 1 designated left-turn
lane eastbound (it will be 2 in the final configuration).
New traffic
signal heads turned to the right prior to activation with wire placement
in road prior to Old Derby Street completed.
Drain grate frame
still rises above existing pavement between entrances to the Derby
Street Shoppes (Road Work Ahead sign is for next project after Cushing
Street).
Beyond the Derby
Street intersection with Gardner and Whiting Streets, the erroneous
South Route 228 reassurance marker has been restored, this time nailed
to a to be removed later telephone pole.
A week earlier on
September 21/22:
Looking east on
Derby Street after Cushing Street showing completion of new sidewalk
construction.
Stacks of curbing
remain for new sidewalk closer to the Whiting Street (MA 53)/Gardner
Street intersection.
New sidewalk work
had not yet reaching the Whiting/Gardner Street intersection. Back of
erroneous South Route 228 reassurance marker can be seen, this was taken
down in December.
At the
intersection with Whiting Street (Route 53) and Gardner Street, sidewalk
after Gardner Street has been removed along with South Route 53/228
reassurance marker that would be put back up a week later.
Closeup view of
lane widening construction after the Derby Street intersection, future
part of Route 53/Whiting Street has been graded, route signs removed.
Looking west on
Derby Street just past Cushing Street showing paved lanes being marked
up for final pavement work.
Similar scene
further west toward the Derby Street Shoppes entrance.
Temporary single
dedicated left turn lane for Old Derby Street marked up prior to final
paving headed west toward North Route 3 ramps.
Work continuing
at site of new traffic signals, not yet activated on flash mode at
off-ramp from Route 3 North.
Problem area at
Benjamin Lincoln bridge for westbound Derby Street traffic, new markings
for center lane, but old shoulder fog line has not been moved creating
potential traffic problem.
More markings on
pavement prior to the final paving of Derby Street at the new dedicated
left-turn lane for the South Route 3 ramp.
Next up. Photos
from two weeks earlier, on September 8....
F. Installation of Real Time
Traffic Management System 'Go Time' Signs (2014-2016)[* New photos for
I-195, 11/8/20] Skip to MA 3
or MA 24].
MassDOT announced
on January 18, 2017 that the contract to place 146 permanent Real Time
Traffic signs along the state's highways had been completed and all
signs activated. These permanent signs went up under a statewide
contract that was started in November 2015. The first of these signs
were put up along US 6 on Cape Cod and Route 25 in the spring of 2014 as
a trial project. The first signs north of the Cape to be activated were
Route 128 between Danvers and Gloucester in the Spring of 2016
Signs on I-90, I-91, I-93, I-95, I-195, I-290, I-495 and along MA 3, MA
24, MA 25 and the MA 140 expressway soon followed. This gallery features
photos of the installed signs along with sketches of the signs from
contract documents if there was any difference between the two, and
commentary as to what could still be changed to improve some of the
signs:
I-84
There are only
two RTT signs planned for this short route. Heading west from the Mass
Pike, this is the planned sign, including the time and distance to the
Connecticut border (this sign has not been installed as of June 4,
2017):
The first and
only installed sign is on I-84 East in Sturbridge which also lists the
time and distance to I-290 in Worcester:
I-90/Mass Pike
(New Photos 10/14/16)
Heading west in
Newton, this first sign appears after the Newton Exit, Exit 17:
The second Newton
sign appears just prior to the I-95/128 exit:
The next sign
westbound is in Framingham:
Eighteen miles
later there is the next sign in Millbury:
The sign in
Charlton has both the distance to I-84 and to the CT state line:
Heading further
west, this the sign up approaching Springfield, in Wilbraham:
The original plan
had the sign going up a couple miles further to the west:
The next sign in
Westfield indicates the distance to the NY Thruway, not the state line
as with other highway's signs:
The final
sign westbound has the same information and was put up halfway
between Exits 3 and 2 in:
Notice
the distance to Lee was increased by a mile from the planned sign:
Returning
Eastbound, the first sign is in West Stockbridge (New 9/2/19):
Notice how the
bottom destination mileage was changed to 40 from 45 in the plans:
The
next sign is halfway between Exits 2 and 3 in Blandford (New 9/2/19):
Heading further
east, the sign in Westfield indicates distances to and along I-91 (New
9/2/19):
Beyond
Springfield, the next RTT sign is in Palmer alerting traffic to the
distances to the next 2 exits:
There's suppose
to be another one in Brimfield prior to the I-84 exit (still not up as
of 7/9/17):
This sign is now
up just prior to the I-290/I-395 Exit in Auburn:
Just before the
I-495 exit in Westborough there are two signs, the first lists the
distance to the next 3 exits, I've kept the sign plan showing the
difference in state mileage to Route 9:
The second
mentions times along I-495:
This was not
among the original sign plans.
The first mention
of I-95 (128) is in Framingham after the Route 9 exit:
Prior to the
I-95/128 Exit there is a sign after the Natick Service Plaza,
activated as of the last week of October 2016:
After the
I-95/128 exit, here is the first of 2 RTT signs in Newton:
Here, the
sign was adjusted down by 1 mile for the Allston-Brighton exit:
The second sign
(and last sign eastbound) is only a couple miles further down I-90 prior
to the Newton Exit and includes the distance to Logan Airport:
Interstate 91
Heading
northbound from Connecticut, the first RTT sign is in West Springfield
(notice the mileage to Springfield was decreased by a mile from the
planned sign, below):
The next
northbound sign is after the I-391 exit in Holyoke (photo by Jay Hogan,
again the mileage in the sign plan was apparently wrong):
There will also
be one further north in Whately approaching Route 2, with the time to
the Vermont border (photo by Jay Hogan, this one identical to the plan):
Heading back
southbound, the first RTT sign on I-91 is in Deerfield which (the sign
plan, below, apparently had the mileage to I-90 wrong, it has increased
from 24 to 28):
This is followed
with the first sign mentioning Springfield put up in Northampton (again,
the mileage differs from the sign plan, in this case by 2 miles):
The last one is
after the Mass Pike exit in West Springfield (the mileage on this sign
has also been changed from the plan for Springfield, as seen below):
Interstate 93
[Signs activated in November 2016]
The first sign
northbound is in Milton prior to the MA 24 exit:
The one issue I
have with this sign is mileage. Under the proposed milepost based
system, the Houghton Pond/Ponkapaug Road exit, whose bridge is just
behind the sign, would be Exit 2. MA 3 is and would be Exit 7, while
Columbia Rd would be Exit 14, therefore, shouldn't the mileage to
those two exits be 5 and 12?
Approaching the
interchange with Route 37 in Braintree is this sign:
The next sign is
six miles further north, just after Neponset Circle. This one one of the
last signs put up, notice the right-hand support due to the placement
next to a steep embankment:
After the Big Dig
Tunnel, the southernmost of two RTT signs Medford lists the time to I-95
(put up week of 8/15/16):
The
northernmost lists both I-95 and I-495 (also put up week of 8/15/16):
North of I-95,
this will be an RTT sign in Wilmington telling drivers how much time
until the New Hampshire border:
+Heading back
Southbound, here's the plan for the sign in Methuen:
The next sign
will be in Andover:
The
sign is different from the sign plan in it includes Route 38 instead
of Route 28 (plan mistake?)
The Anderson RTC
as in 'Regional Transit Center' is a massive Park and Ride (as in take a
bus into Boston).
The next sign is
in Stoneham near Spot Pond, it has the first distance to Boston (Mass
Ave.), and the Logan Airport:
This was a change from the planned sign:
There's no
mention of I-90 Mass Pike, even though there's a connection westbound.
The US 1 sign apparently was supposed to be a Route 1A shield, since
there is no direct connection to US 1 Southbound and it would be rather
out of the way to cross the Tobin Bridge to go to the Airport.
The next sign is
in Somerville and when first placed, due to contractor error, had the
distance to the Zakim is listed as the same for Mass Ave, 5 miles, this
was soon corrected to match the planned sign:
The next sign is
after the Tunnel and the Mass. Ave. exit, just after the South Bay
on-ramp:
Here they
reference Neponset Circle, not the MA 3A exit there. Also this is at
milepost 15, the MA 3 exit is at milepost 7, shouldn't that be 8 Miles?
Seems to match up better with the travel time. Speaking of Neponset
Circle, here's the newly activated sign approaching that location after
the Morrissey Blvd/Freeport St on-ramp:
You'll notice
that the mileage for both Route 3 and 24 have been changed from when the
sign was first put up in July:
Apparently
MassDOT realized that since this is approaching milepost 12, why was it
4 miles for Route 3 (Mile 7) here? Route 24 is around milepost 3.5 so 9
miles makes sense, though they added a mile to that as well.
This is the final
sign along the Southeast Expressway in Quincy, the 1-Mile overhead for
the Braintree Split is in the distance:
The sign was
identical to the plan sketch. Unfortunately for there are some mileage
problems here too, that weren't fixed. This around milepost 8, so the
distance to Route 24 is right, however, since that route is 3.5 miles
from the end of I-93 at I-95, shouldn't the I-95 mileage be at least 8
miles? The Route 18 mileage is okay, since that exit is at milepost 38
and the last milepost heading northbound on 3 is 42.8, around milepost 7
for I-93. so 1+5=6. However, if MassDOT ever goes ahead with the
proposal to renumber exits based on mileposts, this exit would be 42 for
MA 3, so could cause some confusion. The last sign on I-93 South is in
Milton just after the Route 24 on-ramp and was used by MassDOT for the
explanatory graphic about the signs (seen at the top of the section):
To be consistent
with other signs, there should be a 'Via I-95 North' by each entry or on
top of the sign. I guess they assume that drivers will know that I-93
ends at I-95 and that these are I-95 North exits.
I-95
Entering
northbound from Rhode Island, the first RTT sign is one mile over the
state line in Attleboro:
The next sign
is five miles further north before the I-295 Exit, with the first
mention on I-93:
The next sign
northbound, put up in March 2016 and activated in October, is in
Foxboro:
Approaching the
Neponset Street interchange in Canton, the sign was installed the week
of March 21 and activated in October 2016:
It is identical
to the sketch of the sign I had posted.
After the merge
with Route 128, the next sign is in Dedham between Route 109 exit ramps,
put up the week of 9/18:
Before the Mass
Pike, is the next sign in Needham just prior to the new Kendrick Street
and under construction Highland Avenue exits, activated in late October:
This differs
from the planned sign below because originally this sign was to be
placed 1 mile further north, closer to the Highland Avenue exit:
Just
North of the Mass Pike exit in Weston, this sign has been activated:
The next sign is
in Waltham at the Trapelo Road Exit now listing only US 3 and I-93 with
Route 2 on the adjacent overhead sign:
In Lexington,
after the MA 4/MA 225 exit, it is apparently too close to US 3 to
include it on this sign, but still with I-93:
Just prior to the
I-93 exit in Woburn, this is the plan for the signage:
The
distance to the Zakim Bridge has been increased by 1 from that of the
planned sign:
This is the sign
approaching the split with Route 128 in Wakefield, put up in March and
activated in November 2016, same as the sketch:
After the split
with Route 128, here is the RTT sign in Topsfield, which lists the time
to the NH border:
The first
number for the NH border is hard to make out in this photo.
Heading back
South, here's the first sign in Salisbury before the I-495 Exit, put up
in March, identical to the sketch:
Here's a sign put
up further south in Boxford, same as the sketch posted previously:
While here's the
signage after the Centre Street exit approaching Route 128 in Danvers
which will let you know what is the best route to Boston:
The next sign is
in Reading and provides the important time to the often congested I-93
interchange:
The sign just
before the I-93 interchange in Reading has the time to Boston (Zakim
Bridge), US 3 and Route 2:
This sign was
recently placed prior to the US 3 exit in Burlington and has the first
reference to I-90:
While this sign
was placed in March before the US 20 exit in Waltham, with same text as
previous sketch, here seen activated in January 2017:
The next sign in
Needham, tries to help those driving to the Amtrak station, put up after
the Kendrick Street exit in the Add-A-Lane work zone in September and
activated in November:
You can see it
differs from the sign plan from the contract documents:
Apparently,
MassDOT decided that even if its called Route 128 station, a 128 shield
was too confusing, so it has University Ave. instead with the MBTA and
Amtrak logos. The last sign before I-95 leaves Route 128 is just before
the US 1 interchange in Dedham and was installed the week of March 21
and activated by November 2016:
The sign was
identical to the sketch plan which for consistencies sake, I though
shouldn't the MA 3 shield have 'Via I-93 North' next to it, as we
continue south of Route 128, the next sign is after the on-ramp to Coney
Street in Sharon, put up in late March 2016 and activated in November:
Going further
south the last sign in Foxboro notes the approaching state border, again
activated in November 2016:
Text identical
to that in the previously posted sketch.
Interstate 190
There is only one
sign on I-190, southbound in Lancaster:
Interstate
195 [Signs Activated 9/27/16]
Heading east from
Providence, the first sign is just over the RI border in Seekonk,
Courtesy of MassDOT:
A temporary
orange background RTT sign was put in place due to the ongoing
construction on the Braga Bridge and with the Route 79 Viaduct
replacement project, it is still up even though most of the work is done
as of November 2016:
The next
permanent sign is a few miles further east in Somerset, just before
entering Fall River:
The last one
eastbound is in Marion and has the important time to the Bourne Bridge:
*Heading
westbound, the first I-195 RTT sign is in Wareham, noting the time to
the Braga Bridge, a typically congested area:
*The next sign
will be in Fairhaven, continuing the time to the Braga Bridge:
*As does this
sign further west in Dartmouth:
*The last sign in
Swansea simply gives the time to the border, again is this useful
information? Perhaps future coordination with RIDOT could give the time
to Providence:
Interstate 290
Despite its short
length, there will be six RTT signs planned for this route between the
Mass Pike/I-90 and I-495, the first one eastbound is in Auburn just
after the I-90/Mass Pike exit:
The next one is
beyond Worcester in Shrewsbury, not in the proposed location and changed
from the original sign plan, see below:
The last one is
near the end I-290 in Hudson basically providing I-495 drive times:
Turning around,
the first of the RTT signs on West I-290 is to be put up in
Northborough:
The next is 6
miles further west back in Shrewsbury:
The last one is
in Worcester after the interchange with I-190 providing a comparison of
alternate routes to the Mass Pike:
There is no
mention of I-395 on the I-290 signs, nor are there any sketches of
planned RTT signs on I-395.
Interstate 495 (*New photos taken in June 2021)
Heading
northbound, here is the first sign on Northbound I-495 in Middleboro:
The next sign
is a few miles prior to Route 24. Note the 6 mile distance, a 1/2
mile north, beyond the hill is a distance sign saying 24 is 7 miles
away (6 miles is the correct distance, the next distance sign is 3
miles before Route 24, saying its 4 miles away):
The next
sign is beyond Route 24 in Raynham, giving the time not only to
I-95, but travel times on I-95 itself (identical to sketch of
proposed sign):
Approaching
the Mass Pike in Bellingham, the sign will also indicate the time to
I-290/Route 85 Connector:
Beyond the
Mass Pike, here's the next sign in Bolton:
*The next
sign is in Westford, approaching US 3, the minutes reflect a traffic
jam before the US 3 exit in June 2021:
*Further north,
there is this sign in the Chelmsford Area after US 3:
*The last sign
northbound is to be in Methuen, less than 20 miles from I-95:
I don't know the
value of placing the state line distances on these signs, unless the
distance to the next major destination can be obtained other mileage
signs (according to a MassDOT source these are placeholders in case
NHDOT adopts the same system and a NH city can be put up over the
existing text).
+Heading back
south, the first sign will be in Methuen mentioning the time to I-93:
The next sign
will be in Andover approaching I-93 showing the time to I-95/128 via
I-93 or US 3:
+Next, in Lowell
this sign will be installed approaching US 3, again with the time to
I-95/128:
+The plan for the
sign further south approaching Route 2 in Westford:
Here's
a sign approaching the Mass Pike in Marlboro:
The
next sign southbound is in in Hopkinton, with the first mention of
I-95:
Here's
the sign placed further south in Franklin approaching US 1 and I-95
(same as the original design sketch):
The
next sign is just prior to I-95 in Foxboro, this one only has travel
times on I-95 South and North in addition to Route 24:
After I-95,
signs start mentioning the end of I-495 at I-195, this is the sign in
Norton before the Route 123 exit (this is different from the planned
sign that was to be installed a couple miles further north (see below):
You wouldn't need
the MA 25 shield if I-495 was extended along that route (or I-195 for
that matter). You can tell when you're nearing the Cape when signs with
the time to the Bourne Bridge is mentioned, such as this in Raynham
(identical to sketch of planned sign):
This is the last
sign southbound in Middleboro, it was not captured until Sept. 2018, not
being up during my previous drives through the area:
US 1
There are a
couple RTT signs placed along US 1 South between Peabody and Boston, the
first one in Saugus just after the MA 99 South exit*:
Notice that
mileage was changed from the original sign plan:
And the other is
just after the Route 16 exit and before the Tobin Bridge in Chelsea,
this was put up the week of 8/15/16:
US 3 [Signs
Activated in August 2016]
The only sign northbound is in
Bedford with times to I-495 and the New Hampshire Border:
+Heading back
south, here's the first planned RTT sign in Tyngsborough:
By
the time you get to Billerica, the signs have time and distance to
destinations on I-95 (the mileage to I-93, slightly obscured by the Deer
Crossing sign, is 14):
The
final sign southbound in Burlington also includes US 20, but wouldn't it
make sense, and be consistent with other signage, if it included 'Via
I-95 South' while I-93 had 'Via I-95 North'?:
US 6
Signs were
put up in April 2014 along the Mid-Cape Highway as part of trial for
the entire system installed later.
NEW-The first
RTT sign westbound is at the beginning of the Mid-Cape Highway in
Orleans:
This is one
of the signs showing the time to the Sagamore Bridge just west of
Yarmouth, taken in March 2017 (New):
Heading further
west there is a sign between Exits 3 and 2 in Sandwich:
These are July
2016 photos taken of the working signs along US 6 East, first just
beyond the Sagamore Bridge and MA 6A Sandwich exit:
The next before
the MA 132 Hyannis Exit:
Route 2
There are two RTT
signs planned for Route 2. Heading west from Cambridge, the first is in
Lexington, prior to the I-95 Exit:
Heading
eastbound, the sign is placed in Concord prior to the Sudbury Road
intersection with the all-important time and distance to the Alewife
MBTA Station:
This
sign was originally to be 2 miles closer after the MA 126
intersection, as seen by the distances on the sign plan:
Route 3 [Signs activated week of 10/11/16]
Heading South
toward Cape Cod, the first sign placed on Route 3 is in Braintree on the
left side shortly after the merge of the ramps from I-93 North and
South:
The temporary VMS
sign this replaced had Route 18 and Route 139, but the Derby Street
destination is more helpful because it is after Route 3 narrows from 3
to 2 lanes where the highway frequently backs up. The next sign, in
Weymouth beyond the Route 18 exit, features the next appearance of Route
139 and the first for US 44:
Both of which
are also on the next sign in Hanover, just beyond the MA 53 Exit:
It might be
helpful to include more destinations with the route shields, for example
if you were heading to Plymouth and didn't know the exit for US 44 was
there, listing Plymouth would make the sign more useful. The time to the
all important Sagamore Bridge over the Cape Cod Canal starts to appear
on RTT sign in just before the MA 139 exit in Marshfield,, though the
sign was activated when the photo was taken, it does not seem to be
displaying accurate times:
The next sign
is just prior to the first MA 3A Exit in Duxbury (sign identical to
plan):
The first
sign in Plymouth is just beyond the left exit for the Plimoth
Plantation Highway, here time to the Bourne Bridge is also
mentioned:
There is also a
sign placed five miles further south with distances to both the Sagamore
and Bourne Bridge, placed to help out drivers stuck in mid-summer
traffic jams:
The last sign
southbound, 3 miles from the bridge, also in Plymouth and features both
the same information, it was operational as of July 2016:
Heading back
northbound, the first RTT sign is just beyond the start of the Pilgrims
Highway in Bourne:
Again, maybe some
towns to go with the shields may make the sign more meaningful to out of
state drivers, as would on the next sign in prior to the MA 3A to 53
Exit in Duxbury (identical to plan):
Further north,
still in Duxbury approaching MA 139, is the first RTT sign to mention
I-93 (I-93 readers were activated later, in November 2016):
*Entering
Weymouth just beyond the Derby Street interchange, this sign was put up
the week of July 18, 2016 and fully activated with information about
I-93 and I-90 in November:
The addition to
the I-90 shield of Boston indicates the route via I-93 North, since you
could also get to the Mass Pike via I-93 South and I-95. Approaching
I-93 the last RTT sign is in Braintree, ironically, it doesn't include
the distance to I-93 (probably because the 2-mile advance sign for I-93
is visible from this location), but does have the distance along I-93
South to I-95, this was the last sign installed during the week of
August 15 (like all the other Route 3 signs, the text matches that in
the plan sketches) and fully activated in November:
Route 24 [Signs Activated 9/19/16]
Heading south
toward Rhode Island from I-93 the first RTT sign is in Randolph just two
miles after the start of the highway:
The next sign is
in Brockton, prior to the Route 123 interchange:
After I-495,
there is another sign in Raynham, for both I-195 and MA 140:
There is also an
additional sign in Berkley which compares the time to the I-195
interchange via Route 24 and Route 79 which are to join in a concurrency
a few miles to the south:
Better
earlier view:
The
Sign Sketch plan had no miles listed for Route 79, presumably due to
the construction project, recently completed, that rebuilt its
interchange with I-195:
For the MA 79
construction project, a special orange travel time sign was installed a
couple miles north of the Route 79 Exit, still there as of August 2016
(Photo from May 16):
Heading back
north, the first Route 24 RTT sign is in Freetown:
The next sign is
in Raynham prior to the I-495 interchange, with the first reference to
I-93:
The
next sign is in West Bridgewater, with I-93 now 10 miles away:
And another in
Avon referencing times to and on I-93 North, now 5 miles away, though
wouldn't a 'Via I-93 North' for I-90 be appropriate to be consistent?:
The last sign
heading northbound in Randolph has both the times to to I-95 and Route
3:
Route 25
There is one RTT
sign placed at the beginning of MA 25 West just over the Bourne Bridge:
Heading back
east, the first sign is just beyond the I-195 and I-495 interchange in
Wareham:
The second and
final sign is on MA 25 East in Bourne. This was installed in April 2014
as a trial project and activated soon after:
Route 28
There area a pair
of RTT signs along the expressway portion of Route 28 in Bourne,
southbound with the time to Falmouth, and the island ferries:
The distance to
Woods Hole was changed from the original sign plan:
There is also a
sign northbound, not in the original plans which lists the time to the
Bourne Bridge, Route 3 and I-495:
Route 128
The route from
Peabody to Gloucester has three RTT signs that have already been
installed, the one heading northbound includes the time across the
Annisquam River to Grant Circle and is the same as the previously posted
sketch:
The two signs
southbound, one in Essex, after MA 133, seen below, the other in
Beverly, below it, after MA 1A, have the time and distances to I-95 and
I-93 and were partially activated, showing the time to I-95 in June
2016:
Route 140
There will be
three RTT signs placed along the freeway portion of this route from New
Bedford to MA 24. The only sign northbound will be in Lakeville (this,
like the others are identical to the sketch plans):
*The first
southbound sign will be right after the MA 140 freeway begins in
Taunton:
+The other
southbound sign will be in New Bedford, prior to its reaching the
Interstate 195 interchange:
Feel free to
e-mail me any photos you wish to share.
G.
Route 2 Crosby's Corner Reconstruction (2/19/18)
In the spring of
2012 MassDOT began a project to rebuild Route 2 between Bedford Road and
Crosby's Corner, a notorious intersection along the highway in Concord.
In June 2015, a new off-ramp was opened westbound at Crosby's Corner
replacing the previous stoplight at the intersection with Route 2A.
Eventually, the entire intersection will be converted into an
interchange in both directions when the project is completed, currently
scheduled to be in the summer of 2016. Here are a few photos heading
both westbound and on Route 2 toward the new interchange, taken shortly
before construction was completed in April 2016:
Heading west, new
overhead signage bearing a new exit number, 50 were put up in late
2015. If the proposed switch to milepost based numbers, planned
for 2016 but postponed, ever happens, this should become Exit 125. The
one-mile advance sign:
Here's the next
sign, at the 1/2 mile mark:
There 's a
complete overhead assembly at the off-ramp itself, the pull through
shows this is one of the few places in Massachusetts where an alternate
route is officially signed with its parent (other routes like 1A and 3A
run concurrently but are not signed):
And here are the
new Exit 50 gore sign as seen from continuing on Route 2 West, this will
become Exit 125 under the new milepost based exit numbering system that
will be installed by 2021:
And here are the
new reassurance marker's showing the official duplex of Routes 2 and 2A:
Turning around at
the MA 126/Walden Pond intersection, the first sign for the new Crosby's
Corner exit is 1/2 mile away:
Like westbound,
the overhead support at the interchange has 2 signs, the Route 2
pull-through has a left-side upward arrow:
Here are several
photos of the reconstructed roadway eastbound following the exit, to see
westbound views, see below.
This is after the
off-ramp to Route 2A:
Heading over the
bridge seen above:
This is at the
end of the new on-ramp from Crosby's Corner:
Here's the view
on the other side of the hill:
The traffic light
in the distance for Bedford Road would be Exit 51 (or 126) if it was
ever turned into an interchange. Some bonus photos of overhead signage
for the next interchange with I-95:
This is the
1-Mile advance sign, placed back in 2012. There are no auxiliary signs
mentioning MA 128 here, though coincidentally this was proposed to be
Exit 128 under the Milepost Exit Numbering System that was to start
sometime in 2016, but is now indefinitely postponed. Here's the 1/2 mile
advance sign for I-95 South, the Attleboro destination or control city
is not consistent with other exit signage along I-95 in the area that
lists Providence, RI:
Same sign back in
2016 when the Route 2 bridge over I-95/128 was under construction:
The orange
construction sign refers to work on a project that is replacing the
Route 2 bridges over I-95/128. A closer view of the work zone:
The Spring Street
1-Mile advance sign is the last overhead sign before the work area. All
the other overheads were temporarily removed and replaced by orange
ground-mounted signs:
Here's the
appearance of the interchange after work was completed in the summer of
2016:
For some reason
(better visibility?) the Route 128 shield was replaced with a larger one
in 2017. Here was the 2016 version:
Previous Photos
-- taken
on July, 5, 2015:
East
of Crosby's Corner work has concentrated on expanding the roadbed and
adding new stone retaining walls, the first are along the eastbound
side.
Work
is almost complete on the new stone wall westbound 1/4 mile from
Crosby's Corner. Here's a closer view:
Closer to Crosby's Corner there is
evidence of much more work needing to be done:
The
sign in the distance is a temporary exit sign for the new MA 2A
off-ramp. Which, a closer look reveals...
Has
an exit number, 50. This will partially fill in a gap in Route 2 exit
numbers in this area. The last interchange to the East, I-95/MA 128, is
Exit 52, which, coincidentally, should have been Exit 128 when
Massachusetts adopted the federally mandated milepost referencing system
in 2021, however, to reduce the number of exits requiring letters to the
east, they have given it the number 127. The Concord exit will be 125.
H. South Shore Roads
1. Route 18
Widening Project, 2017-2022:
This project
began in 2017 and widened Route 18 to four lanes for about 4 miles from
Middle Street in Weymouth to Route 139 in Abington. Below are a series
of photos taken of construction starting in November 2022, and
proceeding backwards to May 2018. Work was to conclude on the Weymouth
section by the end of 2019, but by late 2020, as photos below indicate,
while much progress had been made over the summer and fall of 2020, with
many sections near completion and four lanes opened up in either
direction from Route 3 to 139. Final paving of the completed lanes
started in the summer of 2021. Lanes between Route 58 and Route 139 were
completed first during the summer of 2021. Work then moved northward
with the final paving of the new lanes in Weymouth taking place in the
fall of 2021. Work however continued, and more new signage was
installed, particularly at major intersections. Work on replacing the
commuter railroad bridge was the last piece of the project to complete.
That was scheduled to be also finished in the fall of 2021, however work
continued into 2022, the bridge was finally opened to 4-lanes as of
November, and remaining guide signage installed. Work now appears to be
complete after more than 5 years...
Latest Photos,
Taken November 23 and 26, 2022
The finally
completed commuter railroad bridge, and an added new Mile 38 marker
before it on Route 18 North on Thanksgiving weekend.
Traffic on Route
18 North heading up the railroad bridge.
Traffic heading
down the commuter railroad bridge, with 4-lane roadway heading towards
Columbian Square in the distance.
A new North Route
18 reassurance marker after the completed commuter railroad bridge.
Turning around....
A new guide sign
for MA 58 South was finally put up in November as well.
A closeup view of
the previously installed guide signs at the start of South Route 58, no
Route 18 doesn't go to Quincy, but Route 53 does.
A first North
Route 18 reassurance marker after Route 58 is beyond the Trotter Road
intersection.
EARLIER PHOTOS
Taken September
27, 2022
This recently
placed Junction Route 58 trailblazer has an arrow implying the route
goes straight at the next intersection, instead of left. This is
complicated by a lack of additional guide signs at the intersection,
these will not be placed until November.
Photos Taken
November 28, 2021
Looking north
from the still incomplete South Weymouth commuter railroad bridge
showing final pavement has been placed on the 4 traffic lanes north of
the bridge.
Traffic at the
bottom of the bridge on Route 18 North shifting onto the newly paved 2
traffic lanes north of the bridge.
Driving the
permanent pavement placed on Route 18 North approaching the entrance to
Union Point. Work was still continuing along the southbound lanes beyond
the traffic light.
Heading further
north in Weymouth toward Columbian Square, all new lane markings in
place, The new building behind the Stockholders Restaurant sign
advertises itself as luxury condos. Is this because it's by a steak
house (and Friendly's) or that it overlooks a Citgo station?
Further north,
beyond the existing 4-lane section by South Shore Hospital and the Park
Drive intersection, the widening has also been completed.
The new sidewalks
are concrete in this section, approaching one of the new flashing
pedestrian crossing signals.
Traffic
approaching the Middle Street intersection and the end of the widening
project work zone.
Previous Photos:
Taken August 10,
2021
Approaching the
commuter railroad bridge on Route 18 South. Traffic was moved back to
the completed future southbound lanes of the bridge after the structure
for the northbound bridge was put in place in early August.
At the foot of
the railroad bridge on Route 18 South. Work continues to tie in the new
northbound bridge with the existing travel lanes.
View at the top
of the commuter railroad bridge on Route 18 South sharing the bridge
with northbound traffic.
About to leave
the commuter railroad bridge on Route 18 South. Hard to tell whether all
the construction equipment at the bottom is for the bridge or the new
apartment building being constructed. Now turning around...
Traffic shifted
to the left approaching the commuter railroad bridge on Route 18 North.
The new bridge structure is behind the concrete barrier at the top of
the bridge.
Traffic shifted
back to the right after the commuter railroad bridge on Route 18 North.
New fencing can be seen behind the guardrails along the Northbound
lanes. Heading back south beyond the Route 58 intersection...
Route 18 south of
the Route 58 intersection has received its final pavement layer and
awaits final lane striping.
The paved lanes
of Route 18 just over the Abington town line.
Repaved Route 18
just south of the Abington Ale House at the corner of Highland Road.
Paved Route 18
looking toward the southern end of the project at the Route 139
intersection in Abington.
Paved Route 18
looking toward the southern end of the project at the Route 139
intersection in Abington.
PREVIOUS PHOTOS
Taken January 2,
2021:
Heading south
from Pleasant Street in Weymouth towards Abington:
Four lanes, and
here 4 lanes and a left turn lane, now open along Route 18 headed south
at the Shea Blvd/Union Point entrance.
Four lanes
continuing south of the Shea Blvd/Union Point entrance.
The four lanes
are about to end as we approach the still under construction commuter
railroad bridge.
Traffic has now
been shifted to the future north lanes approaching the commuter railroad
bridge.
Proceeding on the
commuter railroad bridge with construction going on in the future south
lanes.
Looking south
from the top of the commuter railroad bridge.
The four lanes
begin again as Route 18 approaches Trotter Road.
Scene of widened
Route 18 at the intersection with Route 58 heading toward Abington.
The fully widened
roadway after Route 58 heading toward Abington.
Still heading
toward Abington, the roadway here appears to have its final pavement.
Now across the
line into Abington, the roadway here will need another layer of pavement
in the spring.
Widened 4-lane
roadway in Abington, another pavement layer and landscaping needed here.
Now heading back
north from Route 139:
The widened
roadway passing the fire station, looking north.
The widened
roadway after the Abington Ale House, the right lane will benefit by a
final pavement layer.
Getting closer to
the Weymouth border, a final pavement layer still needed to improve the
right lane.
The newly widened
roadway about to cross into Weymouth.
Heading back
towards the Route 58 intersection along the first completed section of
widened roadway.
Approaching the
Route 58 intersection and added left turn only lane.
Traffic barrels
still in the concrete median between the Route 58 and Trotter Road
intersections.
Two lanes reduce
back to one to cross the again over the commuter railroad bridge.
Traffic squeezing
over to cross the commuter railroad bridge.
The have
completed a temporary sidewalk along the northbound lanes which meets up
with the permanent one by the commuter rail parking lot.
Looking from the
top of the bridge as the two lanes increase again to 4 at the bottom of
the bridge.
Entering the
widened section of Route 18 North after the commuter railroad bridge.
The recently
widened Route 18 roadway between the commuter railroad bridge and Shea
Blvd.
Stopping for the
light at Shea Blvd, still need a final pavement layer here. Now skipping
to the northern end of the project...
The recently
widened Route 18 roadway at the end of the former 2-lane section near
Middle Street, the sidewalk still needs to be completed and a final
pavement layer applied.
The northern end
of the Route 18 widening project at Middle Street, the interchange with
Route 3 is down the hill after the traffic light.
Taken in
mid-November 2020. Heading north from Route 139 in Abington to Pleasant
Street in Weymouth:
The widened
roadbed has received a final layer of pavement and all lanes are now
open from Route 139 to just short of the fire station.
Only 1 lane is
open from here to the Weymouth line restricted by cones or orange
barrels, some landscaping work remains.
Line painting is
complete with more landscaping work needed to be done heading up hill
towards the Abington Ale House.
Some final
curbing work needs to be completed before final line painting can be
done near the top of the hill.
Work appears near
completion along Route 18 between the Abington Ale House and the
Weymouth town line, including newly paved sidewalks.
Same appearance
heading north as get closer to the Weymouth border.
The widened
roadway at the Abington/Weymouth border, portable VMS with "Use Caution"
text concerns driving in a construction zone, but could be applicable to
driving Route 18 at any time.
Now in Weymouth,
the Route 18 roadway more recently paved and lanes painted, though the
new lanes are also restricted by traffic cones and barrels.
Approaching the
Route 58 intersection, road widens further to accommodate a left-turn
only lane.
Now past the
Trotter Road intersection headed towards the commuter railroad bridge
where traffic narrows back to one-lane in each direction.
That is because
work on the bridge continues and all traffic must use what will be the
southbound side of the bridge.
Looking north
from the top of the bridge towards the nearly completed widened roadway
on the other side.
After the bridge
the southbound lanes have been re-striped, but not those for Route 18
North.
Heading further
north, it appears work on southbound lanes is complete, waiting the lane
re-striping of Route 18 North.
Lanes southbound
have been repainted to allow for a left turn only lane to Shea Blvd, on
other side of traffic signal.
Four lanes of
traffic now open along Route 18 North after the 99 Restaurant,
southbound waiting for remaining sidewalk paving to be complete across
from the Citgo station.
All lanes are now
open approaching the Pleasant and Pond Streets intersection in South
Weymouth.
The newly opened
4-lane Route 18 south of Pleasant/Pond Streets meets the existing 4-lane
section to the north.
2. Taken in
September 2020. Heading north in Abington:
Progress seen
heading north in Abington with future southbound lane now paved along
with northbound lane.
The newly paved
Route 18 South lane continues toward the curve at the Abington Ale
House.
Future lanes on
both sides now paved beyond Abington Ale House heading north toward
Weymouth.
Curbing has now
been installed along both sides of the highway as the route approaches
the Abington/Weymouth border.
Approaching the
Weymouth line, work still needs to be done to install curbing along the
northbound lanes.
The newly paved
lanes end at the Weymouth line where the Route 18 North roadway was
previously widened. Not much progress seen up to Commuter Railroad
bridge since August, see photos below.
Heading south
starting at Pleasant Street in Weymouth
Soon after the
beginning of construction starts for the new southbound lanes prior to
the Shea Blvd./Union Point intersection.
Approaching the
Shea Blvd intersection showing grading of future south lane starting
which continues toward railroad bridge.
Which then turns
into a paved lane blocked off by cones closer to the bridge.
The paved
southbound lane continues to the foot of the bridge.
Traffic shifts to
right to go over temporary bridge while new bridge construction goes on
to the left.
View from the top
of the temporary railroad bridge showing road work and new building work
surrounding the commuter rail parking lot.
View from the
just south of of the temporary railroad bridge showing start of newly
paved future south lane across from commuter rail parking lot.
Approaching the
intersection with Trotter Road with the new pavement of the future
southbound lane continuing.
View southbound
after the Route 58 intersection of the paved new lane and curbing
heading towards Abington.
The paved new
lane and curbing continues along the future south lane, only near the
Abington town line.
New pavement
starts again along southbound Route 18 after crossing into Abington.
New pavement and
curbing continue along southbound Route 18 in Abington.
Curbing completed
along both sides of Route 18 starting at the DiNatale Landscaping Co. in
Abington, though new pavement of existing lanes temporarily ends.
New pavement
starts again approaching the Abington Ale House, though no curbing
northbound again.
New pavement ends
along Route 18 after the curve following the Abington Ale House.
The existing
pavement returns along southbound Route 18 until the Route 139
intersection.
Photos taken in
August 2020:
A new overhead
set of traffic signals has been placed just north of Route 139 in
Abington for the fire station, little other widening progress seen at
the very southern end of the project.
The new northern
lane has been paved starting north of the fire station.
The paving of the
future new northern lane continues up the hill toward the Abington Ale
House. No new progress heading south.
The paving of the
future new northern lane continues after the Ale House. Note grading of
future lane heading south.
The paving of the
future new northern lane continues heading north along with south lane
grading.
Meanwhile the
deterioration of the pavement on the current lanes continues.
Appoaching the
Weymouth line, the southbound future lane is paved as well along with
the installation of new curbing.
The paved and
curbed southbound future lane continues, along with the paved northern
lane approaching the border.
The new pavement
comes to an end northbound at the previously completed section at the
Weymouth line.
However, the
placement of curbing and new pavement continues along Route 18 South
heading toward the Route 58 intersection.
The new pavement
expands to cover the entire South Route 18 lanes approaching Route 58.
More paving along
the future Route 18 South lane approaching the commuter railroad bridge,
steel supports have been placed on the bridge for the future northbound
lanes.
A closer look at
the steel structure now in place for the right side of the commuter
railroad bridge.
Looking north
from the top of the railroad bridge showing traffic using widened
section of Route 18.
Traffic heading
north transitioning to new lanes after the commuter railroad bridge,
notice grading along the southbound roadway.
Curbing has been
completed and new sidewalk paved north of the railroad bridge heading
toward the intersection at Shea Boulevard.
The completed
curbing and sidewalk continues toward Shea Boulevard, traffic still
restricted to one lane this direction by traffic barrels.
The paved and
widened Route 18 North lanes at Shea Boulevard/Union Point Development.
The sidewalk
transitions to concrete at the entrance to Union Point and continues as
paved after the intersection.
The new paved
northbound roadway, sidewalk and curbing continue after the Shea
Boulevard intersection.
New pavement
stops and work on the new sidewalk has not been completed further north
in the vicinity of the 99 Restaurant.
Looking north
towards the Pleasant Street/Pond Street intersection with widened
northbound lanes paved but sidewalk work continuing.
Work has just
started on installing curbing approaching the Pleasant Street
intersection.
The paved widened
northbound lanes continue to the Pleasant Street intersection.
Earlier Photos
Taken of paving
along Route 18 North between Railroad Bridge and Pleasant Street on May
26, 2020:
Heading south
after Pleasant Street showing some paving in current northbound lane, if
not future lane.
Approaching
intersection with Shea Blvd. at entrance to Union Point, more paving
completed after intersection, see photos below.
Looking north
from commuter rail bridge showing new paving along northbound lanes
after the bridge.
Work continues on
bridge and its approaches causing Route 18 North traffic to shift to
right onto newly paved lanes after the bridge.
Traffic now using
new right most northbound lane as work continues along the right
shoulder to include the installation of curbing.
Newly paved
northbound lanes continue until intersection with Shea Boulevard, see
photo at top of section.
A closer look at
the end of the northbound lane full paving at Shea Boulevard.
North of Shea
Boulevard the new pavement is restricted to the right most side of the
Route 18 North lanes.
The Bump advisory
sign indicates a widened area of new pavement between the 99 Restaurant
and the Citgo station.
Paving of the
future northbound lane continues with pavement encompassing all the
northbound lanes after the station to just before Pleasant Street.
Previous Photos
Taken along Route
18 North the entire length of the widening project work zone on May 3,
2020:
Little progress
seen since the beginning of the year just beyond the Route 139
intersection. New utility poles are in but most of the wires are still
on the old poles.
In vicinity of
fire station. Again, new poles placed bur wiring predominantly on old
poles, pavement conditions have deteriorated further along this stretch.
Further north
approaching the Abington Ale House, little progress seen until reach the
top of the hill.
Along Route 18
North clearing of utility poles from future northbound lane still needs
to be completed for any further work to proceed.
Now past the
Abington Ale House, work is still needed to relocate utilities and
guardrail in new lane right of way.
While some of the
future northbound lane has been graded, work remains to relocate
utilities approaching the border with Weymouth.
More work has
been done to clear the southbound future lane than the one for Route 18
North at the Abington/Weymouth line.
Little progress
seen in clearing utility poles from right of way along Route 18 South,
compared to completed North lanes approaching Route 58 intersection.
VMS prior to
railroad bridge on Route 18 North warns of upcoming paving operations
north of the bridge during May.
Work continues on
building the new northbound lanes on the commuter railroad bridge, after
most of the old bridge was demolished.
Looking north
from the top of the commuter railroad bridge showing bridge construction
ongoing.
View from other
side of commuter railroad bridge showing transition to graded new Route
18 lane north of the bridge awaiting paving.
Some further work
being done along graded new lane awaiting paving further north from
commuter railroad bridge.
Further north
approaching intersection with Shea Boulevard with more graded new lane
awaiting paving.
Construction
equipment still grading future Route 18 North lane approaching between
Shea Boulevard and Pleasant Street.
More work is
needed before paving can begin on this part of the future Route 18 North
lane approaching Pleasant Street.
Concrete culverts
still need to be placed before the short section between Pleasant Street
and South Shore Hospital can be widened.
Not much progress
seen in the northern widening area between Park Street and Middle Street
since January.
New gas line
pipes are stored along the Route 18 south lanes approaching Middle
Street indicating these will have to be placed before widening work can
be completed.
Earlier Photos
Photo from early
March 2020 at the commuter rail bridge:
Looking north at
the commuter rail bridge still under construction in April 2020. Route
18 was to be closed down at night for a week in mid-April to expedite
final reconstruction. Paving of the new northbound lanes north of the
bridge is suppose to then start in late April or early May.
Earlier photos
from December 27, 2019 near commuter rail bridge:
Concrete drainage
structures await placement sitting in future Route 18 North lanes to
north of bridge.
While the wires
have been moved to the new telephone poles along the southbound lanes,
the old poles still stand in the future north lanes approaching the
bridge.
Roadbed is quite
bumpy approaching the commuter rail bridge, unlikely to be fixed until
spring.
Work is
continuing to expand side of commuter rail bridge for future additional
Route 18 North lane.
View from top of
the bridge, large crane still being used to widen east side of bridge
for additional northbound lane.
View at bottom of
south side of commuter rail bridge, not much progress in expanding paved
new lanes toward the bridge.
Photos from
December 15, 2019 at north end of project in Weymouth:
Heading south
beyond Middle Street shows utility poles still in the future additional
Route 18 South lane.
Not too much
progress seen further south heading toward Park Avenue, Weymouth portion
of project was to be completed by end of 2019.
Piece of
construction equipment in future Route 18 South lane indicates some
progress is being made, most utility poles approaching Park Avenue have
been moved.
Photos from
October 23, 2019 of work on the commuter rail bridge:
Work continues on
replacing and widening commuter rail bridge near the South Weymouth
commuter rail station, looking north.
A closer view of
work on the future northbound lanes over the bridge.
Photos from
October 6, 2019 heading north between Route 139 and Pleasant Street:
View approaching
Abington Ale House, work to move wires to new utility poles along Route
18 North has begun.
View heading
toward Weymouth, little but utility work being done in this area prior
to widening, lanes are closed between 8 PM and 5 AM Sunday to Thursday.
New utility poles
are only evidence of future widening approaching the Weymouth town line.
Work has started
along future southbound lanes to the left near the Route 58 intersection
in South Weymouth.
Work continues on
widening the northbound side of the commuter rail bridge in South
Weymouth.
Photos from
September 1, 2019 heading south from Route 3 to Route 139:
This is how the
first section of the widening project between Middle Street and Park
Drive appeared on September 1. Work is still underway to place new a new
drainage system under the future south lanes.
Approaching Park
Drive work is still continuing on moving both the above and below ground
utilities before widening work can begin.
A few traffic
cones is the only evidence of work done in the second widening zone
between Columbian Street and Pleasant/Pond Street intersection.
Little work on
widening has occurred in the past two months in the third zone area
between Pleasant Street and the entrance to the Union Point Development,
especially along the northbound side.
The intersection
with Shea Blvd. at Union Point has a new traffic signal designed for 2
southbound lanes, currently the left turn only arrow is above the second
through lane at this location.
Not much progress
to report south of Shea Blvd. during the last 2 months. Power lines
still on old utility poles.
Pipes for
drainage work still stand along Route 18 North along with old utility
poles prior to commuter rail bridge.
Work can be seen
at the commuter rail bridge. Traffic was detoured during the weekend of
August 24-25 so that work could be expedited on replacing the northbound
lanes.
Construction
equipment and a crane are parked besides Route 18 North lanes for bridge
reconstruction.
View looking
south from the top of the commuter rail bridge showing little progress
widening the southbound lanes headed toward Route 58.
New retaining
wall along Route 18 South awaits utility pole removal so road can be
expanded opposite the South Weymouth Commuter Rail Station parking lot.
Nothing new to
report in past two months at intersection with Route 58 except new
yellow traffic light structure going up in the right.
A closeup view of
the new traffic light.
Little work can
be seen southbound in moving the power lines from the old to new poles
that would allow for road widening between Route 58 and the Abington
line.
View largely
changed southbound entering Abington in the last couple month, more
utility pole removal is need before widening can begin.
This section of
Route 18 in Abington is supposedly to be the last part of the widening
project, which explains the lack of progress here.
The road
conditions have only gotten worse beyond the Abington Ale House with a
mixture of old and new pavement where underground utilities have been
moved.
The cleared
future southbound lane is now being used as a storage area for drainage
pipes approaching Route 139.
Southbound lanes
by Abington Fire Station, future new lane also a storage area and
existing pavement torn up for utility relocation underground, while
wires remain to be moved above ground.
New utility poles
along northbound lanes hint at construction to come approaching end of
project limits at Route 139 in Abington.
Photos at
Commuter Rail Bridge from July 2019:
Work is
proceeding in demolishing old bridge along former northbound lanes.
Looking south
toward Route 58 interchange showing progress in preparing road widening
opposite rail station.
Photos from May
2019 between Route 3 and South Shore Hospital:
View heading
south showing clearing for new lane along properties after intersection
with Middle Street.
Work continues
approaching the intersection with Park Drive (Route 128 until 1959).
Widening project
work picks up again after the 4-lane section surrounding South Shore
Hospital, new utility poles in place.
Work moving
utilities for the widening is still occurring along Route 18 South
approaching the intersection with Pleasant Street.
Photos from April
2019 between Pleasant Street and Route 139:
View heading
south after Pleasant Street in Weymouth showing progress in moving
utilities out of future roadway right-of-way.
Similar work
going on further south by Stockholders and the 99 Restaurant.
Work not as
pronounced approaching the Shea Boulevard intersection on Route 18
South.
Work mostly along
northbound lanes approaching the Commuter Rail bridge southbound.
Utility lines now
on new poles along southbound Route 18 approaching railroad bridge,
poles along northbound side still need to be removed.
Work was almost
completed along new bridge section which Route 18 traffic was to shift
onto the first week, then delayed to the second week of May.
Looking south
from top of railroad bridge toward intersection by South Weymouth
Commuter Rail Station with completed new northbound land separated by
painted line after the bridge.
On the right, old
utility poles have had wires removed to be placed on new poles, finished
northbound lane with painted lines over it to exclude traffic to the
left opposite the South Weymouth Commuter Rail Station parking lot.
Concrete pipes
await placement along Route 18 South just prior to the Route 58
intersection.
A new slightly
wider support posts awaits new traffic signals at the intersection of
Routes 18 and 58 South.
South of Route 58
the completed northbound lane is striped to prevent use by traffic and
work is proceeding to remove wire from the old utility poles along Route
18 South.
Similar
conditions further south just prior to crossing into Abington.
The completed
northbound lane ends as Route 18 enters Abington, construction on this
southernmost section will not finish until 2020.
Less progress
heading south in Abington and lack of maintenance on to be replaced
roadbed leads to a bumpy ride and blurry picture.
Not much progress
seen since last fall in the widening construction along the southbound
lanes near the Abington Ale House.
Similar story on
the bumpy roadbed south of the Abington Ale House.
More concrete
pipes await placement, as well as utility poles heading south toward
Route 139 in Abington.
Little has
changed since last fall approaching the Route 139 intersection.
Nine days later,
a look at the completed and striped off new Route 18 North lane by the
South Weymouth Commuter Rail station parking lot.
Portable VMS in
the new Route 18 North lane advising drivers as to upcoming traffic
shift on commuter rail bridge in May.
Looking south
along the ready to use Route 18 North lane between Route 58 and the
Railroad Bridge.
Photos from
November 2018:
Twilight view of
cleared land on both sides of current roadway as seen on MA 18 North in
Abington near the Weymouth town line.
Starting at the
Weymouth line preliminary paving has been completed for future
northbound right lane.
Newly paved lane
continues to MA 58 intersection, seen at traffic light in distance and
then beyond intersection to just south of railroad bridge.
Heading south a
few days later approaching the railroad bridge, work on the bridge is
being staged behind the concrete barriers on the left, while clearing
has been completed along the southbound lanes.
Former utility
poles in the future southbound lanes have been removed as seen
approaching the railroad bridge.
Temporary
advisory sign (along with portable VMS, not pictured) regarding lane
shift southbound approaching the railroad bridge.
Apparently work
to demolish the current bridge while it's still open requires shifting
traffic over, the Route 18 North lane is now partly in the former
shoulder.
Construction
equipment and other needed items in the construction zone at the top of
the bridge.
View looking
south from the top of the bridge which was to show the beginning (or
end) of the new paved lane heading northbound, hidden by traffic
unfortunately.
View of paved
future northbound lane on left as Route 18 traffic is shifted back to
its original alignment after the railroad bridge.
Future Northbound
lane paved heading past commuter rail parking lot.
The widening
project has resulted in the future roadway's close proximity to the
Public Storage warehouse building.
View of completed
paving between the MA 58 and Trotter Road intersections on Route 18
North. This section was already 4 lames, but the road has been widened a
little more with new curbing added.
My attempt to
capture the railroad bridge approach heading north at dusk.
Photos from
September 2018:
Area cleared
along North Route 18 just prior to the railroad bridge for future lane.
VMS messages indicate preliminary paving was to take place during
October, weather permitting.
Heading south
now, prior to the Union Point development entrance, new utility poles
have started going up in this area.
New barriers and
barrels put up along Route 18 South prior to the Route 58 intersection
where preliminary widening work is taking place.
New temporary
barriers have also been placed along MA 18 North after the current
railroad bridge, work to demolish the old bridge and open a new wider
one will take place in 2019.
One of the VMS
advising traffic of paving work prior to the railroad bridge on Route 18
South prior to the South Weymouth commuter rail station.
View from top of
railroad bridge looking south shows progress grading new northbound
lanes as seen in the first photo.
Closer view of
new lane being constructed northbound approaching the Route 58
intersection heading south on Route 18.
Work has also
started for adding a northbound lane between the Route 58 intersection
and the Abington town line.
More future
northbound lane grading awaiting preliminary paving approaching the
Abington town line.
Construction
equipment stored near the end of the current widening work being done
just over the line in Abington.
Only preliminary
work still has been completed at the southern end of the project
approaching Route 139.
The exception is
near the Abington Ale House where the widening work is apparently being
coordinated with a new development (see earlier photos below).
Previous photos
from July 2018:
Only preliminary
work and some new utility poles can be seen southbound approaching the
southern limits of the project at Route 139 in Abington.
Only some tree
cutting has been completed southbound approaching Route 139.
Little progress
can be seen since May approaching the current railroad bridge on Route
18 South in Weymouth.
Work can be seen
on building the new bridge to the left of the current structure heading
south.
View looking
north from the top of the railroad bridge, not too different from that
in May.
Earlier photos
from May 2018:
Work zone sign
south of Route 139 intersection on Route 18 North in Abington.
Some clearing but
not much work has started north of Route 139 heading towards Weymouth.
Work had started
along the southbound lanes in coordination with a new development going
in near the Abington Ale House.
Starting at the
Abington/Weymouth town line work was proceeding in putting in new
utility poles along the sides of the future widened highway.
Portable VMS sign
warns drivers of lane closures overnight for widening work as more new
utility poles stand next to existing ones in South Weymouth.
Route 18 about to
head onto bridge over commuter rail tracks, bridge to be demolished and
rebuilt, part of new bridge can be seen to the left of the current one.
Miscellaneous
construction equipment and materials are store along northbound lanes
prior to bridge.
Looking north
from top of railroad bridge showing clearing and other work taking place
in project work zone.
Utility pole
relocation work continues north of the bridge.
Some of the
bigger construction equipment being stored in future Route 18 southbound
lane in Weymouth. Turning around and heading south...
Clearing for
future Route 18 south lane heading toward railroad bridge in Weymouth.
Heading south
over current railroad bridge, clearing for new bridge continues on the
right.
Looking south
toward Route 58 intersection from top of current railroad bridge, new
bridge construction seen on right.
Some preliminary
work has been completed approaching the Route 58 intersection
southbound.
View of the new
utility poles placed beyond the future highway lanes south of the Route
58 intersection.
Now further south
in Abington, one can tell that maintenance of this section of Route 18
was deferred awaiting the highway's widening.
Passing
southbound work being done in coordination with a new development along
the southbound lanes prior to the Abington Ale House.
New barrier wall
being placed for new building development providing room for future
southbound Route 18 lane across from the Abington Ale House.
More preliminary
work can be seen along Route 18 South approaching the Route 139
intersection.
This residential
property in Abington will be losing much of its front yard to the new
Route 18 South lane.
2. A Trip along
"The Coastal Route," Route 3A North in September 2018:
Photos taken from
Plymouth to Hingham on Route 3A, (mostly) the old coastal route between
Boston and Cape Cod, which was given the Route 3A designation (after
first being New England Route 6A) in the 1920s. The other route, the
inland route or "Cape Way" got the primary Route 3, then Route 53,
number at the same time:
A modern, and
very large, North Route 3A reassurance marker seen in North Plymouth.
A North Route 3A
trailblazer on the left side of the road, going left leads you back to
Route 3 just north of US 44.
A guide/paddle
sign, not of recent vintage at the intersection with Chestnut Street in
Duxbury.
Guide/Paddle
signs at the intersection of Routes 3A and 14 in Duxbury.
Junction Route
139 trailblazer approaching first of two intersections with this route
in Duxbury, with an interesting twist...
You turn right to
go onto Route 139 West and left to go east. Route 139 does an 180 degree
turn at the Marshfield coast. MassDOT apparently decided changing
directions was too confusing. The previous guide signs at this location
had no direction.
One of many
old-style Mass. DPW tenth-mile posts along this stretch of Route 3A.
These were installed along most routes in the state in the 1970s.
Recent
Guide/Paddle sign installations approaching the second intersection with
Route 139 in Marshfield, the sign directions here are geographically
correct.
The signs at the
intersection itself, Route 3A North joins Route 139 West for about 1/2
mile.
MassDOT decided
to put the somewhat modern style large route markers on separate posts
west of the intersection of Routes 3A and 139.
Slightly older
Guide/Paddle signs approaching the split of Route 3A North and Route 139
West in Marshfield.
The signs at the
actual intersection. Of course, you can get to Route 3 using 3A, but it
will take longer.
This part of
Route 3A in Marshfield north of Route 139 was recently reconstructed and
received new signage, such as this North 3A reassurance marker.
One of the signs
not updated was this Guide/Paddle sign at the intersection with Ferry
Street. Humarock is a coastal neighborhood of Marshfield.
Another new North
Route 3A reassurance marker heading toward the border with Scituate.
Heading across
the latest iteration of the North River bridge that is the border
between Marshfield and Scituate. The bridge was built in the 2000s.
New Junction
Route 123 trailblazer in Scituate.
Guide/Paddle
signage in the roundabout at the intersections of Routes 3A and 123. The
Scituate sign points to Country Way, the original Coastal Route, and
original alignment of Route 3A until 1932 when Justice Cushing Way was
built as a bypass between Scituate and Hingham.
Additional
signage in the roundabout which marks the eastern terminus of Route 123.
A typical North
Route 3A reassurance marker in Scituate.
Except for one of
the several on wide 3-digit shields near Scituate High School.
An older North
Route 3A reassurance marker in the next town to the north, Cohasset.
A rather old
Junction Route 228 trailblazer in Hingham. This dates back to the 1980s
and was not replaced, unlike shields heading south, during the recent
Division 5 sign replacement project (perhaps it wasn't spotted among the
plant growth).
Guide/Paddle
signage at the Route 3A/228 intersection. There currently is no signage
for 228 South, the small paddle sign disappeared a few years ago and has
not been replaced. Prior to the building of Chief Justice Cushing
Highway in 1932 this was a concurrency between Routes 128 and 3A on East
Street which ran between Summer Street, to the left, and Hull Street, to
the right.
3. Signs along
the Route 106 corridor from Kingston to Bridgewater from May 2018:
Here's some photos of route beginnings clustered around Route 3A and 106
in the Kingston Area.
The first of two guide signs for the beginning of Route 106 on Route 3A
North.
Notice the second smaller sign for Route 27, which begins about a mile
further west on 106. If its that important to sign, wouldn't it be better
to just extend 27 to 3A?
Speaking of Route 27, here's the first guide/paddle sign for the
beginning of Route 27 North.
The intersection only features trailblazers. I would prefer two-digit
routes to take precedence and instead would have Route 106 begin here with
27 beginning at 3A.
A few miles west, and over the border with Plympton, is the beginning of
MA 36 North, a short route apparently deserving of less than standard
quality paddle signs.
Further west in Halifax is the beginning of Route 105 South.
The second sign has an unusual number font.
Here's the end of Route 104 East at Route 106 further to west in East
Bridgewater:
And a photo of the Route 106 and 28 intersection in Bridgewater:
Here's a couple of signs from the intersection of Whiting Street (MA
53), Derby Street (Formerly MA 128 and also 228 at least to the 1990s) and
Gardner Street in Hingham. A closeup of a Mass. Guide (aka Paddle) Sign
recently updated with new text:
The sign used to read North MA 228 to Route 3, South Weymouth. It was
one of 3 green signs put up between 1988 and 1993 to mark the split of 228
from 53. The first sign actually read South MA 228. In the spring of 2014
the South 228 sign was removed and the two remaining were greened out with
the new text added. MassDOT had apparently realized that 228 hasn't been
officially routed along Derby Street for at least 15 years. Still, the
route signs, put up around the same time, were not removed. In December
2016, a contract was let to replace signage in District 5, which includes
Hingham, interestingly, the contract calls for replacing the route signs
at the intersection, including the 228 shields. Apparently, the project
engineer was not aware they are not needed, not the town which apparently
approved their installation. Unfortunately, no one pointed out the error
and the signs were installed in June 2017. Here are photos showing the new
signs and those that they replaced. First, the North MA 228 trailblazer on
MA 53 South approaching Derby Street, the back of the sign above is
in the center of the photo:
The previous
sign:
If you look closely, you'll notice the directional banner had been
updated to specifications in the 2009 MUTCD even though the shield dates
from the 1980s, and has been wrong for at least 15 years.
Here's a closeup of the signs that follow on MA 53 South, incredibly the
sign replacement contract installed new shields without replacing the
support post. Later, in September 2019, this sign was taken down when the
surrounding sidewalk was removed for a widening project:
However, the
signs were put back up in late September, nailed to the nearby telephone
pole (which will be removed shortly), in a different order:
Here's the
previous shields on the same post:
The shields above date from the 1980's,
as does the rusting sign post, the South directional banner is at least
10 years older.
The new North 228 trailblazer on Route 53 North prior to Derby Street,
with the corrected green guide sign in the distance. This was taken down
during the intersection reconstruction project that started in August
2019, however it was later put back up attached to the telephone pole seen
in front of it:
The North Route 228 reassurance marker on Derby Street beyond the
intersection, as well as trailblazers for Routes 53 North on Derby Street
heading toward the intersection have not been replaced as of June 24. The
South MA 53/228 trailblazer, hidden by leaves, was replaced. Both sign
assemblies were taken down during the widening and reconstruction of the
Derby Street/Whiting Street/Gardner intersection in the fall of 2019:
Here's the signage on Route 53 South approaching Queen Anne's corner
with the correct information about Route 228:
Meanwhile, signage that could be replaced, like here at the corner of
Main and Central Streets in Hingham, was not replaced:
A correct replacement shield on Route 53 after Cushing Street in
Hingham, the next intersection north on 53 from the photo above:
And a correct Route 228 on Main Street in Hingham just north of the
Cushing and South Pleasant Street intersection:
This Route 228 sign put up earlier in the week is missing a right arrow
because this is on Route 3A South approaching the Route 228 intersection:
Here's a new Route 3A North reassurance marker put up on Otis Street at
Hingham Harbor. The reassurance marker that it replaced was less than 10
years old. The older shield though was smaller with one post. Did someone
request a larger shield for this location?
Seeing double in Queen Anne's Corner:
When the intersection of Routes 53 and 228, known locally as Queen
Anne's corner, at the border of Norwell and Hingham was reconstructed
around 2010 new signage was put in place but most of the old signage was
not removed. This left this curious situation with 2 Junction 53 signs on
228 North ahead of the intersection:
In 2017, the contractor for the Retroflective Sign Update contract
removed the old sign in the back, but replaced it with a new assembly:
Here's the new End Route 53 sign at the intersection with Route
3A/Southern Artery in Quincy, photo taken in November 2019:
Here's the former End Route 53 sign seen from the intersection of the
Southern Artery and Washington Street (Route 3A) in Quincy taken in April
2016. Historically, until about 1960, this was the intersection of Routes
3, 3A and 135:
E. Sign Goofs
This goof has
been around for a few years on Hancock Street in Quincy Center. The
arrows are correct, if not confusing, as you can get to 3A either going
straight of right:
This new guide
sign appeared with the completion of the multi-year project
rehabilitating the Longfellow Bridge between Boston and and Cambridge
which is part of Route 3 in the summer of 2019. As you see the eastern
part of Memorial Drive has been upgraded:
This sign
appeared in Quincy at the corner of Furnace Brook Parkway and Adams
Street in June 2017. While technically correct, if you turn left you
will eventually get to I-93 South which takes you to the beginning of
Route 128 in Canton, this sign replaced an older smaller To 128 sign
that dated to the time that route ended in Braintree (before 1989). This
should say 'To I-93' or 'To I-93/US 1':
Once this photo
was posted on Facebook and on AARoads.com Forum, a MassDOT sign engineer
saw it and asked it be changed to 'To I-93', this change was made on
June 23:
Here's a couple
goofs found near the Route 58 interchange with US 44 in Carver. First
heading southbound:
Apparently they
had some extra shields in New Jersey or Delaware.
Turning around
and heading back toward US 44, drivers see this pair of relatively new
guide signs:
Someone forgot to
check whether there is a MA 44. This same error is also at the signs at
the intersection ahead:
NEW-Beyond the US
44 interchange there is also a circle 58 sign as well:
Earlier, from
10/30/16 showing a little mix up in a guide sign on Route 30 East in
Weston:
From 10/16/16:
This second US 3 shield has appeared on Route 3 South in Duxbury, after
the first Route 3A Exit, however it was changed to a MA 3 shield in late
November:
The previous shield which has been US 3 for several years was also
replaced at the same time:
Here's a new Exit sign that has appeared
along Soldiers Field Road westbound in Boston for the Harvard Square
Exit in July 2014:
It replaced a former green sign with
similar information. Is Harvard Square so much of an attraction that it
deserves a brown sign now?
A Fixed Sign Goof Along Forbes Road in
Braintree. Look at these 2 official MassDOT Guide Signs as they appeared
in June 2013:
Both US shields seem to originally had a 6 in them, then overwritten
with 3. They are getting warmer, I guess.
Here's what was on the back of the first sign:
These lead to the intersection between Forbes Rd, Granite Ave. (MA 37)
and the first South Shore Plaza access Road. The Guide signs there are
older and indicate a turn left onto Granite Street or take MA 37 to the
right.
Update
11/24: Looks like someone noticed the error, and the signs were fixed.
Here's the new version of the second sign above:
Here's a New and Correct Guide Sign in Boston. Part of the I-93 Signing
Project. This is at the on-ramp from Neponset Circle to the Southeast
Expressway Northbound:
From August 2013 (Updated in April 2014):
Or Not ; That is the Question...Apparently
Not
Starting
in the Spring of 2013 new routes signs started appearing throughout
Boston, some along their designated routes and intersecting roadways
throughout the city, and some not. During the summer, for example, new
Route 2A signs were put up along Massachusetts Avenue in Boston east
of where that route has officially ended, at Route 2,
Commonwealth Avenue.
Here's
an example of one of the signs along Mass Ave headed toward the Boston
Medical Center Area just beyond Tremont Street:
And
here's one headed the other direction...
This
one is between Columbus Avenue (MA 28) and Huntington Ave (MA 9). Both
photos taken in early September 2013. Both of these signs are more
than 1/2 mile East from Commonwealth/Route 2. The other thing wrong
with these signs are the directional banners, they are 180 degrees
off. East 2A should be West, and vice versa. The same problem occurs
with all the other signs put up at the same time in the area...
This
sign is further west along Mass Ave between Huntington Avenue and
Boylston Street by the Christian Science Church Headquarters.
The
wrong directions also apply to signs on intersecting roadways. Here
are the signs along Tremont Street at Mass Ave.:
Wrong
directional banners are also a problem with other route signs put up at
the same time:
This
is a Route 28 West Sign on Tremont St prior to the Route 2A signs seen
above. First of all, MA 28 runs along Columbus Avenue one block to the
west, and second, it is a north/south route. Curiously, the Route 28
signs put up along Mass Ave are correct. Here's one approaching
Columbus Ave from the west...
However,
headed on Columbus Ave, you again see directionally challenged Route
2A signs...
To
head toward Cambridge and points west you must follow the signs for
Route 2A East.
Curiously
though two blocks east on Mass Ave at Huntington Ave (MA 9) there is no
Route 2A signage and the new Route 9 signage is correct:
A week later I
checked out the signage at the still official end of Route 2A at the
intersection of Mass Ave and Commonwealth Ave (Route 2)...
While
there are no new Route 2A shields at this intersection, a couple new
Mass. Guide Signs (MGSs) had been place along the ramp from
Commonwealth Ave (Route 2) East to Mass. Ave.:
There
is no matching Route 2A East Guide Sign to Imply the Route has been
extended East. There is also a new smaller guide sign for Route 2A
along Commonwealth at the off-ramp:
Though
the Guide Signs are correct, this does not extend to the new route
markers in the area. The first Route 2A signage on what its official
route west of Mass Ave has the same problem as the others, a wrong
directional banner:
That
should be west. Also a new sign was put up east of Commonwealth at the
Mass Ave intersection with Boylston Street. Only one direction here, but
its the wrong one. If you want to go to Cambridge you need to turn left:
This
sign was placed in July and was accompanied by a 'To I-90 West' sign and
a straight arrow...
The
direction is correct, and technically the arrow is to. If you go
straight you will get to Copley Square and can access West I-90 there.
But it would be easier simply to take a left, go a block and make a
left on the I-90 ramp along Mass Ave. And this is not the only error
here. Approaching Beacon Street on MA 2A West, a couple blocks away
from Commonwealth Ave., you see another West Route 2 Sign:
This
is at the corner of Mass Ave and Beacon St. If you do turn here, you
will eventually get to Route 2 in Kenmore Square.
Not
that all the signs in this area are wrong....
This
'To MA 2' signage is between the I-90 West ramp and Commonwealth Avenue.
And here are the of signs at what is the official End of MA 2A East at the
intersection with Commonwealth Ave...
The
Guide signs are an old design and appear to be a few years old. the route
shields, however, are of recent vintage. These new signs help establish
that Route 2 is not going anywhere, so if Route 2A is to end at its
parent, it's official route has not been extended.
And, some more
photos taken on Thanksgiving morning...
So, what is going
on here?
In a later post
to AARoads Forum, poster Roadman, a MassDOT sign engineer, said he spoke
to a colleague in the District 6 Office in Boston about the Route 2A and
other recent signage. The colleague denied that MassDOT was responsible
for the signs, nor could he find anyone working for the City of Boston
to take credit either.(1) The Boston official suggested the work was by
an 'unknown organization.' However, a road trip I took on Thanksgiving
morning documenting the problems with many of the new signs pointed to evidence suggesting
it must be a city project. The signs appear in locations overseen by two
different state agencies which would create a problem in placing some of
them, if the state had done it. As of the end of 2013 nothing had been
done to fix or take down any problems signs. Here's the blog
entry from that November trip.
Signs Eventually to Be Fixed by Boston
Transportation Dept. (UPDATE 4/6/14):
On February 26,
2014, a Boston TV station, Fox 25, aired this
'undercover report' detailing the problem Route 2A and others
signs documented above and in the blog post. Again MassDOT denied it had
anything to do with it, however, Boston Transportation officials were
now ready to blame a contractor, Jacobs Engineering, for whom the city
had hired, for putting up the problem signs. The Boston officials, even
the new mayor, said they were embarrassed that not only had they
approved the wrong contract drawings, but that they had not noticed the
signs were wrong until the reporter showed them his report (from the BTD
response above, this seems to be stretching the truth). Officials
indicated they were moving quickly to fix the signs and possibly seek to
get some money back from Jacobs. In March, BTD employees fixed the MA 2A
signs by rearranging the banners, only to be told, that by someone at
MassDOT that the signs should not be there at all, since the route ends
at Comm Ave. They then, according to This
Updated Report from Fox 25, went out and removed most of the
incorrect 2A markers. The only one left, apparently, is the one below
between Symphony Hall and Boylston St (see above) where the directional
banner was replaced by a 'To' banner:
While this is now
'correct' technically, Mass Ave crosses I-90 and MA 2 before 2A, so
shouldn't they have 'To' markers too? They also fixed the signs featured
in the Fox 25 report with the opposite arrowed West 2A markers within a
few feet of each other. This was fixed by replacing the directional
banner with 'Jct' and, removing the arrow (sorry for hard to see, late
evening photo):
As of early April
there are still mistaken signs elsewhere in Boston. Here, along Comm Ave
west of Kenmore Square, they have extended MA 30 from its end in
Brighton:
However, to show
you not all the route signs installed by Jacobs were wrong, here are the
signs approaching Columbus Avenue on Mass Ave heading west as of April
2014:
And here are some
of the signs installed at the intersection of Comm Ave and Charlesgate
East near Kenmore Square:
One of the
correctly placed MA 2A signs can be sign on the right side of the photo.
Check Out My Other Photo Pages:
Notes:
(1)
http://www.aaroads.com/forum/index.php?topic=10141.msg246192#msg246192
Posted 9/10/13
*CCROG Memo To: Transportation Committee, From: Roger Krahn, Principal
Transportation Engineer/ Planner, Date: September 13, 2019
Subject: Interchange Exit Renumbering. Downloaded from:
http://crcog.org/wp-content/uploads/2018/12/Memo-2019-09-13-Exit-Renumbering.pdf,
Oct. 24, 2019.
Copyright (c) Robert H. Malme 2015-2019