NC 140 shield image by wikimediaWilmington Bypass

First Section Opened: 2005

Full Completion Date: Summer 2018


HIGHWAY STATUS

I-40 to NC 133 Section Opened: August 2005

NC 133 to US 421/ I-40 to US 17 Sections Opened: June 30, 2006

US 17 to US 74/76 Opened:  September 2014 (as NC 140)

US 421 to US 74/76:   Under Construction, Completion Date: June 2018




The Wilmington Bypass, a planned 25-mile freeway to run from US 17 near Scotts Hill westward over to I-40 then further west to US 74-76 then south to US 17 near the town of Town Creek is currently signed as Interstate 140 along part of the western half of its route, signed NC 140 over its southern most completed section, and designated NC 140 along its eastern half. The following map showed the completed sections of the route in 2006:

Image of Map of Wilmington showing route of opened portion of I-140













Map courtesy of Wilmingtontoday.com

History of the Wilmington Bypass


Four different construction projects have been undertaken to build nearly 18 miles of the Bypass route currently open from Scotts Hill to US 421 and from US 74/76 to US 17. Work began on two projects covering the 6.5 mile I-140 section from I-40 to US 421 in mid-2001. The three-mile section from I-40 to Castle Hayne Road (NC 133) was completed first, with the roadway opened to traffic on August 22, 2005.1 The 3.5 mile section from NC 133 to US 421, including a bridge over the Cape Fear River (named for former Wilmington Mayor Dan Cameron) was opened to traffic on June 30, 2006.2 Construction on the 5 mile section east of I-40, signed as US 17 only, and known as the John J. Burney Jr. Freeway, was started in late 2003 and this section was also opened to traffic on June 30, 2006.2,3 Interchanges along the I-140 section are for I-40, NC 133 and US 421. When the road opened these interchanges did not have exit numbers, these were added in spring or summer of 2007.(An exit list is below.)

Work on the next two sections from US 421 to US 74-76, approximately 7 miles, was originally scheduled to start in 2009,5  but this segment's construction was delayed until 2014. Instead what was to be the final section, approximately 5 miles from US 74-76 to US 17 near its intersection with NC 87, became the fourth segment to be constructed. Funded through federal stimulus moneys, work began under a design-build contract in late March 2010 (for more details, see below)6 and was completed in September 2014.7

A future I-140 interchange is planned for Blue Clay Road but is not planned to be built until around 2024. This will take traffic to the Wilmington International Airport. An additional exit is planned east of I-40 for the planned Military Cutoff Road Extension, which may become part of a planned new section of US 17 running north of Scotts Hill.8

Here's the official NCDOT timetable for the construction of the Western Portion of the Wilmington Bypass12:

Segment Location Length Start Date Completion Date
A NC 87 SOUTH OF BISHOP TO US 74/US 76 EAST OF MALMO 5.3 miles 2010 September 2014
BA US 74/US 76 EAST OF MALMO TO SR 1430 (CEDAR HILL ROAD) 3.9 miles 2013 June 2018
BB (CEDAR HILL ROAD) TO WEST OF US 421 NORTH OF WILMINGTON 3.7 miles 2013 April 2018
C WEST OF US 421 TO EAST OF I-40 7.1 miles 2001 June 2006




Route Numbering History


The Wilmington Bypass was first proposed as a bypass route for US 17. The route was designed to take through traffic from the crowded Wilmington streets and reroute it around the city. When the route was completed from Scotts Hill to US 421 in 2006, the segment west of I-40 was signed a I-140 and, even though the route was not make it back to the original alignment of US 17 until after 20179, the entire route on both sides of I-40 was designated US 17, with US 17 then routed south on US 421 to its existing alignment. The former US 17 through Wilmington became US 17 Business. Truck US 17, signed along streets in downtown Wilmington, was decommissioned.5 However, in 2014 NCDOT reversed course and proposed that US 17 be re-routed through Wilmington along its old path, with the exception of using Military Cutoff Road and Oleander Drive to make it back to its original crossing over the Cape Fear River Memorial Bridge. The reason stated by NCDOT was that the amount of traffic using Military Cutoff Road justified a route designation. This proposal was endorsed by the region's Transportation Advisory Committee in August 2014.9 NCDOT submitted this request to AASHTO's US Route Numbering Committee which approved the relocation on May 15, 2015.10 Meanwhile, NCDOT designated the entire Bypass route, including the section signed as I-140, as NC 140 on January 14, 2015 citing their wish to have the entire route designated as Interstate 140 in the future.11 The FHWA granted the interstate designation for the western Wilmington Bypass route on May 31, 2003, it is unknown at this time when NCDOT will apply for the remainder to become I-140, or when US 17 signage will be removed. It may be no signage will change until the entire Bypass is complete.12 A proposed Wilmington end-point for I-74 (and a possible spur of I-74, see More about I-74 Here) would meet I-140 where it would intersect the existing US 74-76 freeway.13

Wilmington Bypass and US 74/76 Videos



Travel over the opened section of the Wilmington Bypass on this Video Courtesy of J. Austin Carter Taken in March 2013 (Best using Windows Media Player).


Continue on US 74/US 76 in Brunswick County and check out construction of the next segment of the Wilmington Bypass (and the possible future path of I-74) on this Video Also Courtesy of J. Austin Carter Taken in January 2013 (Best using Windows Media Player).

Photos of I-140 signage (Hover over for Larger Image)



From Section Under Construction in March 2013, courtesy of J. Austin Carter:

Photo of future I-140 roadway near interchange with US 17, by J. Austin 
Carter, March 2013
At the future southern end of I-140 at US 17 near Leland, Looking north along roadbed. Photo courtesy of J. Austin Carter. (3/26/2013)


Photo of Future I-140 roadway near interchange with US 17, by J. Austin 
Carter, March 2013
At the future southern end of I-140 at US 17 near Leland, Looking southbend along roadbed back toward future US 17 interchange. Photo courtesy of J. Austin Carter. (3/26/2013)


Photo of Current I-140 construction near interchange with US 17 at NC 87, by 
J. Austin Carter, March 2013
At the future southern end of I-140 along US 17 near Leland, Looking at construction from US 17 South. Photo courtesy of J. Austin Carter. (3/26/2013)


Photo of Future I-140 On-ramp Progress from US 17 North, by J. Austin 
Carter, March 2013
This is the future I-140 on-ramp from US 17 near Leland. Photo courtesy of J. Austin Carter. (3/26/2013)


Photo of posts for future I-140 exit sign, 1 mile from interchange with US 74/
76 west of Wilmington, by J. Austin Carter, March 2013


From the current eastbound lanes of US 74/76 showing posts for future 1 mile advance sign for I-140 . Photo courtesy of J. Austin Carter. (3/26/2013)


Photos from Open Segment of I-140 Taken in 2006 and 2007

Photo of exit signage for I-140 at interchange with NC 133, July 2006
Along NC 133, Castle Hayne Road, nearing the I-140 interchange, July 2006


Photo of exit signage for NC 133 interchange along West I-40 near Wilmington, May 
2006
Photo of exit signage for the NC 133 interchange along West I-140, May 2006. Since then exit numbers have been added, this is now Exit 18.


Photo of signage at current end of I-140 at US 421, July 2006. Courtesy of 
Adam Prince
Here's signage at the current end of I-140 at US 421, July 2006. Photo courtesy of Adam Prince.


Photo of Begin East I-140 sign approaching Dan Cameron Bridge in 
Nov. 2007 near Wilmington, Photo courtesy of John Meisenhelder
Here's a Begin I-140 sign in the distance as you start crossing the Dan Cameron Bridge going east. Photo courtesy of Jon Meisenhelder.


Photo of End East I-140 sign approaching I-40 interchange in Nov. 2007 near 
Wilmington, Photo courtesy of John Meisenhelder
And since all things that begin must end, here's the eastbound End I-140 sign at I-40. Photo courtesy of John Meisenhelder, Nov. 2007.


Photo of I-140 milemarker Mile 16 sign in Nov. 2007 near Wilmington, 
Photo courtesy of John Meisenhelder
This is one of the I-140 East mile markers, Mile 16. Photo courtesy of John Meisenhelder,Nov. 2007.


Photo of overhead signage at eastern end of US 17 Wilmington Bypass, July 2006
Here's the signage at the start of the Loop in Scott's Hill that reflected NCDOT's initial decision to route US 17 onto, but leave I-140 off of, the eastern half of the Wilmington Bypass. (7/06)


An I-140 Extension?



The NCDOT Strategic Highway Corridor map of the Wilmington area shows I-140 being extended 9.5 miles over the proposed Cape Fear Skyway south and east back over the Cape Fear River to US 421. (See map below (16)). This is NCTA's preferred route for the Skyway, one of several proposed projects of the North Carolina Turnpike Authority (NCTA) and would be constructed as a toll highway. The preferred route of the Skyway bridge would run from Carolina Beach Road at Independence Boulevard south of Wilmington over the Cape Fear River. It would then connect to US 17 through an 8-mile-long extension of Interstate 140 from it's current planned end near Town Creek. This alignment has not been finalized (see below), however, and other routes do not have the toll highway meeting I-140. The project, if officially approved, is expected to cost between $1 and 1.5 billion and would take five years to build, the earliest construction would start is 2013.(17) A feasibility study completed during the summer of 2008 indicated only about 50% of the construction could be funded by tolls. Additional funding from the state would be needed.(18) More information is available at the official NC Turnpike Authority Cape Fear Skyway Page.

Image of map showing one of the proposed routes for the Cape Fear Skyway 
Bridge toll highway, from NC Turnpike Authority 

Changes Made in the Final Sections to be Built:



NCDOT announced in July 2009 that federal stimulus funds would help start further construction on I-140/US 17. The next section to be constructed though was not going to be from US 421 to US 74/76, Segment "B", but the section between US 74/76 and US 17 near NC 87, Segment "A''. This is a design/build construction project which began in March 2010. This segment was more 'shovel ready' and able to receive stimulus funds. The project was completed in September 2014. Segment "B" was complicated by another water crossing and later, environmental litigation. Work finally began in the Fall of 2014, meaning   there will be a gap in the route for at least a couple more years. (19) The entire route, though officially not complete until the summer of 2018, could open as early as late 2017.

Not NCDOT's First I-140 Proposal



This is not the first route NCDOT proposed as I-140. In 1999, officials in Sanford wanted the newly completed US 1 freeway from Raleigh to their city designated an interstate to help attract further business. NCDOT applied to the FHWA to have the freeway designated as Interstate 140. The FHWA rejected the designation, however, saying Sanford was not a large enough urban area to warrant its own interstate highway. Perhaps some day if all of US 1 is made a freeway between I-40 in Raleigh and I-73/74 in Rockingham (as proposed in the NCDOT Strategic Highway Corridors plan) then someone may suggest revisiting a US 1 interstate designation proposal.

I-140/NC 140 Exit List (20):



Exit 1 [Left Exit]

 US 17 shield image from wikimedia North

Wilmington

Exit 5

US 74 shield image from wikimedia US 76 shield image from wikimedia

Leland

[Portion Under Construction]

Exit 14

US 421 shield image from wikimedia (US 17 shield image from wikimedia South)
Wilmington
Myrtle Beach

Exit 18

  NC 133 shield image from wikimedia
Castle Hayne

Exit 20A

I-40 shield image from Shields Up!
Wilmington
Carolina Beach

Exit 20B

I-40 shield image from Shields Up!
Benson
Raleigh