I-295 Page Banner Image


Image of NC 295 shield, from Shields Up!

Fayetteville Outer Loop

First Section Opened: 2003

Full Completion Date: 2026

Completed Sections:

River Road to US 401: Opened June 2003

I-95 to River Road: Opened July 2005

Murchison Road to Bragg Blvd:
Opened August 2014

US 401 to Murchison Road: Opened August 11, 2016

Bragg Blvd to All-American Freeway: Opened-Dec. 2, 2016

All-American Freeway to Cliffdale Road: Opened-Nov. 26, 2019

Cliffdale Road to US 401: Opened August 19, 2020

Parkton Road to Black Bridge Road: Opened-November 21, 2022

LATEST-Camden Road to I-95 South-July 10, 2024

Click Here For Photos (NEW 8/28/24)

Click Here for Sign Plans (Updated 4/20/22)

Current Sections Under Construction:

Loop to I-95 North, I-95 to Loop, to be completed-Summer 2025

Raeford Road to Camden Road-Awarded July 2022, Completion-Spring 2026

Go to I-295 Exit List

History of the Fayetteville Outer Loop

A western bypass of Fayetteville has been in the planning stages for decades. The 36-mile Outer Loop route was planned both as a vehicle bypass of Fayetteville and as a direct interstate link to Fort Bragg for military and civilian transportation.1 The completed freeway would run from I-95 at its current intersection with US 13 to the west and south of Fayetteville reconnecting with I-95 north of St. Pauls in Robeson County. The route was officially designated as Interstate 295 in 2019.

Construction on the Loop began in 2001. Currently, in February 2023, almost 26 miles are open to traffic. The latest section to open is a short 2-mile stretch from Parkton Road and Black Bridge Road at the southern end of he Loop, separated from the rest. Previously, a section from Cliffdale Road to Raeford Road (US 401) opened on August 19, 20202 less than a year from the section from the All-American Freeway to Cliffdale Road on November 26, 2019. NCDOT announced funding of $105 million for the project in September 2012 and the contract was put out to bid in August 2014. Work started on October 24, 2014. The segment has two interchanges with Reilly Road near a Fort Bragg gate at Canopy Lane in addition to that at Cliffdale Road and was originally to be completed in October 2018, then March 2019.3 The opening of the segment from US 401 to NC 211/ Murchison Road on August 16, 2016 closed what was two disconnected segments. The older eastern, and longest, segment, signed until 2014 as Future Interstate 295, consists of the first section of the Loop completed in June 2003, which ran three miles from US 401 (Ramsay Street) across the Cape Fear River to River Road4 and a second section, about 4 miles, connecting I-95 to River Road that was completed in July 2005. A western segment, 1 1/2 mile route designated NC 24/27, taking those routes from Bragg Blvd (where NC 24/27 intersects the Loop from the south) to Murchison Road (NC 210), opened in the summer of 2014. A 1/2 mile segment to continue the highway west to the All-American Freeway was finished on December 2, 2016. In late 2014, NCDOT replaced all the Future I-295 signage in the eastern section with NC 295 signs (see photos below) and the rest of the route when opened in 2016 was also signed as NC 295. NCDOT sought in 2019, and was granted by both AASHTO and the FHWA, permission to sign the completed section as I-295.5 In November 2019, an overhead sign along a new section opened between the All-American Freeway to Cliffdale Road had an I-295 shield, it was then assumed that the rest of the Loop back to I-295 would have its signs changed from NC 295 to I-295 in the not too distant future. According to NCDOT the contractor, Traffic Control Safety Services Inc. of Winston-Salem had until the spring of 2022 to complete the sign upgrades.6 All signs eventually went up as of April 21, 2022. (with a few exceptions, see photos below) This image from City of Fayetteville video shows a new I-295 sign:

Image taken from City of Fayetteville video showing I-295 shield on overhead sign on new All-American 
                                        Freeway to Cliffdale Road section just prior to its opening on Nov. 26, 2019

The remaining segments west and south of Yadkin Road back to I-95 near St. Pauls were originally not funded, but in December 2014 it was announced that the latest NCDOT STIP would fund projects to complete the entire Loop, the first of these projects will start in 2016, the last in 2021, and the whole Loop could be complete by 2025.5 In December 2015 then NC Governor McCrory announced changes to the state budget that would allow more money to be dedicated to transportation projects. Under the plan, the last segments of the Outer Loop would be accelerated a year to start construction in 2020, the Loop would be completed by 2023 under the new timetable, which was approved by the NCDOT Board in January 2016.7 The latest project to start is the southern most segment from I-95 to Camden Road, west of Fayetteville, construction started in January 2018 and was completed, at least to I-95 South more than 6 years later in July 2024. The last segment to be constructed, from US 401 to Camden Road, was to be let in July 2020 with work scheduled to be completed by 2024, however the letting date was first pushed back to February 2021 in the fall of 2019, then due to financial constraints caused by the COVID-19 virus was dropped from the tentative 13-Month Letting list in April 2020.8 This meant the project did not start until August 2022 and that the entire Loop now won't be finished now until at least mid-2026, a year later than the original date cited in 2014. The section between Strickland Bridge Road and I-95 will be signed as NC 295 until the last segment is completed. Each of these projects are discussed in greater detail below in the Current and Future Construction section.

Here was the official NCDOT schedule for the projects to complete the I-295 Fayetteville Outer Loop between Fort Bragg and I-95 in Robeson County from the 2020-2029 STIP and later NCDOT press releases in 2020. Since this was published the completion dates for Segments AA and AB have been delayed until July 2024 and BA and BB are now set for July 2026:

Segment Location Cost ($Mil) Start date  Completion date
DA East of SR 1415 (Clearwater Blvd) to West of NC 24/27 (Bragg Blvd) - COMPLETED   54.4 Oct. 2014 July 2015
CB South of SR 1400 (Cliffdale Rd) to East of SR 1415 (Clearwater Blvd) - UNDER CONSTRUCTION 125.5 Oct. 2014 Oct. 2018
CA South of US 401 to South of SR 1400 (Cliffdale Rd) - UNDER CONSTRUCTION   14.8 2016 March 2021
BB South of SR 1104 (Strickland Bridge Rd) to South of US 401 (ROW in Progress)   45.0 Aug. 2018 2022
BA South of SR 1003 (Camden Rd) to South of SR 1104 (Strickland Bridge Rd) (ROW in Progress)   60.9 Aug. 2018 2022
AB South of SR 1118 (Parkton Rd) to South of SR 1003 (Camden Rd) - UNDER CONSTRUCTION 119.5 Jan. 2018 July 2021
AA I-95 in Robeson County to South of SR 1118 (Parkton Rd) in Cumberland County - UNDER CON.  48.3 Jan. 2018 July 2021

Total Cost for 22.5 Miles: 570.4

Here's the earlier official NCDOT schedule for the now completed section of the Fayetteville Outer Loop between Fort Bragg and I-95/US 13:8

Segment Location Length Start date  Completion date
B West of NC 24-87 (Bragg Blvd) to East of NC 210 (Murchison Rd) 1.0 Miles June 2009 March 2013
BC East of NC 210 (Murchison Rd) to 1.1 Miles East of NC 210 1.1 Miles March 2011 July 2014
BB West of NC 24-87 (Bragg Blvd) to East of NC 210 (Murchison Rd)-Paving of Sections B and BC 2.1 Miles Jan. 2013 August 2014
CA 1.1 Miles East of NC 210 to East of SR 1600 (McArthur Rd) 2.0 Miles March 2011 July 2014
CB East of SR 1600 (McArthur Rd) to West of US 401 2.1 Miles March 2011 July 2014
CC 1.1 Miles East of NC 210 to to West of US 401-Paving Sections CA and CB-UNDER CONSTRUCTION 4.1 Miles March 2014 August 2016
DA West of US 401 to East of SR 1714 (River Road) 3.3 Miles June 2000 June 2003
DB East of SR 1714 (River Rd) to US 13/I-95 4.8 Miles August 2003 July 2005

Videos driving the open sections of the Outer Loop (New 1/16/22)

Construction Tour by Gregarious Drivers of Greensboro, Part 1    Part 2 (New 10/20/21)

Filmed by Roadway Wiz during the summer of 2021 (new):

Exits 12 to 21 Northbound      Exits 21 to 12 Southbound

Exits 21 to 28 Northbound      Exits 28 to 21 Southbound

Exits 28 to 34 Northbound      Exits 34 to 28 Southbound

Construction photos along the future sections of the Outer Loop (2019-)

NEW! Photos taken of new signage at southern I-295 interchange with I-95 North by David Johnson, August 2024

Image of new 1 mile advance sign for I-295 North on I-95, by David Johnson,August 2024

A new 1 Mile advance sign for the, for now, NC 295 North exit. The ramp is not open, so this sign should be covered up.

Image of pair of new arrow-per-lane signs for NC 295 North on yet to
       open ramp from I-95 North in St. Pauls, by David Johnson,August 2024

First of a pair if arrow-per-lane signs on the unopened ramp from I-95 North to the NC 295 North exit.Since they plan to open the ramp next year, before the Loop is completed, they will have to cover over the text for Fort Liberty and Pope AAF.

NCDOT photo of opened southern end of the Fayetteville Outer Loop, July 10, 2024

Image of overhead ramp signs at the southern end of the Future I-295/Fayetteville Outer 
                                               Loop at I-95 in St. Pauls, NCDOT, July 2024

Video screen grabs from I-95 video by  made in early May 2024:

Image of nearly completed ramp from I-95 North to NC 295 (Future I-295) North in St. Pauls, 
       screen grab from Mileage Mike Travels video, May 2024View from I-95 North of the future ramp to NC 295 North near completion as seen from I-95 North.


Image of bridge over I-95 North for NC 295 (Future I-295) North ramp in St. Pauls, 
       screen grab from Mileage Mike Travels video, May 2024View of the completed future I-295 Loop bridges from I-95 North.


EARLIER PHOTOS

Photos by David Gallo at the US 401/Raeford Road interchange, January 2024

Image of overhead signage at I-295 interchange with US 401 South with updated Fort Liberty 
        control city, by David Gallo, January 2024I-295 North control city on overhead sign on US 401 South changed to Fort Liberty.


Image of completed I-295 North bridge over US 401 in Fayetteville, by David Gallo, January 
        2024Closeup of completed I-295 North bridge over US 401.


Image of completed I-295 bridge over US 401 in Fayetteville, by David Gallo, January 2024Under the completed US 401 North bridge with the southbound bridge to the right.


Image of future I-295 North ramp to US 401 South in Fayetteville, by David Gallo, January 2024Completed ramp from I-295 North to US 401 South about to head under the bridge on the right.


Image of completed I-295 North ramp for US 401 exit in Fayetteville, by David Gallo, January 2024Looking up the future ramp from I-295 North to US 401, future exit sign gantry already installed.


Image of traffic using ramp to I-295 North from US 401 in Fayetteville, by David Gallo, January 2024Traffic from US 401 using 2-lane ramp to access I-295 North.


Google Maps Street View images along I-95 at both I-295 interchanges, August 2023

New signage due to I-95 widening at north end of I-295:

Image of overhead ramp sign for I-295 South/US 13 North exit on I-95 South in Parkton, Google 
        Maps Street View, August 2023The new overhead exit sign for South I-295/North US 13 on I-95 South. Notice there has been no change to Fort Liberty at that time. Heading in the other direction...


Image of new 1 1/2 Miles advance overhead sign for I-295 South/US 13 North exits on I-95 North in Parkton, Google 
        Maps Street View, August 2023The new 1 1/2 Miles advance sign for the South I-295/North US 13 exit on I-95 North. The sign reflects the completion of a new ramp to I-295 North that has not opened yet.


Image of new 1 Mile advance overhead sign for I-295 South/US 13 North exit on I-95 North in Parkton, Google 
        Maps Street View, August 2023The new 1 Mile advance overhead. Signs in this direction also still refer to Fort Bragg. These signs were put between April and August.


Image of old ramp sign for I-295 South/US 13 North exit on I-95 North in Parkton, Google 
        Maps Street View, August 2023The one remaining old sign lets drivers know there is still only the one ramp for both South I-295 and North US 13 heading northbound. The support for the future sign is behind it.


Image of new gore sign for I-295 South/US 13 North exit on I-95 North in Parkton, Google 
        Maps Street View, August 2023The new gore sign however has the suffix for the future North US 13 only exit.


Image of covered over overhead ramp sign for future I-295 South exit on I-95 North in Parkton, Google 
        Maps Street View, August 2023The future exit sign for the new South I-295 exit is covered up.


Image of overhead ramp sign for I-295 South/US 13 North exit on I-95 South in Parkton, Google 
        Maps Street View, August 2023The connection from I-95 North to the new South I-295 exit ramp is still to be constructed.


Southern Interchange construction, Google Maps Street View images from June 2023:

Image of future I-295 North ramp under construction from I-95 North in St. Pauls, Google 
        Maps Street View, June 2023The future I-295 North ramp leaving from a future widened I-95 North.


Image of future I-295 North ramp under construction from I-95 North in St. Pauls, Google 
        Maps Street View, June 2023A closer look at the construction after the future I-295 North ramp. The conveyor belt across I-95 has been partially disassembled with work complete.


Image of completed bridge to carry future I-295 over I-95 North in St. Pauls, Google 
        Maps Street View, June 2023The future widened I-95 North lanes heading towards the completed future I-295 bridges.


Image of future I-295 bridge over I-95 North in St. Pauls, Google 
        Maps Street View, June 2023A closer look at the future I-295 bridges over I-95 North.


Image of future I-295 North ramp under construction from I-95 South in St. Pauls, Google 
        Maps Street View, June 2023Turning around and approaching the future I-295 North ramp leaving from a future widened I-95 South.


Image of future I-295 North ramp under construction from I-95 South in St. Pauls, Google 
        Maps Street View, June 2023Approaching the future I-295 North ramp from I-95 South. It appears at least 2 new lanes are being built here.


Meanwhile, Google Maps has jumped the gun and shows the southern I-295 interchange as open, here's a screen grab from October 2023:

Google Maps image of open I-295 interchange with I-95 in St. Pauls, October 2023

EARLIER PHOTOS

Images from Google Maps Street View along the new section of NC 295 starting at Parkton Road, March 2023

Image of uncovered and covered NC 295 trailblazers along Parkton Road at southern end of newly 
        opened section to Black Bridge Road, Google Maps Street View, March 2023Pair of NC 295 trailblazers, North uncovered, along Parkton Road approaching recently opened section of Fayetteville Outer Loop north to Black Bridge Road.


Image of North NC 295 trailblazer along Parkton Road at southern end of newly 
        opened section to Black Bridge Road, Google Maps Street View, March 2023North NC 295 trailblazer along Parkton Road approaching roundabout and northbound on-ramp.


Image of North NC 295 trailblazer at northbound on-ramp from Parkton Road to 
        opened section of Fayetteville Outer Loop to Black Bridge Road, Google Maps Street View, March 2023North NC 295 trailblazer at Parkton Road roundabout entrance to northbound on-ramp.


Image of North NC 295 reassurance marker beginning of newly 
        opened section from Parkton Road to Black Bridge Road, Google Maps Street View, March 2023A North NC 295 reassurance marker merging onto the Outer Loop from Parkton Road.


Image of Cumberland County sign along newly opened section of NC 295/Fayetteville Outer Loop from 
        Parkton Road to Black Bridge Road, Google Maps Street View, March 2023The first guide sign after Parkton Road is one indicating entering Cumberland County.


Image of ground mounted 1 mile advance sign for Black Bridge Road exit on newly opened section 
        of NC 295 North/Fayetteville Outer Loop starting at Parkton Road, Google Maps Street View, March 2023The 1 Mile advance sign for the Black Bridge Road exit, Exit 4.


Image of Mile 4 marker along newly opened section of NC 295/Fayetteville Outer Loop from 
        Parkton Road to Black Bridge Road, Google Maps Street View, March 2023The mile markers are temporarily signed for North and South NC 295, for at least 3 more years.


Image of ground mounted exit sign for Black Bridge Road exit on newly opened section 
        of NC 295 North/Fayetteville Outer Loop, Google Maps Street View, March 2023The exit sign for Black Bridge Road with temporary signage indicating all traffic needs to exit.


Image of gore sign for Black Ridge Road at end of newly opened section of NC 295 North/Fayetteville 
        Outer Loop, Google Maps Street View, March 2023The gore sign at the Black Bridge Road exit ramp.


Image of pair of NC 295 trailblazers on Black Bridge Road approaching on-ramp rounabout to newly opened section of NC 295/
        Fayetteville Outer Loop to Parkton Road, Google Maps Street View, March 2023The pair of NC 295 trailblazers on Black Bridge Road, the South one uncovered this time approaching the roundabout and open southbound ramp.


Image of South NC 295 trailblazer approaching on-ramp on Black Bridge Road, Google Maps 
        Street View, March 2023The 1/2 Mile advance sign for Parkton Road is one indicating entering Cumberland County.


Image of Entering Robeson County guide sign along newly opened section of South 
        NC 295/Fayetteville Outer Loop from Black Bridge Road to Parkton Road, Google Maps Street View, March 2023The sign southbound indicating entering Robeson County approaching the current end of South NC 295 at Parkton Road.


Image of a South NC 295 mile marker along
        NC 295/Fayetteville Outer Loop approaching the Parkton Road exit, Google Maps Street View, March 2023A southbound NC 295 mile marker prior to the Parkton Road exit.


Image of ground mounted ramp sign along newly opened section of South 
        NC 295/Fayetteville Outer Loop for the Parkton Road exit, Google Maps Street View, March 2023The Parkton Road exit sign and All Traffic exit signage at the southern end of NC 295.


Image of gore sign for the Parkton Road exit at southern end of newly opened section of South 
        NC 295/Fayetteville Outer Loop, Google Maps Street View, March 2023The gore sign for the Parkton Road exit, but not the last exit sign heading south.


Image of 1 1/4 mile advance sign for the I-95 North exit on southern end of South 
        NC 295/Fayetteville Outer Loop, Google Maps Street View, March 2023There is a 1 1/2 mile advance sign for the I-95 North exit awaiting the opening of the final section beyond Parkton Road


Google Maps images from I-95 showing progress constructing the future interchange with the Fayetteville Outer Loop, February and March 2023

View of future ramp to I-295 North/Fayetteville Outer Loop being constructed from I-95 North in St. Pauls, 
        Google Maps Street View image, March 2023View from I-95 North showing progress in constructing the future I-295 North exit ramp. Notice in the distance that the conveyor built to shift excavated dirt around the interchange has been partially dismantled.


View of completed I-295 North/Fayetteville Outer Loop bridge from I-95 North in St. Pauls, 
        Google Maps Street View image, February 2023View from I-95 North approaching the competed future I-295 North bridges. Turning around...


View of future ramp to I-295 North/Fayetteville Outer Loop being constructed from I-95 South in St. Pauls, 
        Google Maps Street View image, March 2023View from I-95 South of I-295 North exit ramp construction on the other side of the bridge.


Image of Future I-295 North/Fayetteville Outer Loop bridge from I-95 South in St. Pauls, 
        Google Maps Street View image, March 2023View of the completed future I-295 North bridge over I-95 South.


Google Maps Street View images from other intersecting roadways, March 2023:

Image of completed NC 295 (Future I-295) bridge over US 301 in St. Pauls, Google Maps Street 
        View,  March 2023View of the completed NC 295 bridge crossing over US 301 in St. Pauls.


Image of completed NC 295 (Future I-295) bridge over Waldo's Bridge Road, Google Maps Street View, 
                                          March 2023View of completed NC 295 bridge over Waldo's Bridge Road north of the current end of the highway at Black Bridge Road.


Image of construction of Future I-295 Fayetteville Outer Loop from
      future interchange at Camden Road, Google Maps Street View, March 2023View of construction around the future site of the Loop's interchange with Camden Road looking north.


PREVIOUS PHOTOS

Images from Google Maps Street View at the I-295 exit off of I-95, November 2022 to January 2023:

Image of newly placed 2 miles advance overhead sign for I-295/Fayetteville Outer Loop exit on I-95 
       South in Wade, Google Maps Street View, January 2023Newly placed overhead 2 Miles advance overhead sign for I-295/US 13 exit on I-95 South, currently being widened, notice the removal of To US 401 text.


Image of NC 295 trailblazer still in place along ramp from I-95 North to I-295/Fayetteville Outer Loop exit 
       in Wade, Google Maps Street View, December 2022Signs along the ramp from I-95 North still indicate NC 295, not I-295 as of December 2022.


Image of NC 295 trailblazer at the beginning of I-295/Fayetteville Outer Loop South in Wade, Google 
        Maps Street View, December 2022There is also still a NC 295 shield at the end of US 13 approaching the ramp to I-95 South.


Image of overhead sign for I-295/Fayetteville Outer Loop exit off of I-95 South in Wade, Google 
        Maps Street View, November 2022Newly placed overhead sign along ramp to I-295 and US 13 exits from I-95 South, as seen from I-95 North lanes in November 2022.


Images of I-295 signage from Google Maps Street View taken between May 2022 and January 2023, going north to south:

Image of first South I-295 reassurance marker after I-95 interchange, Google Maps Street View, 
        September 2022The first South I-295 reassurance marker after the I-95 interchange.


Image of ground mounted 2 miles advance sign for I-95 exit on I-295 North, Google Maps Street View, 
        September 2022 The 2 miles advance sign on I-295 North for the I-95 exit, the interchange being reconstructed as part of the I-95 widening project between Fayetteville and I-40 in Benson.


Image of first South I-295 reassurance marker after I-95 interchange, Google Maps Street View, 
        September 2022The next exit is River Road one of the original exits.


Image of South I-295 reassurance marker after the River Road exit, Google Maps Street View, 
        September 2022The second South I-295 reassurance marker after the River Road exit, there did not appear to be any headed north.


Image of I-295 trailblazer on River Road, Google Maps Street View, 
        September 2022 A South I-295 trailblazer along River Road, here the To US 401 information remains.


Image of South I-295 trailblazer at River Road, Google Maps Street View, 
        September 2022 The corresponding North I-295 ramp signage on River Road which includes references to I-95 and US 13.


Image of North I-295 reassurance marker after US 401 Lillington interchange, Google Maps Street View, 
        September 2022A North I-295 reassurance marker after the US 401 interchange.


Image of first South I-295 reassurance marker after I-95 interchange, Google Maps Street View, 
        January 2023The US 401 exit sign on I-295 South, the original end of the Loop.


Image of I-295 overhead ramp signage on US 401 North, Google Maps Street View, 
        January 2023 I-295 ramp signage along US 401 North, all signage with Fort Bragg will have to be changed when the name of the base is changed, perhaps later this year.


Image of I-295 overhead ramp signage on US 401 South, Google Maps Street View, 
        January 2023 The I-295 ramp signage now along US 401 South.


Image of South I-295 reassurance marker after US 401 Lillington exit, Google Maps Street View, 
        January 2023 The South I-295 reassurance marker after the US 401 exit.


Image of brown auxiliary sign for McArthur Road exit on I-295 South, Fayetteville Outer Loop, Google Maps Street View, 
        September 2022A brown sign for attractions at the McArthur Road North exit.


Image of overhead signage for McArthur Road exits on I-295 South, Fayetteville Outer Loop, Google Maps Street View, 
        September 2022Overhead signage at the ramp for the McArthur Road North exit.


Image of overhead ramp sign for McArthur Road North exit on I-295 South, Fayetteville Outer Loop, Google Maps Street View, 
        September 2022As overhead sign for attractions at the McArthur Road North exit headed north on I-295.


Image of South I-295 reassurance marker after the McArthur Road interchange, Fayetteville Outer Loop, Google Maps Street View, 
        January 2023The South I-295 reassurance marker after the McArthur Road exits.


Image of South I-295 trailblazer at the Murchison Road interchange, Fayetteville Outer Loop, Google Maps Street View, 
        January 2023This South I-295 trailblazer at the Murchison Road on-ramp is accompanied by ones for NC 24 and 87.


Image of North I-295 ramp sign at the Murchison Road interchange, Fayetteville Outer Loop, Google Maps Street View, 
        January 2023Heading the other way is an overhead sign for the I-295 North ramp.


Image of North I-295 reassurance marker after the Murchison Road interchange, Fayetteville Outer Loop, Google Maps Street View, 
        October 2022The North I-295 reassurance marker after the Murchison Road interchange.


Image of mile marker no longer with I-295 shield at the NC 24/27 Bragg Blvd. interchange, Fayetteville Outer Loop, Google Maps Street View, 
        May 2022Instead of changing all the plain mile markers to ones with I-295 shields, they decided instead to replace the I-295 ones that existed between the Bragg Blvd. and Murchison Road exits with the plain variety, see older photos for previous version.


Image of I-295 shield now on Bragg Blvd to Murchison Road C/D ramp from the northbound Fayetteville Outer Loop, Google Maps Street View, 
        May 2022Overheads along the C/D ramp northbound between Bragg Blvd and Murchison Road now have I-295 shields, here at the Bragg Blvd exit.


Image of I-295 shield now on Bragg Blvd to Murchison Road C/D ramp from the northbound Fayetteville Outer Loop, Google Maps Street View, 
        May 2022Also here approaching the Murchison Road exit.


Image of I-295 shield now at ramp to Murchison Road from the northbound Fayetteville Outer Loop, Google Maps Street View, 
        May 2022Also at the Murchison Road exit which didn't have any shield previously (see older photo, below).


Image of South I-295 trailblazer at the Cliffdale Road on-ramp, Fayetteville Outer Loop, Google Maps Street View, 
        January 2023The South I-295 trailblazer at the Cliffdale Road on-ramp.


Image of North I-295 trailblazer at the Cliffdale Road interchange, Fayetteville Outer Loop, Google Maps Street View, 
        January 2023Heading the other way and the trailblazer at the I-295 North ramp.


EARLIER PHOTOS

Photo by NCDOT showing opened section from Parkton/Leeper Road to Black Bridge Road on November 21, 2022 from Parkton Road bridge:

Image of newly opened section of Fayetteville Outer Loop from Parkton Road 
                                                         to Black Bridge Road, NCDOT, November 2022

Photos taken by LC along the soon to be opened section between Parkton/Leeper Roads and Black Bridge Road on November 6, 2022:

Image of view looking north from Parkton Road bridge over soon to be opened section of 
                                                 Fayetteville Outer Loop to Black Bridge Road, by LC, November 2022Similar to photo above, looking north over nearly completed section of Fayetteville Outer Loop from Parkton Road bridge.


Image of view looking south from Parkton Road bridge over section of 
                                                 Fayetteville Outer Loop to I-95, partially complete, by LC, November 2022Looking south from Parkton Road bridge towards I-95, not to be completed until 2024.


Image of view looking west along Parkton Road to new roundabout and soon to be opened ramp for 
                                                 Fayetteville Outer Loop north to Black Bridge Road, by LC, November 2022Approaching new Parkton Road roundabout at future ramp to the Outer Loop heading south.


Image of view looking east toward roundabout on Parkton Road for soon to be opened off ramp of 
                                                 Fayetteville Outer Loop from Black Bridge Road, by LC, November 2022A closer look heading east on Parkton Road of roundabout for the southbound Outer Loop.


Image of view looking west from Parkton Road roundabout to soon to be opened ramp to 
                                                 Fayetteville Outer Loop north to Black Bridge Road, by LC, November 2022Temporarily blocked ramp to the Fayetteville Outer Loop heading north from Parkton Road.


Image of view looking west along Parkton Road bridge over soon to be opened section of 
                                                 Fayetteville Outer Loop to Black Bridge Road, by LC, November 2022Looking along the new Parkton Road bridge over the soon to be open section of Outer Loop.


Image of view looking east along Parkton Road bridge over soon to be opened section of 
                                                 Fayetteville Outer Loop to Black Bridge Road, by LC, November 2022Looking east along the new Parkton Road bridge.


Image taken along Black Bridge Road approaching new roundabout with ramps for soon to 
        be opened section of Fayetteville Outer Loop to Parkton/Leeper Roads, by LC, November 2022View of Black Bridge Road approaching new roundabout for soon to open ramps for section of Fayetteville Outer Loop headed south to Parkton/Leeper Roads.


Image taken along new Black Bridge Road roundabout toward closed future ramp to 
        section of Fayetteville Outer Loop, by LC, November 2022View of from roundabout of future ramp to Fayetteville Outer Loop.


Image taken along Black Bridge Road bridge looking north to 
        yet to be completed section of Fayetteville Outer Loop to Camden Road, by LC, November 2022Looking north from Black Bridge Road bridge toward incomplete section to Camden Road.


Image taken along Black Bridge Road bridge looking south to soon to
        be opened section of Fayetteville Outer Loop to Parkton/Leeper Roads, by LC, November 2022Now looking south from new Black Bridge Road bridge along soon to open section of the Outer Loop headed south to Parkton/Leeper Roads.


Image taken looking east along Black Bridge Road bridge toward new roundabout with ramps 
        for soon to be opened section of Fayetteville Outer Loop to Parkton/Leeper Roads, by LC, November 2022Looking east along the Black Bridge Road bridge toward one of the new ramp roundabouts.


Image taken looking west along Black Bridge Road bridge toward new roundabout with ramps for soon to 
        be opened section of Fayetteville Outer Loop to Parkton/Leeper Roads, by LC, November 2022Looking west over the Black Bridge Road bridge and new roundabout with the soon to open ramps for section of the Outer Loop headed south.


Image taken of future on-ramp to Black Bridge Road from soon to 
        be opened section of Fayetteville Outer Loop from Parkton/Leeper Roads, by LC, November 2022Road Closed sign in front of on-ramp from the Outer Loop headed north to Black Bridge Road and its new connection to Old Plank Road.


Image taken along Black Bridge Road approaching new roundabout with ramps for soon to 
        be opened section of Fayetteville Outer Loop to Parkton/Leeper Roads, by LC, November 2022View from roundabout at soon to open ramp to Loop headed south to Parkton/Leeper Roads.


Photos taken by Val Melvin of new I-295 signs along US 401 north of Fayetteville on April 21, 2022:

Image of new Junction I-295 trailblazer and guide signs now with I-295 shields on US 401 North near 
       Spring Lake, photo by Val Melvin, April 2022New I-295 shields placed along US 401 prior to I-295 North ramp.


Image of new I-295 shields on overhead signs on US 401 North near 
       Spring Lake, photo by Val Melvin, April 2022New I-295 shields placed along US 401 prior to I-295 North ramp.


Images taken from Google Maps Street View in October 2021

Image of NC 295 still appearing on 2 Miles advance sign for Fayetteville Loop exit on I-95 South 
      (under construction for widening project) in Cumberland County, Google Maps Street View image, October 20212 Miles advance sign for the Fayetteville Loop still with NC 295 shield. I-95 is currently being widened in NC between Fayetteville and I-40 in Benson.


Image of NC 295 still appearing on ramp sign for Fayetteville Loop exit on I-95 South 
      in Cumberland County, Google Maps Street View image, October 2021The exit sign for the Fayetteville Loop also still with NC 295 shield.


Image of new future I-295 South ramp being built from I-95 South 
      in Cumberland County as part of widening project, Google Maps Street View image, October 2021Future I-295 South exit ramp, being built as part of I-95 widening paralleling current ramp with sign still having NC 295 shield.


Image of South NC 295 reassurance marker still standing along Fayetteville Outer Loop after the 
      I-95 exit in Cumberland County, Google Maps Street View image, October 2021The NC 295 South reassurance marker still stands at start of Fayetteville Loop after the I-95 exit.


Image of North NC 295 reassurance marker still standing along Fayetteville Outer Loop north of 
      River Road exit in Cumberland County, Google Maps Street View image, October 2021A NC 295 North reassurance marker still standing after the River Road exit.


Image of mile marker still with North NC 295 shield still standing along Fayetteville Outer Loop prior to 
      the River Road exit in Cumberland County, Google Maps Street View image, October 2021The mile markers also still have NC 295 shields on them north of the Murchison Road exit.


Photos taken heading south from Cliffdale Road to US 401/Raeford Road on August 19, 2020 by David Johnson, First heading south:

Image of 1-mile ground mounted advance sign for Cliffdale Road, no longer with All Traffic Must Exit banner
        on I-295 South in Fayetteville, by David Johnson August 20201-Mile advance sign for Cliffdale Road exit on I-295 South with All Traffic Exit banner now removed.


Image of ground mounted exit sign for Cliffdale Road, no longer with All Traffic Must Exit banner
        on I-295 South in Fayetteville, by David Johnson August 2020Exit sign for Cliffdale Road exit on I-295 South with All Traffic Exit banner also now removed.


Image of new bridge over Cliffdale Road on newly opened section of I-295 South in Fayetteville, by 
        David Johnson August 2020Heading toward the bridge over Cliffdale Road on newly opened section of I-295 South.


Image of I-295 South Mile Marker after Cliffdale Road bridge in Fayetteville, by David Johnson August 2020The new South I-295 mile marker after the Cliffdale Road bridge.


Image of I-295 South Reassurance Marker after Cliffdale Road exit in Fayetteville, by David Johnson August 2020The new South I-295 reassurance marker after the Cliffdale Road exit. Also in the distance a Speed Limit 65 sign.


Image of 1-Mile Advance ground mounted sign for US 401 exit on Outer Loop/I-295 South in Fayetteville, 
        by David Johnson August 2020The new 1-Mile advance sign for the US 401/Raeford Road exit on I-295 South, the new southern end of the Fayetteville Outer Loop.


Image of 1/2 Mile Advance ground mounted sign for US 401 exit on Outer Loop/I-295 South in Fayetteville, 
        by David Johnson August 2020The new 1/2 Mile advance sign for the US 401/Raeford Road, with the All Traffic Exit tab at the end of the Fayetteville Outer Loop.


Image of continued Loop construction approaching the US 401 exit on Outer Loop/I-295 South in Fayetteville, 
        by David Johnson August 2020Construction continues along I-295 approaching the US 401/Raeford Road exit at the last mile marker southbound.


Image of continued Loop construction in median approaching the US 401 exit on Outer Loop/I-295 South in Fayetteville, 
        by David Johnson August 2020Construction barrels help narrow the travel lanes approaching the current end of I-295 South at US 401/Raeford Road.


Image of continued Loop construction of future US 401 bridge on the Fayetteville Outer Loop/Future I-295 
        , by David Johnson August 2020Construction continues to complete the I-295 bridge over US 401/Raeford Road as part of the future extension of the Loop to Camden Road.


Image of Future I-295 bridge construction over US 401 from exit ramp at end of I-295 South in Fayetteville, 
        by David Johnson August 2020Construction of bridge for US 401/Raeford Road exit seen heading down exit ramp southbound.


Image of overhead US 401 ramp signs at end of I-295 South in Fayetteville, 
        by David Johnson August 2020Closeup view of overhead ramp signage approaching US 401/Raeford Road exit at the current end of I-295 South.


Image of Future I-295 bridge construction over Raeford Road at end of I-295 South in Fayetteville, 
        by David Johnson August 2020View of future bridge over US 401/Raeford Road from the end of the I-295 South exit ramp.


Image of Future I-295 bridge construction south of US 401/Raeford Road at end of ramp from I-295 South in Fayetteville, 
        by David Johnson August 2020View of future I-295 looking south from US 401/Raeford Road.


Image of Future I-295 bridge construction south of Raeford Road at end of I-295 South in Fayetteville, 
        by David Johnson August 2020Looking further south at future I-295 bridge structures under construction from US 401/Raeford Road.


Now turning around and heading back toward Cliffdale Road:

Image of Junction I-295 sign on US 401 South in Fayetteville approaching newly opened I-295 North interchange, 
                                     photo by David Johnson August 2020Approaching the new I-295 North ramp on US 401 South, a Junction I-295 sign awaits the opening of I-295 South.


Image of North I-295 overhead ramp sign on US 401 South in Fayetteville at opened interchange, 
                                     photo by David Johnson August 2020The overhead signs at the new I-295 North ramp from US 401 South.


Image of heading up ramp to I-295 North from US 401 South in Fayetteville, 
                                     photo by David Johnson August 2020Traveling the new 2-lane ramp to I-295 North from US 401 South.


Image of end of new ramp from US 401 South onto I-295 North in Fayetteville, 
                                     photo by David Johnson August 2020Approaching the end of the new I-295 North ramp from US 401 South with construction continuing of the unopened future highway to the left.


Image of merging onto newly opened North I-295 lanes from ramp from US 401 South in Fayetteville, 
                                     photo by David Johnson August 2020Merging onto the new I-295 North lanes, some work still needed to be completed along the right shoulder.


Image of Newly placed North I-295 reassurance marker following ramp from US 401 South in Fayetteville, 
                                     photo by David Johnson August 2020The new North I-295 reassurance marker followed by the Mile 13 Marker.


Image of 1-Mile advance ground mounted sign for Cliffdale Road exit on newly opened section of North 
        I-295 in Fayetteville, photo by David Johnson August 2020The 1-Mile advance sign for Cliffdale Road along I-295 North.


Image of Mile 14 marker before 1/2 Mile advance ground mounted sign for Cliffdale Road exit on newly opened section of North 
        I-295 in Fayetteville, photo by David Johnson August 2020The Mile 14 marker before the 1/2 mile advance sign for Cliffdale Road along I-295 North.


Image of travel lanes approaching Cliffdale Road on newly opened section of North 
        I-295 in Fayetteville, photo by David Johnson August 2020Heading into a curve before the Cliffdale Road exit along I-295 North.


Image of ground mounted exit sign for Cliffdale Road exit on newly opened section of North 
        I-295 in Fayetteville, photo by David Johnson August 2020The exit sign for Cliffdale Road, the former southern end of I-295.


Previous Photos

Photos taken heading north from Cliffdale Road on June 26, 2020 by David Johnson:

Image of North NC 295 trailblazer at ramp from Cliffdale Road, by David Johnson, June 2020A North NC 295 North trailblazer at the current beginning of the Fayetteville Outer Loop.


Image of future I-295 South ramp nearly completed to Cliffdale Road, by David Johnson, June 2020View of future I-295 North ramp to Cliffdale Road, next section is supposed to open by late 2020.


Image of NC 295 (Future I-295) North lanes after ramp from Cliffdale Road, by David Johnson, June 2020 Current NC 295 North lanes after merging from ramp from Cliffdale Road.


Image of first NC 295 reassurance marker and noise wall north of Cliffdale Road exit, by David Johnson 
        June 2020First North NC 295 reassurance marker placed before installed noise wall. This was removed in the spring of 2022 when the road was re-designated I-295, but was not replaced (The next one is still in place after the Canopy Lane exit, seen on a Street View image from November 2022).


Image of noise wall installed along NC 295 (Future I-295) North between Cliffdale Road and Canopy Lane in
        Fayetteville, by David Johnson June 2020More of one of the noise walls installed along NC 295 North through Fort Bragg.


Image of ground mounted 1/2 mile advance sign for Canopy Lane exit on NC 295 (Future I-295) North in 
        Fort Bragg, by David Johnson June 2020The 1/2 mile advance sign for the Canopy Lane exit.


Image of NC 295 North roadway in vicinity of Canopy Lane exit in Fort Bragg, by David Johnson June 2020 Fort Bragg related fencing can be seen along current NC 295 North approaching the Canopy Lane exit.


Image of Canopy Lane exit sign on NC 295(Future I-295) North in Fort Bragg, by David Johnson June 2020 The ground mounted exit sign for the Canopy Lane exit.


Image of gore sign and off-ramp from NC 295 (Future I-295) North roadway for Canopy Lane exit in Fort Bragg, by David Johnson June 2020 The gore sign and off-ramp for the Canopy Lane exit.


Image of noise wall along NC 295 (Future I-295) South roadway in Fort Bragg, by David Johnson June 2020 Another noise wall, this time along the NC 295 lanes after the Canopy Lane exit.


Image of overhead 1-Mile advancce sign for All American Freeway/Bragg Blvd exit with I-295 shield, by David Johnson June 2020 The 1-Mile Arrow-per-Lane (APL) advance sign for the All American Freeway/Bragg Blvd. exit features the first reference to I-295 North.


Image of overhead 1/2 Mile advancce sign for All American Freeway/Bragg Blvd exit with I-295 shield, by David Johnson June 2020 The 1/2 Mile Arrow-per-Lane (APL) advance sign with the same information, notice the blank space under the I-295 and I-95 shields, will text eventually go there?


Image of overhead ramp sign for All American Freeway/Bragg Blvd exit with I-295 shield, by David Johnson June 2020 The Arrow-per-Lane (APL) sign at the exit ramp, the C/D ramp continues all the way to the Murchison Road exit. This is the last overhead sign reference to I-295 North.


Image of flyover ramp to I-295 South from All American Freeway, by David Johnson June 2020 Looking at the beginning of the northbound C/D ramp and flyover ramp to I-295 South.


Image of overhead signage on I-295 North and along Bragg Blvd exit C/D ramp, by David Johnson June 2020 Overhead signage both along the mainline and the northbound C/D ramp from I-295 North.


Image of gore signage at split of ramps to Bragg Blvd and the All American Freeway from I-295 North, by David Johnson June 2020 Gore signage along the northbound C/D ramp at the split of ramps for the All-American Freeway and Bragg Blvd., from I-295 North.


Image of C/D ramps to Bragg Blvd and the All American Freeway crossing each other from I-295 North, by David Johnson June 2020 Two northbound C/D ramps crossing each other for the Bragg Blvd. exit, from I-295 North.


Image of I-295 North mile marker approaching Murchison Road exit, by David Johnson June 2020 First of 3 North I-295 mile markers between the Bragg Blvd. and Murchison Road exits, all were replaced by plain ones in 2022.


Image of ground mounted 1-Mile advance sign for Murchison Road exit on I-295 North in Fayetteville, by David Johnson June 2020 Closer view of the 1-Mile advance sign for the  Murchison Road exit (while NC 24/87 travel between Bragg Blvd. and Murchison Road along I-295 North, they never share the I-295 lanes.


Image of overhead signage along NC 24/87 C/D lanes approaching the Murchison Road exit along I-295 North in Fayetteville, by David Johnson June 2020 Overhead signage for the Murchison Road and Bragg Blvd. exits along the NC 24/87 C/D lanes.


Image of overhead APL signage along I-295 North C/D lanes with NC 295 North listed, by David Johnson June 2020 The overhead APL signage at the Murchison Road exit still has a NC 295 shield.


Image of signage along I-295 North referring it to the Airborne and Special Operations Highway, by David Johnson June 2020 Signage approaching the Murchison Road exit referring to the Fayetteville Outer Loop as the Airborne and Special Operations Highway.


Image of ground mounted signage along I-295 North for the Murchison Road exit and overhead ramp signage
        with a missing 295 shield, by David Johnson June 2020 Signage for the Murchison Road exit ramp while the C/D ramp signage is still missing a shield for the pull through part of the APL sign.


Image of the last North I-295 Mile marker after the Murchison Road exit, by David Johnson June 2020 This is the last mile marker heading north with an I-295 shield prior to the merge of the ramp from Murchison Road.


Image of the overhead 1-Mile advance sign for the McArthur Road exit on I-295 North, by David Johnson June 2020 The overhead 1-mile advance sign for the McArthur Road interchange on what is officially I-295 North.


Image of the ground mounted guide sign for Leaving Fort Bragg on I-295 North in Fayetteville, by David Johnson June 2020 The guide sign indicating you are now leaving Fort Bragg (no salutes are necessary) on I-295 North prior to McArthur Road.


Image of the overhead signs for the McArthur Road interchange on I-295 North in Fayetteville, by David Johnson June 2020 The overhead signs at the ramp to McArthur Road South.


Image of the guide sign for Fayetteville City Limit on I-295 North in Fayetteville, by David Johnson June 2020 A Fayetteville City Limit guide (warning?) sign after McArthur Road.


Image of the 1-Mile advance sign for the US 401 exit on I-295 North in Fayetteville, by David Johnson June 2020 The ground mounted 1-Mile advance sign for US 401.


Image of the ground mounted ramp sign for the US 401 exit on I-295 North in Fayetteville, by David Johnson June 2020 The exit sign at the ramp to US 401.


Image of North NC 295 mile marker on I-295 North in Fayetteville, by David Johnson June 2020 The first of the remaining mile markers which still list North NC 295.


Image of North NC 295 reassurance marker on I-295 North after US 401 exit, by David Johnson June 2020 The first of the remaining North NC 295 reassurance markers after the US 401 exit.


Image of ground mounted 1-Mile advance sign for River Road on I-295 North, by David Johnson June 2020 The 1-Mile advance sign for the River Road exit.


Image of ground mounted 1-Mile advance sign for I-95 exit on I-295 North, by David Johnson June 2020 The 1-Mile advance sign for the last exit for I-95.


Image of overhead signage at I-95 exit ramp on I-295 North, including end NC 295 trailblazer, by David Johnson June 2020 Overhead signs at the I-95 exit ramp, including a new End NC 295 trailblazer.


Image of overhead signage at I-95 exit ramp on I-295 North, by David Johnson June 2020 Closeup of overhead signs at the I-95 exit ramp.


Image of end NC 295 trailblazer at beginning of US 13 after I-95 exit ramp at end of I-295 North, by David Johnson June 2020 The other End NC 295 trailblazer at the beginning of US 13 North, no Begin banner however.


Photos taken of southern I-295 interchange construction from I-95 North on June 19, 2020 by David Johnson:

Image of conveyor belt across I-95 for future I-295 interchange construction near Hope Mills, by David 
        Johnson June 2020Wide angle view of conveyor belt system across I-95 to move dirt around future I-295 interchange area.


Image of dirt pile moved by conveyor belt across I-95 at future I-295 interchange near Hope Mills, by 
        David Johnson June 2020Dirt pile collected from conveyor belt across I-95 by southbound lanes.


View of conveyor belt for dirt being carried across I-95 from besides northbound lanes at site of 
        future I-295 interchange near Hope Mills, by David Johnson June 2020Other side of conveyor belt besides I-95 North lanes.


Image of future I-295 exit ramp bridge from I-95 North near Hope Mills, by David Johnson June 2020 Workers on top of new I-295 bridge being built over I-95 North.


Image of construction vehicles parked along graded future I-295 North lanes from I-95 North near Hope 
        Mills, taken by David Johnson June 2020Construction vehicles parked along graded future I-295 lanes along I-95 South.


Image of second ramp bridge being constructed over I-95 North lanes near Hope Mills for future I-295 
        interchange, by David Johnson June 2020View of the second I-295 bridge being built behind the first one from I-95 North.


Image of interchange construction for future I-295 Fayetteville Outer Loop along I-95 South lanes 
        near Hope Mills, by David Johnson June 2020Looking across the I-95 South lanes at grading of future I-295 lanes underway.


Image of future ramp bridge supports being placed along I-95 North for Future I-295 interchange near 
        Hope Mills, by David Johnson, June 2020Support being placed along I-95 North for future I-295 ramp.


Image of supports for future I-295 Fayetteville Outer Loop ramp bridge along I-95 South near Hope 
        Mills, by David Johnson June 2020More bridge supports, here along I-95 South.


Photos taken at the future southern I-95 interchange with I-295 on December 5, 2019 by DanTD:

Image of I-95 South approaching construction zone for Future I-295 interchange near St. Pauls, photo 
                                         posted to Wikimedia by DanTDView of I-95 South heading under bridge prior to I-295 interchange construction zone.


Image of concrete barrier along I-95 South separating traffic 
        from future ramp to I-295 North near St. Pauls, photo on Wikimedia by DanTDConcrete barrier separates I-95 South traffic from future ramp to I-295 North.


Image of Mile Marker 38 behind concrete barrier at Future I-295 interchange 
      construction zone near St. Pauls, photo on Wikimedia by DanTDMile Marker 38 along I-95 South at site of I-295 interchange construction, seeming to indicate that I-295 will be Exit 38.


Image of future flyover ramp bridge for I-295 North over I-95 South lanes 
        near St. Pauls, on Wikimedia by DanTDStart of flyover bridge construction to carry Future I-295 over I-95 South lanes.


Image of conveyor belt system over I-95 South lanes to carry excavated 
      material from Future I-295 interchange over highway, in Wikimedia by DanTDView from I-95 South of conveyor belt system aiding in removing dirt from interchange construction area.


Photos taken at the future southern I-95 interchange with I-295 in September 2019 by Adam Prince:

Image of traffic along I-95 South nearing Future I-295 interchange near St. Pauls NC, by Adam PrinceApproaching the construction area for the future I-295 interchange near St. Pauls.


Image of construction of Future I-295 interchange with I-95 near St Pauls, NC., by Adam PrinceContractors have cleared land alongside I-95 South for future interchange.


Image of conveyor belt built above I-95 lanes to carry dirt excavated for Future 
      I-295 interchange near St Pauls, NC., by Adam PrinceA conveyor belt system is being used to carry excavated dirt across the I-95 lanes as a more efficient method of construction than hundreds of truck trips.


Image of closer view of dirt conveyor belt built as part of southern I-295 interchange project with 
        I-95 near St. Pauls, NC, by Adam PrinceA closer view of the conveyor belt over I-95 South.


Image of construction zone for I-295 interchange near St. Pauls, NC from I-95 South, by Adam PrinceView of tree clearing for construction of the I-295 interchange on the other side of I-95.


Photos along opened sections of the Outer Loop (2005-2016)

Photos taken in August 2016 by Rob Adams:

Image of exit sign for NC 295 on I-95 South, showing new control city of Fort Bragg. Photo by Rob AdamsExit sign on I-95 showing designation as NC 295 and new control city of Fort Bragg, now accessible by Fayetteville Outer Loop. Sign still has NC 295 shield as of June 2020.


Image of new signs at beginning of NC 295 west along ramp from I-95 South. Photo by Rob AdamsOverhead signage along on-ramp from I-95 South showing NC 295 designation and new control city of Fort Bragg.


1 Mile Advance sign for US 401 exit, now with exit number 28 tab and All Traffic Must Exit tab removed.US 401 exit sign with new exit number tab (28) replacing former 'All Traffic Must Exit' tab.


Image of newly placed NC 295 South reassurance marker beyond US 401 exit in Spring Lake, photo by Rob AdamsNC 295 South reassurance marker. Sign plans indicated these were to be accompanied by Future I-295 signs (see sign plans below).


Image of NC 295 reassurance marker beyond McArthur Road exit on NC 295 South in Fayetteville, photo by Rob AdamsAnother reassurance marker beyond the McArthur Road exit showing noise barriers along Outer Loop corridor.


Image of 1-Mile Advance sign for NC 210/24/87 Murchison Road exit on NC 295 South in Fayetteville, photo by Rob Adams1 Mile Advance sign for Murchison Road exit on NC 295 South showing re-routing of NC 24 West/NC 87 North away from Bragg Blvd.


Image of 1-Mile Advance sign for Bragg Blvd/NC 24 East/NC 87 South exit on newly opened section of Fayetteville Outer Loop, photo by
        Rob AdamsOverhead signage at end of newly opened section showing signs for both Murchison Road and Bragg Blvd exits (the All American Fwy text should be covered over since the Loop will not extend that far until this December).


View signage for Bragg Blvd exit at current end of NC 295 South in Fayetteville, photo by Rob AdamsOverhead signage at current end of NC 295 at Bragg Blvd. Traffic uses the future C/D lanes to access Bragg Blvd.


Image of overhead signage along C/D lanes at current end of NC 295 Fayetteville Outer Loop at Bragg Blvd., photo by Rob AdamsSignage along the unfinished C/D ramp directing traffic to Bragg Blvd heading south.


Image of overhead guide signage along Bragg Blvd in Fayetteville now with NC 295 shield, photo by Rob AdamsPreviously placed guide signage along Bragg Blvd for Loop entrance ramp, now with NC 295 shield.


Image of overhead guide signage along Bragg Blvd for Fayetteville Outer Loop, now with NC 295 shield, from Rob AdamsAnother overhead guide sign on Bragg Blvd with newly placed NC 295 shield at the ramp itself.








Photo of overhead exit sign for NC 24/NC 87 with exit number on Fayetteville Loop. Photo by Lou CorsaroPREVIOUS PHOTOS

Overhead exit signage for NC 24/87 exit at the western end of Fayetteville Loop segment with NC 295 exit number in place. Work continuing the Loop to the All-American Freeway (to open in December 2016) and beyond can be seen in the distance.


Image of numbered exit gore sign on current western end of Fayetteville Outer Loop. Photo by Lou CorsaroCloser view of Exit Gore sign with Future 295 number at off-ramp to Bragg Blvd.


Image of overhead signage at bottom of ramp to Bragg Blvd from Fayetteville Loop westOverhead signs at the bottom of the ramp leading from the current western end of the Fayetteville Loop


Image of signage approaching Fayetteville Loop on Bragg Blvd. Photo by Lou CorsaroGuide signage approaching Fayetteville Loop on Bragg Blvd heading North with missing space for future NC 295 (and eventually I-295) shield.


Image of overhead signage for NC 24/87 at Fayetteville Loop on-ramp on Bragg Blvd. Photo by Lou CorsaroOverhead signage for NC 24/87 approaching entrance to the on-ramp for Future 295 North heading south on Bragg Blvd. The blank space on the left-hand sign is for an NC 295 shield.


Overhead guide signage for NC 24/NC 87 approaching Fayetteville Loop on NC 210. Photo by Lou CorsaroOverhead signage for West NC 24 and South NC 87 approaching Fayetteville Loop interchange on NC 210 North with missing NC 295 (future I-295) shield.


Image of NC 24/87 trailblazers before Fayetteville Loop overpass on Bragg Blvd. Photo by Lou CorsaroWest NC 24 and South NC 87 trailblazers approaching Fayetteville Loop overpass on NC 210 heading north under overpass.


Image of new NC 295 reassurance marker on Fayetteville Outer Loop taken by Dan Murphy 
2/5/15 South NC 295 reassurance marker beyond I-95 exit. By late 2014 all the Future I-295 shields were taken down on the Loop and at exit ramps and replaced with NC 295 signs (2/5/15). Courtesy of Dan Murphy.


Previously Taken Photographs 2005-2010

I-295 Fayetteville Outer Loop Sign Assembly-Eastern End.Original sign assembly at the then beginning of the Outer Loop at US 401, showing the future I-295 signage, none of the Future 295 shields had a directional banner. (Feb. 2005)


I-295 Fayetteville Outer Loop at Cape Fear River.View going eastbound just west of the US 401 interchange headed toward the bridge over the Cape Fear River. (Feb. 2005)


I-295 Fayetteville Outer Loop, River Road exit sign.View from the Cape Fear River bridge with the first sign for the River Road exit, where the Outer Loop ended before the next section was completed in July 2008. Notice the narrowness of the right and, particularly the left shoulders, which appear to not meet Interstate standards. (Feb. 2005) The exits did not have numbers, these were installed when the next section of the Loop to Bragg Blvd. was completed.


I-295 Fayetteville Outer Loop, River Road Shields.Then new signage at the Outer Loop interchange at River Road, the only previous marker at the ramp was a street sign listing Future 295 (July 2005).


I-295 Fayetteville Outer Loop, I-95 interchange signage, image by Adam 
Prince.Here's signage at the end of Northbound Future I-295 at the I-95 interchange. There is a high-speed flyover to I-95 North (Photo courtesy of Adam Prince).


I-295 Fayetteville Outer Loop, End Future 295 and Begin US 13 signs.An End 295/Begin US 13 sign at the eastern (northern) end of the Loop, beyond the I-95 interchange. (July 2005)


I-295 Fayetteville Outer Loop, US 401 exit signage, image by Adam Prince.Signage at the original end of the Loop going westbound (south) at US 401 (notice the 0 on the shield doesn't quite mix with the other numbers (photo courtesy of Adam Prince).


History of I-295 Route Number

NCDOT originally petitioned to have this roadway designated as I-195. The odd-number designation as an interstate spur route probably was chosen (at least as a temporary designation) because a funding source was not secured at the time to construct the entire 35-mile loop. The I-195 designation, however, was rejected by AASHTO in June 2003. Later in that year funds were secured to start planning to extend the route further south, making it a true loop back to I-95.10 NCDOT then decided the route should be called I-295 and this number subsequently appeared on several NCDOT publications.* AASHTO followed the FHWA's lead and approved the I-295 number designation at the May 6, 2005 meeting of the organization's Special Committee on U.S. Route Numbering (USRN).11

Though the Interstate 295 number was now official, NCDOT first signed the road as Future I-295. This was probably due to design aspects of the highway that do not meet interstate standards (such as the narrow shoulders on the Cape Fear River bridge (noted in the photo above) and the US 13 interchange (see photo below) which does not at present allow freeway to freeway access from I-95 North, nor as of 2020, allow traffic to take a left turn onto the Loop from I-95 North, traffic must take a right and turn around at the next intersection. The upcoming I-95 widening project in the area includes a reconstruction of the interchange to include a new ramp from I-95 North which will take traffic over US 13 and then to the current I-295 North flyover ramp where I-295 south traffic would take another ramp back over I-95 to meet a new ramp from I-95 South, from the I-95 project documents in May 2020 (a considerable alteration from a former flyover ramp design from I-95 North to I-295 South):

NCDOT plan for reconstructed interchange between I-95 and I-295 north of Fayetteville, May 2020

Despite this, NCDOT insisted that when the route was completed to US 401, it would be signed as I-295. However, in May 2014 NCDOT released plans for the final contract needed to complete the loop to the All-American freeway. Apparently, the FHWA, either due to the design aspects, or because funding was incomplete to build the entire 34 mile loop, indicated they could not approve the interstate designation. The sign plans now had the route signed as NC 295, even where earlier plans had shown I-295 signs (see below). By the end of 2014 NCDOT had changed all Future 295 signage between I-95 and US 401 to NC 295, including on the exit sign on I-95.12 NCDOT had plans, however, to post Future I-295 signs alongside the NC 295 signs on the Loop when the route to the All American Freeway was completed, perhaps indicating the NCDOT belief that the FHWA decision will change later on. However, those signed were never posted, as shown in the photos above.13

NCDOT Asks for I-295, Again

In September 2018, the AASHTO USRN published applications for its upcoming Fall Meeting in October. Among the 3 from NCDOT were two asking that the existing NC 295 from I-95 to the All American Freeway be signed as I-295 and for the rest of the route, currently under construction, to be designated as Future I-295.14 The I-295 application mentions the previous approval of the Future I-295 designation, that the route is up to Interstate Standards, and provides an important link between Fort Bragg and I-95. The Interstate Standards reference is questionable, as cited above due to both the bridge over the Cape Fear River and the interchange with I-95 that includes stop signs and left turns, and now a redesigned ramp from I-95 North which makes traffic heading for NC 295 South to take a right on US 13 then make a U-Turn. The application also implies that AASHTO never asked that the previous Future I-295 signs be removed, meaning it was either the FHWA or NCDOT itself. On September 20, AASHTO approved the application, no concurrence by the FHWA required (the NCDOT application stated the FHWA had given a favorable opinion on the addition of the route to the interstate system back in 2003). In May 2019, the FHWA added I-295 to its official Auxiliary Interstate Route log.15 In November 2019, NCDOT put up I-295 shields along the I-95 to All-American Freeway section after the section to Cliffdale Road.15 On April 21, 2020, NCDOT posted a route change memorandum indicating NC 295 was officially to be signed along the Loop south of Cliffdale Road, indicating the approval came way back in August 2019. The document included a map implying the remainder north to I-95 is signed I-295, but it is unknown whether though the interstate shields have gone up on this section of the Loop, a press release issued in June 2020 stated NC 295 ran from Cliffdale Road to I-95.16 On April 21, 2020, NCDOT officially released a route change ordinance document stating that NC 295 ran from the All-American Freeway south to Cliffdale Road.17 However, when the section opened between Cliffdale Road and Raeford Road/US 401 in August 2020, NCDOT signed the route as I-295 and stated the earlier section between the All-American Freeway and Cliffdale Road would be signed as I-295 as well. The remaining NC 295 signs were to be replaced by I-295 shields 'eventually' at an unknown future date.2 On July 14, 2021, NCDOT announced a contract had been approved that would re-sign the Loop from I-95 to the All-American Freeway as I-295 using shield overlays on existing signs (see sign plans below). The contractor could start work in August and had to be complete by March 2022. It appeared all signs were up by mid-April, with some exceptions (see photos).6

* Though several other route numbers appear for the Loop on other documents. The official 2005 state highway map listed it as NC 13. NCDOT called the route the 'NC 24 extension' on its contract listing for the US 301 to I-95 section in previous TIP documents.

I-295 Fayetteville Outer Loop, NC state map image. Here's Future I-295's first appearance on a map, the 2006 North Carolina State Transportation Map, that is. In anticipation of the current 'demotion' of the route to NC 295, that designation appeared on the Loop on the 2013-2014 state map.


This photo shows that traffic coming from I-95 south must take a left turn crossing the west- (south) bound Loop. (courtesy of Adam Prince)











Details on Construction of Completed Segments

Before the budget problems cropped up construction of the next section from US 401 to the Bragg Blvd. was scheduled to start in late 2008. With the passage of the economic stimulus bill in February 2009, NCDOT got $385 million for highway construction, the project was then split up into three contracts: X-0002BC, X-0002CA, and X-0002CB. Only one of which qualified as a 'shovel-ready' project and could start using the stimulus funds. Construction was started on a 1.5 mile (2.5 km) section from west of Bragg Blvd. to Murchison Road in July 2009. This section is separated from the completed section east of US 421 by 3 miles and was completed in 2013.1 This project did not include, however, final paving, structures, and signing which were let in a separate contract in October 2012. Work started in January 2013 and the segment was opened on Monday, August 4, 2016.4

The next part of the project was at the western end, 1/2 mile from Bragg Blvd. to the All-American Freeway, started in the fall of 2009. This project, like that between US 401 and NC 210, was meant only to build the highway to a graded surface. Paving of this part of the highway and the building of the remainder east from Murchison Road to connect to US 401 was put off until this project was completed in March 2014.19 The paving contract (C203361) was let on June 17, 2014, with work starting on August 25, 2014. Work was completed in December 2016.20 Work also started on a small (about 1.2 mile or 1.9 km) segment of the Loop (Contract C202829) west of the All American Freeway in November 2011. This segment will extend the Loop to just east of Yadkin Road and, was completed by December 2015, since there was no interchange on the south end of this project, it was not opened until the Cliffdale Road segments was completed to the south.21

Signage Plans (Updated 4/20/22)

Here are some of the signs that have been posted, or were planned to be posted, along the future length of the Fayetteville Outer Loop.

From US 401 south to I-95. The section from Camden Road to I-95 will be completed first and signed temporarily as NC 295. Sign plans for the Camden Road to US 401 section indicate the shields will be changed to I-295 when completed:

Image of NCDOT sign plan for overhead signs on I-295 North at ramp to Strickland Bridge RoadSigns on I-295 North at the exit ramp for Strickland Bridge Road.


Image of NCDOT sign plan for exit ramp sign for Camden Road to be built as last part of
        Fayetteville Outer LoopPlan for Camden Road exit sign along I-295 South.


Image of NCDOT sign plan for exit sign for Black Bridge Road on under construction
        section from Camden Road to I-95Plans for mile marker switch on I-295 South and exit sign for Black Bridge Road.


Image of NCDOT sign plan for overhead sign at split of ramps at end of I-295 South
        at I-95Plans for overhead sign at split of ramps for I-95 North and South at end of I-295 South. Only I-95 South will get an exit number.


Image of NCDOT sign plan for overhead APL sign on I-95 North showing future replacement of
        NC 295 shield with I-295Plans for overhead APL sign on I-95 North showing eventual NC 295 shield replacement with I-295 when entire loop is complete.


Signing the Loop as I-295

After almost 4 years since the 2018 approval of the I-295 designation for the entire Loop, I-295 shields have replaced NC 295 ones on existing exit and ramp signs. Here are the plans for the contract that was completed in April 2022:

Image of NCDOT sign plan with new I-295 shield overlay for Fayetteville Loop 
      exit on I-95 in Cumberland County, June 2019Here is the latest plan for placing an I-295 shield over the existing NC 295 shield for the exit signs on I-95.


Image of NCDOT sign plan for new I-295 trailblazer for Fayetteville 
      Loop exit on I-95 in Cumberland County, June 2019Here is the plan for placing new I-295 shields at the ramps for the River Road exit.


Image of NCDOT sign plan for new I-295 signage at US 40 exit on Fayetteville 
      Outer Loop in Cumberland County, June 2019Here is the plan for placing new I-295 shields on existing signage at the on-ramps at US 401.


Image of NCDOT sign plan for new I-295 trailblazer for Fayetteville 
      Loop exit on I-95 in Cumberland County, June 2019Here is the plan for placing new I-295 shields along the C/D ramps for the Murchison Road exit.


Image of plan of signage at the Bragg Blvd exit on the Fayetteville Loop, from NCDOTHere is a 2020 plan for the exit signage along I-295 at the Bragg Blvd. exit for I-295 South and All-American Freeway. .


Image of plan of signage on the All American Freeway for the Fayetteville Loop, from NCDOT Here is a 2020 plan for the exit signage for I-295 on the All-American Freeway. Notice, like the previous 2013 plan I posted the reference to a future official exit number. NCDOT has been petitioned to designate the All-American Freeway as NC 555 back in 2014, but this number was never approved.




Exit signage plan for Fayetteville Outer Loop, from NCDOTHere was the original plan for signage at the end of the Bragg Blvd-Murchison Road segment, with then planned I-295 North sign.




New 2019 Sign plan for Fayetteville Loop section at Murchison Road interchange, from NCDOTThis is the new plan at Murchison Road from August 2019.


New signage plan for Murchison Road interchange on Fayetteville Outer Loop, from NCDOTHere was the previous signage plan for the same area with the change from I to NC 295 in 2014.


Image of sign plan for updating mile marker 21 on Fayetteville Outer Loop in August 2021, from NCDOT Plan for how mile markers will also be updated by overlaying small I-295 shields over the NC 295 ones.


Image of sign plan for Bragg Blvd exit on Fayetteville Loop, from NCDOTThe previous plan for signage at the Bragg Blvd interchange. Note the future planned placement of an I-295 South pull-through sign.


New signage plan for Fayetteville Outer Loop at the All-American
  Freeway, from NCDOTHere was the previous plan for signage for the All-American Freeway with the then new NC 295 designation.


Image of sign plan for reassurance markers along the Fayetteville Outer Loopm from NCDOTHere was the planned signage for the Loop itself in 2014, NC 295 reassurance markers were to be paired with Future I-295 signs. These signs were never put up.


Current Construction (Updated 7/10/24)

Until late 2011 construction on the rest of the Loop, even with a continued significant proportion ($258 million, 19% for current construction) of highway trust fund moneys available,4 was to be a decade or more away.21 However, in the fall of 2011 the NC government announced its intention of funding construction of additional priority highways, which would include I-295.  One of two segments under construction in mid-2020, from Cliffdale Road to US 401 was started under a design-build contract awarded to Barnhill Contracting Co. in August 2016, work included replacement of an existing bridge over Bones Creek. NCDOT indicated in June 2019 that the route will be open by the fall of 2020,22 but work ground to a halt during the second half of 2019. Work resumed in early 2020 and was completed 3 months ahead of schedule in August 2020. Meanwhile, NCDOT announced the $129.7 million contract to build the segment from Camden Road to I-95 in December 2017. Work started on January 2, 2018 and was originally planned to be completed by June 2022, it includes interchanges at Parkton Road and Black Bridge Road. As of the end of March 2022 the project was listed as 85.6% complete, however a month later at the end of April it was listed only as 53.5%. This apparently was not a typo, since the numbers were not changed afterwards. Something again must have happened to increase the cost and scope of the project. Something similar happened in the spring of 2021, when the % complete went down by about 20% in month, but the percentage number went back up above 80% by the end of the year. At the end of July 2024 the project finally got back to its early 2022 completion levels, listed as 89.7% complete.23 The completion date was moved in early 2021 to December 2024, and in early 2023 to July 2025. However, a 2-mile section from Parkton Road at the Robeson/Cumberland County border to Black Bridge Road was opened on November 21, 2022.24 In August 2023, in a news release about a street closure related to completing the Camden Road interchange, NCDOT indicated that the section south of Camden Road to I-95 could open by mid-2024.25 The route was opened on July 10, 2024, offering drivers a direct ride from Camden Road to I-95 South. The connection to I-95 North, however, along with the connections from I-95 to the Loop are currently not scheduled to open until the I-95 widening project is completed in the summer of 2025.26

Earlier, Google Maps in April 2024 added the entire completed section (including unopened lanes north to Waldo's Beach Road and south to I-95) though it's erroneously labeled as Garrison Drive not NC 295:

Google Maps image of completed section of Future I-295 Fayetteville Outer Loop, 
                                                     both open and unopened to traffic posted online in April 2023

Drivers on I-95 started to notice in late summer 2019 a conveyor belt being built over the roadway. This carried dirt being excavated for the I-295 interchange across to the east side of the interstate where it was carried elsewhere until late 2021, preventing over 100,000 truck trips that would have been needed to do the same job.27 (Photos of construction in this area can be found here). As for the remaining segment from US 401/Raeford Road to Camden Road, a news article from early March 2022 indicated a small section south of Raeford Road to near Century Circle would open during the summer, though there's no interchange at that location.28 The contract for the remaining part of the segment to just south of Camden Road, as indicated in the table at the top of the page, was to be let in January 2019, however, due to litigation over Right-of-Way issues this was delayed until May. In December 2018, NCDOT decided to split the contract with the northern segment (TIP U-2519BB) between US 401 and Strickland Road to be let in May 2019 and the remainder between Strickland Road and Camden Road (TIP U-2519BA) to be let in October 2019, dubbing it a 'strategic letting'.29 However, in April 2019, the projects disappeared completely from the 12-Month Tentative Letting List, no reason given. The project later appeared in the August 2019 to July 2020 list for July 2020. This delay pushed back the original NCDOT timeline, which would probably have meant completion by the end of 2023. As indicated above, this project was suspended due to COVID-19 related financial issues in the spring of 2020. The press release about the opening of the Cliffdale Road to Raeford Road section indicated the project was now to be let in August 2022.2 Since that time, however, both parts of the project has been accelerated to be let in June 2022. NCDOT advertised the availability of the project on April 19, 2022 and announced on July 8 that he project would be awarded to Branch Civil Inc. of Roanoke, Virginia for $152 million.The project will build the interchange with Camden Road plus one at Strickland Bridge Road. Work started in August 2022 and as of July 27, 2024 is is over 1/2 complete at 51.9%.30 NCDOT announced on August 27, 2024 that work would soon start on building the last interchange for the Loop at Strickland Bridge Road.31 Work is officially scheduled to be completed in early 2027, however the NCDOT press release announcing the opening of the Camden Road to I-95 segment in July 2024 indicated it could open as early as spring 2026.26

The proposed path and potential interchanges for the to be built sections are in the map below:5

NCDOT construction timetable for the Fayetteville Loop in Dec. 2015

The plans for the US 401 to Murchison Road section indicated the route will become full I-295 upon the project's completion and also listed exit numbers that will be placed at all interchanges from the vicinity of Bragg Blvd back to I-95. The 2014 project plans indicated though that the route would be signed as NC 295 and slightly altered the exit numbers. Exit numbers appeared on the segment between Bragg Blvd. and Murchison Road by December 2015. The remaining exit numbers were installed after the segment from US 401 to Murchison Road opened on August 11, 2016.

I-295 EXIT LIST

Exit numbers, including for the now opened section from Camden Road to I-95 South, going south to north.12

I-295 I-95 exit plan from Sign Maker









I-295 River Road exit sign, from Sign Maker







I-295 US 401 exit sign, from Sign Maker








I-295 McArthur Road exits sign, from Sign Maker







I-295 NC 210 Murchison Road exit sign, from Sign Maker








I-295 NC 24 NC 27 exit sign, from Sign Maker







**


I-295 Canopy Lane exit sign from Sign Maker









I-295 Cliffdale Road exit sign image, by SignMaker









I-295 US 401 Raeford Road exit sign image, by SignMaker

*Partially open SB








I-295 Strickland Bridge Road exit sign image, by SignMaker

*







I-295 Camden Road exit sign image, by SignMaker

*(Partially Opened NB in July 2024)









I-295 Black Bridge Road exit sign image, by SignMaker















I-295 Parkton Road exit sign image, by Signmaker

















I-295 I-95 North exit sign image, by SignMaker

*(Ramp to I-95 South opened on 7/10/24)








*Not Completed Exits as of July 2024

**Fort Bragg became Fort Liberty in 2023, the City of Fayetteville is currently discussing a name change for Bragg Blvd.