Massachusetts
Highway Sign Replacement Contract List through 2027
Current Projects
as of February 14, 2025
Route
Where
Percent Complete
Completion Date
Attleboro to Norwood
100%
Autumn
2021*
[Installation of all overhead signs not complete**]
Worcester to Leominster
100%
Autumn 2024*
[Work
completed-2/1/25]1
Dartmouth to Wareham
14%
Autumn 2025
[Sign shop drawings being submitted-11/1/24]
Wareham to Raynham
10%
Summer 2026
[Sign foundation installation continuing-2/11/25]
Braintree to Plymouth
0%
Spring 2026
[Notice to Proceed given on 2/11/25]
Peabody to Gloucester
5%
Autumn
2025
[Work continues- 12/1/24]
*Project continues (will continue) after original estimated date of
completion, MassDOT Project listings no longer include a projected
completion date as of July 2021.
**Despite MassDOT listing as project complete, two 1/2 mile advance
signs for the I-495 exit have not been installed as of 8/16/24.
1. ProjectInfo
site states completion, will confirm in future road trip.
2. Work
completed, photos of installed signs available at my Misc.
Mass. Road Signs Gallery:
Future Projects
Route
Where
To be Let in
/
Central Artery/Tunnel
System Spring 2026
Springfield to Chicopee
Spring 2026 (was Summer 2025)
Auburn to
Webster
2027*
Harvard
to Concord
Spring 2026 (Was Summer 2025)
Templeton
to Lancaster
2027*
West
Springfield to Agawam
2027*
Freetown to Taunton
Summer 2025 (Was Spring
2025) [25% package received-10/25/24]
Uxbridge to Worcester
Spring 2025 [Project Advertised-2/8/25]
Methuen
2027*
*New MassDOT Project listing containing no date for start of
construction, assuming 2027 or later since only projects up through FY
2026 have years listed.
Notes:
Information current as of February 14, 2025 obtained from MassDOT Project
Listings (ProjectInfo) for Structural Signing contracts under
construction or design, downloaded from:
https://www.mass.gov/service-details/massdot-project-info
For sign projects
planned between 2016 and 2020, MassDOT had contractors install exit tabs
and gore signs that can fit future milepost based numbers. MassDOT then
renumbered these exits to the milepost system under 3 contracts from
October 2020 to August 2021.