Massachusetts
Highway Sign Replacement Contract List through 2027
Current Projects
as of September 1, 2023
Route
Where
Percent Complete**
Completion Date
Attleboro to Norwood
100%
Fall
2021*
[Installation of all overhead signs not complete***]
Reading to Lynnfield
90%
Spring 2022*
['Completed'****-6/18/23]
Lynnfield to Danvers
100%
Summer 2023
['Completed'-9/1/23]
Worcester to Leominster
6%
Autumn
2024
[Work continues-9/1/23]
Attleborough to N. Attleborough 0%
Spring 2024
[Notice to Proceed given-4/13/23]
Chelsea to
Danvers
60%
Autumn 2021*
[D and G type signs being
installed-8/14/23]
Burlington to
Tyngsborough 31%
Spring 2023*
[Sign foundation work
continues-7/26/23]
Wareham to
Bourne
0%
Spring 2024
[Notice to Proceed
given-3/24/23]
*Project continues (will continue) after original estimated date of
completion, MassDOT Project listings no longer include a completion date
as of July 2021.
**In March 2023, MassDOT mistakenly recategorized all under construction
sign contracts in the ProjectInfo site as '100% Complete'. The % listed
currently based on those numbers given previously. [While this was
corrected in May some recently started projects are still listed as
complete.]
***Despite MassDOT listing as project complete, two 1/2 mile advance
signs for the I-495 exit have not been installed as of 3/12/23 as well as
a new sign for the I-495 exit on I-95 South that was knocked down soon
after installation.
****As of June 2023 the project page lists the work as completed,
however there are still 5 signs that have yet to be placed as of 6/18/23.
Future Projects
Route
Where
To be Let in
/
Central Artery/Tunnel
System Spring 2026
Dartmouth to
Wareham
Summer 2024 (Was 2027)
Springfield to Chicopee
Spring 2026 (was Summer 2025)
Auburn to
Webster
2027*
Wareham to Raynham
Summer 2024 (Was 2027)
Harvard
to Concord
Spring 2026 (Was Summer 2025)
Braintree to Plymouth
Spring 2025
West
Springfield to Agawam
2027*
Peabody to Gloucester
Summer 2024 (Was Fall 2023)
Freetown to Taunton
Spring 2025
Uxbridge to Worcester
Spring 2025 (was Fall 2020)
*New MassDOT Project listing containing no date for start of
construction, assuming 2027 since projects up through 2026 have years
listed.
Notes:
Information current as of September 1, 2023 obtained from MassDOT
Project Listings (ProjectInfo) for Structural Signing contracts under
construction or design, downloaded from:
https://www.mass.gov/service-details/massdot-project-info
For sign projects
planned between 2016 and 2020, MassDOT had contractors install exit tabs
and gore signs that can fit future milepost based numbers. MassDOT then
renumbered these exits to the milepost system under 3 contracts from
October 2020 to August 2021.