Massachusetts
Highway Sign Replacement Contract List through 2028
Current Projects as of September 18, 2026
Route
Where
Percent Complete
Completion Date
Springfield to Chicopee
0%
Autumn 2028
[Notice to Proceed Given - 8/11/26]
Burlington to Reading
1%
Autumn 2027
[Work Started 7/1/26]
Attleboro to Norwood
100%
Autumn 2021*
[Installation of all overhead signs not complete**]
Wareham to Raynham
100%**
Summer 2026
[Overhead Sign Work Continuing -8/5/26]
Harvard to Concord
0%
Summer 2028
[Notice to Proceed - 8/28/26]
Braintree to Plymouth
45%
Summer 2026
[Overhead Sign Installation Restarted, New Signs installed SB to at least Exit 36-9/18/26]
Peabody to Gloucester
93%
Spring 2026*
[Overhead sign work continues- 9/15/26]
Freetown to Taunton
15%
Autumn 2026
[Concrete Foundation Work Completed-9/7/26]
Uxbridge to Worcester
33%
2027
[Work Continues-8/1/26]
Methuen
7%
2027
[Construction Continues-8/1/26]
*Project continues (will continue) after original estimated date of
completion, MassDOT Project listings no longer include a projected completion date as of July 2021.
**MassDOT listed project as complete between April and June 2026.
1. ProjectInfo site states completion, will confirm in future
road trip.
2. Work
completed, photos of installed signs available at my Misc.
Mass. Road Signs Gallery:
Future Projects
Route
Where
To be Let in (or FY*)
/
Central Artery/Tunnel
System Spring 2027 (Was Spring 2026)
Auburn to Webster
Summer 2027 (Was Spring 2027)
Lincoln
to Arlington
Spring 2027 [75% Package Received 5/18/26]
Fitchburg
to Lancaster
Spring 2028
West Springfield to Agawam
Summer 2027 (Was Spring 2027)
*For those having no official date for start of construction.
**Unofficially, to be confirmed by road trip at later date.
Notes:
Information current as of September 18, 2026 obtained from MassDOT Project Listings (ProjectInfo) for Structural Signing
contracts under construction or design, downloaded from: https://www.mass.gov/service-details/massdot-project-info